Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 10 contracts
Samples: Design Build Agreement, Professional Services Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 10 contracts
Samples: Development Agreement, Development Agreement, Development Agreement
Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:: “Δ“ is the adjustment amount;
Appears in 5 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 4 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 3 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 90 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 3 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 3 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 90 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 2 contracts
Samples: Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 2 contracts
Samples: Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ ∆ = N * (Price) * (([A-B]/B)/T) where:
Appears in 2 contracts
Samples: Build Agreement, Build Agreement
Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 2 contracts
Samples: Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.1. 12.1.3.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 181 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding or subtracting the product of the following (which amount may not be less than zero) to from the Price: where: Δ = N * (Price) * (([A-B]/B)/T) where:“Δ” is the adjustment amount;
Appears in 2 contracts
Samples: Comprehensive Development Agreement, Comprehensive Development Agreement
Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 2 contracts
Samples: Build Agreement, Build Agreement
Delay in NTP1. 4.3.1.112.1.4.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:: ““ is the adjustment amount;
Appears in 2 contracts
Samples: Design Build Agreement, Design Build Agreement
Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ O = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Design Build Agreement
Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Design Build Agreement
Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Developer -Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Development Agreement
Delay in NTP1. 4.3.1.112.1.3.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBADBC, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Financial Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: where: Δ = N * (Price) * (([A-B]/B)/T) where:“Δ“ is the adjustment amount;
Appears in 1 contract
Samples: www.txdot.gov
Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, then: to the Segment 1 Price: the Segment 1 Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Segment 1 Price) * (([A-B]/B)/T) where:: and
Appears in 1 contract
Samples: Design Build Agreement
Delay in NTP1. 4.3.1.1. 4.3.1.1 TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ ∆ = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Design Build Agreement
Delay in NTP1. 4.3.1.1. 12.1.4.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Development Agreement
Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 [180] days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Professional Services Agreement
Delay in NTP1. 4.3.1.1. 12.1.3.1 TxDOT anticipates that it will issue the NTP1 concurrently with or shortly after execution and delivery of this DBAAgreement, but shall have the right in its sole discretion to defer issuance. If the effective date of the NTP1 is more than 180 181 days after the Proposal Due Date, Date and such delay in issuing the NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB ContractorDeveloper-Related Entity, the Price will be adjusted by adding or subtracting the product of the following (which amount may not be less than zero) to from the Price: Δ ∆ = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Comprehensive Development Agreement
Delay in NTP1. 4.3.1.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:
Appears in 1 contract
Samples: Design Build Agreement
Delay in NTP1. 4.3.1.112.1.5.1. TxDOT anticipates that it will issue NTP1 concurrently with or shortly after execution and delivery of this DBA, but shall have the right in its sole discretion to defer issuance. If the effective date of NTP1 is more than 180 days after the Proposal Due Date, Date and such delay in issuing NTP1 was not caused in whole or in part by the acts, omissions, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval of any DB Contractor-Related Entity, the Price will be adjusted by adding the following (which amount may not be less than zero) to the Price: Δ = N * (Price) * (([A-B]/B)/T) where:: “Δ“ is the adjustment amount;
Appears in 1 contract
Samples: Build Agreement