Common use of Delay in NTP1 Clause in Contracts

Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 8 contracts

Samples: Design Build Agreement, Professional Services Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:: “Δ“ is the adjustment amount;

Appears in 5 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 4 contracts

Samples: Development Agreement, Development Agreement, Development Agreement

Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 4 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 3 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 90 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 3 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 3 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.1. 12.1.3.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 181 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding or subtracting the product of the following (which amount may not be less than zero) to from the Price: where: Δ = N * (Price) * (([A-B]/B)/T) where:“Δ” is the adjustment amount;

Appears in 2 contracts

Samples: Comprehensive Development Agreement, Comprehensive Development Agreement

Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:: ““ is the adjustment amount;

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 2 contracts

Samples: Build Agreement, Build Agreement

Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 [180] days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Professional Services Agreement

Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ O = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Design Build Agreement

AutoNDA by SimpleDocs

Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Developer -Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Development Agreement

Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Design Build Agreement

Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Design Build Agreement

Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Build Agreement

Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Design Build Agreement

Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Development Agreement

Delay in NTP1. 4.3.1.1. 12.1.3.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 181 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding or subtracting the product of the following (which amount may not be less than zero) to from the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Comprehensive Development Agreement

Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, then: to the Segment 1 Price: the Segment 1 Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Segment 1 Price) * (([A-B]/B)/T) where:: and

Appears in 1 contract

Samples: Design Build Agreement

Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 90 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Design Build Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.