Definition of Substantial Completion. The Premises shall be treated as having been substantially completed (and ready for occupancy for the purposes of Section 2.4 of the Lease) on the later of: (a) The date on which Landlord’s Work, together with common facilities for access and services to the Premises, has been completed (or would have been completed except for Tenant Delay) except for items of work and adjustment of equipment and fixtures which can be completed after occupancy has been taken without causing substantial interference with Tenant’s use of the Premises (i.e. so-called “punch list” items), or (b) The date when permission has been obtained from the applicable governmental authority, to the extent required by law, for occupancy by Tenant of the Premises for the Permitted Use, unless the failure to obtain such permission is due to a Tenant Delay. In the event of any dispute as to the date on which Landlord’s Work has been completed, the reasonable determination of Landlord’s architect as to such date shall be deemed conclusive and binding on both Landlord and Tenant.
Appears in 4 contracts
Samples: Lease (Inotek Pharmaceuticals Corp), Lease Agreement (Radius Health, Inc.), Lease Agreement (Flexion Therapeutics Inc)
Definition of Substantial Completion. The Premises shall be treated as having been substantially completed (and ready for occupancy delivered to Tenant for the purposes of Section 2.4 3.1 of the Lease) on the later of:
(a) The date on which LandlordXxxxxxxx’s Work, together with common facilities for access and services to the Premises, has been completed (or would have been completed except for Tenant Delay) except for items of work and adjustment of equipment and fixtures which can be completed after occupancy has been taken without causing substantial interference with TenantXxxxxx’s use of the Premises (i.e. so-called “punch list” items), or
(b) The date when permission has been obtained from the applicable governmental authority, to the extent required by law, for occupancy by Tenant of the Premises for the Permitted Use, unless the failure to obtain such permission is due to a Tenant Delay. In the event of any dispute as to the date on which Landlord’s Work has been completed, the reasonable good faith determination of Landlord’s architect as to such date shall be deemed conclusive and binding on both Landlord and Tenant.
Appears in 1 contract
Definition of Substantial Completion. The Premises shall be treated as having been substantially completed (and ready for occupancy for the purposes of Section 2.4 of the Lease) on the later of:
(a) The date on which Landlord’s Work, together with common facilities for access and services to the Premises, has been completed (or would have been completed except for Tenant Delay) except for items of work and adjustment of equipment and fixtures which can be completed after occupancy has been taken without causing substantial material interference with Tenant’s use of the Premises (i.e. so-called “punch list” items), or
(b) The date when permission has been obtained from the applicable governmental authority, to the extent required by law, for occupancy by Tenant of the Premises for the Permitted Use, unless the failure to obtain such permission is due to a Tenant Delay. In the event of any dispute as to the date on which Landlord’s Work has been completed, the reasonable determination of Landlord’s architect as to such date shall be deemed conclusive and binding on both Landlord and Tenant.
Appears in 1 contract