Damages for delay. If COD for the Project does not occur on the Scheduled Completion Date unless the delay is due to Force Majeure, the Concessionaire shall pay additional fees to Maha-Metro amounting to Rs. 2.00
Appears in 6 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Damages for delay. If COD for the Project does not occur on the Scheduled Completion Date unless the delay is due to Force Majeure, the Concessionaire shall pay additional fees to Maha-Metro amounting to Rs. 2.005.00
Appears in 4 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement