Common use of DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION Clause in Contracts

DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. The number of calendar days available to the Contractor to substantially complete the Work is the Contract Time. The date of commencement of the Work shall be the date of this Agreement unless otherwise indicated below. The Contractor shall substantially complete the Work, no later than « » ( « » ) calendar days from the date of commencement, subject to adjustment as provided in Article 10 and Article 11. « »

Appears in 2 contracts

Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

AutoNDA by SimpleDocs

DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. The number of calendar days available to the Contractor to substantially complete the Work is the Contract Time. The date of commencement of the Work work shall be May 18, 2020 or ten (10) working days after the Owner provides a list of all meters being changed, whichever date of this Agreement unless otherwise indicated belowis later. The Contractor shall substantially complete the Work, no Work not later than « » ( « » (120) calendar days from the date of commencement, subject to adjustment as provided in Article 10 9 and Article 11. « »10.

Appears in 1 contract

Samples: Contract Agreement

DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. The number of calendar days available to the Contractor to substantially complete the Work is the Contract Time. The date of commencement of the Work shall be the date of this Agreement unless otherwise indicated below. The Contractor shall substantially complete the Work, no later than « » Thirty ( « » 30 ) calendar days from the date of commencement, subject to adjustment as provided in Article 10 and Article 11. « »

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. The number of calendar days available to the Contractor to substantially complete the Work is the Contract Time. The date of commencement of the Work shall be the date of the issuance of a Purchase Ord this Agreement unless otherwise indicated below. The Contractor shall substantially complete the Work, no later than « » ( « » ) calendar days from the date of commencement, subject to adjustment as provided in Article 10 and Article 11. « »or he Contract Time.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

AutoNDA by SimpleDocs

DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. The number of calendar days available to the Contractor to substantially complete the Work is the Contract Time. The date of commencement of the Work shall be the date of this Agreement unless otherwise indicated below. The Contractor shall substantially complete the Work, no later than « » ( « » ) calendar days from the date of commencementMarch 31st 2015, subject to adjustment as provided in Article 10 and Article 11. « ».

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. The number of calendar days available to the Contractor to substantially complete the Work is the Contract Time. The date of commencement of the Work shall be the date of this Agreement unless otherwise indicated below. The Contractor shall substantially complete the Work, no later than « » ( « » ) calendar days from the date of commencement, subject to adjustment as provided in Article 10 and Article 11. « ».

Appears in 1 contract

Samples: Construction Contract