Decisions of the Project Representative. 13.1 The Project Representative shall, within a reasonable time, make decisions on all claims of the Town or the Contractor and on all other matters relating to the execution and progress of the structural work or the interpretation of the Contract Documents. 13.2 The Project Representatives decision in matters relating to the project, shall he final, if within the terms of the Contract Documents. 13.3 If, however, the Project Representative fails to render a decision, within ten (10) days after the parties have presented their evidence, either party may then avail itself of the remedies provided in this contract or available to it by law. If the Project Representative renders a decision after such remedies have commenced, such decision may be entered as evidence but shall not disturb or interrupt such proceedings except where such decisions is acceptable to the parties concerned.
Appears in 4 contracts
Samples: Contract for the Procurement of Services, Contract for the Procurement of Services, Contract
Decisions of the Project Representative. 13.1 13.1. The Project Representative shall, within a reasonable time, make decisions on all claims of the Town or the Contractor and on all other matters relating to the execution and progress of the structural work or the interpretation of the Contract Documents.
13.2 13.2. The Project Representatives decision Representative’s decision, in matters relating to the project, shall he be final, if within the terms of the Contract Documents.
13.3 13.3. If, however, the Project Representative fails to render a decision, decision within ten (10) days after the parties have presented their evidence, either party may then avail itself of the remedies provided in this contract Contract or available to it by law. If the Project Representative renders a decision after such remedies have commenced, such decision may be entered as evidence but shall not disturb or interrupt such proceedings except where such decisions decision is acceptable to the parties concerned.
Appears in 2 contracts
Samples: Contract for Burner Service and Boiler Cleaning, Contract for Fire Alarm Maintenance and Inspections
Decisions of the Project Representative. 13.1 The Project Representative shall, within a reasonable time, make decisions on all claims of the Town or the Contractor and on all other matters relating to the execution and progress of the structural work or the interpretation of the Contract Documents.
13.2 The Project Representatives decision in matters relating to the project, shall he be final, if within the terms of the Contract Documents.
13.3 If, however, the Project Representative fails to render a decision, within ten (10) days after the parties have presented their evidence, either party may then avail itself of the remedies provided in this contract or available to it by law. If the Project Representative renders a decision after such remedies have commenced, such decision may be entered as evidence but shall not disturb or interrupt such proceedings except where such decisions is acceptable to the parties concerned.
Appears in 1 contract
Samples: Contract Agreement