Delay Event. (a) Upon a Delay Event the Planned Availability Date will be extended by the addition of a period equal to the duration of the Critical Delay insofar as the Contractor is not required to make up for this Critical Delay by applying paragraph (b). The Contractor must adapt the Project Planning accordingly.
Appears in 2 contracts
Samples: Rijkswaterstaat DBFM Agreement, Rijkswaterstaat DBFM Agreement
Delay Event. (a) Upon If a Delay Event occurs, the Planned Scheduled Availability Date will be extended by the addition of a period equal to the duration of the Critical Delay Delay, insofar as the Contractor is not required to make up for this Critical Delay by applying paragraph Paragraph (b). The Contractor must adapt the Project Planning accordingly.
Appears in 2 contracts
Samples: Model Dbfmo Agreement, www.government.nl