Definition of Ameritech Make Ready Work. Ameritech Make Ready Work: (a) is any work that is required to be performed by Ameritech to make poles ready for CLEC’s attachment. (b) does not include any work regarding the facilities or attachments of other parties with attachment to the pole necessary to accommodate CLEC’s attachment. The following applies: (a) When CLEC is allowed to perform certain Make Ready work, all standards and conditions specified in section 7.9 will be followed. (b) CLEC will not be allowed to perform certain Make Ready Work that is required to be performed by Ameritech employees pursuant to Ameritech collective bargaining agreements, work rules and policies. If CLEC is denied the ability to perform certain Make Ready Work, Ameritech will address the reason for such denial on a case-by-case basis.
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Definition of Ameritech Make Ready Work. Ameritech Make Ready Work:
(a) is any work that is required to be performed by Ameritech to make poles ready for CLEC’s attachment.
(b) does not include any work regarding the facilities or attachments of other parties with attachment to the pole necessary to accommodate accommo date CLEC’s attachment. The following applies:
(a) When CLEC is allowed to perform certain Make Ready work, all standards and conditions specified in section 7.9 will be followed.
(b) CLEC will not be allowed to perform certain Make Ready Work that is required to be performed by Ameritech employees pursuant to Ameritech collective bargaining agreements, work rules and policies. If CLEC is denied the ability to perform certain Make Ready Work, Ameritech will address the reason for such denial on a case-by-case basis.
Appears in 1 contract