Common use of Delay in NTP2 Clause in Contracts

Delay in NTP2. 4.3.2.1. If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. The Price adjustment shall apply to the period beginning on the date of 4.3.2.3. The Price for Work performed on and after the date of issuance of NTP2 will

Appears in 8 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Delay in NTP2. 4.3.2.1. If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. The Price adjustment shall apply to the period beginning on the date ofof issuance of NTP2. 4.3.2.3. The Price for Work performed on and after the date of issuance of NTP2 willwill be adjusted by adding the product of the following to the Price: where:

Appears in 7 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Delay in NTP2. 4.3.2.1. 4.3.2.1 If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. 4.3.2.2 The Price adjustment shall apply to the period beginning on the date of 4.3.2.3. 4.3.2.3 The Price for Work performed on and after the date of issuance of NTP2 willwill be adjusted by adding the product of the following to the Price:

Appears in 6 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Delay in NTP2. 4.3.2.1. If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. The Price adjustment shall apply to the period beginning on the date of 4.3.2.3. The Price for Work performed on and after the date of issuance of NTP2 willwill be adjusted by adding the product of the following to the Price: where:

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

Delay in NTP2. 4.3.2.1. If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2.DB 4.3.2.2. The Price adjustment shall apply to the period beginning on the date ofof issuance of NTP2. 4.3.2.3. The Price for Work performed on and after the date of issuance of NTP2 willwill be adjusted by adding the product of the following to the Price: where:

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

Delay in NTP2. 4.3.2.1. If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. The Price adjustment shall apply to the period beginning on the date ofof issuance of NTP2. 4.3.2.3. The Price for Work performed on and after the date of issuance of NTP2 will

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Delay in NTP2. 4.3.2.1. If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. The Price adjustment shall apply to the period beginning on the date of 4.3.2.3. The Price for Work performed on and after the date of issuance of NTP2 willwill be adjusted by adding the product of the following to the Price:

Appears in 1 contract

Samples: Design Build Agreement

Delay in NTP2. 4.3.2.1. 4.3.2.1 If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. 4.3.2.2 The Price adjustment shall apply to the period beginning on the date ofof issuance of NTP2. 4.3.2.3. 4.3.2.3 The Price for Work performed on and after the date of issuance of NTP2 willwill be adjusted by adding the product of the following to the Price: ∆ = N * (Price - C) * (([A-B]/B)/T) where:

Appears in 1 contract

Samples: Design Build Agreement

Delay in NTP2. 4.3.2.1. 4.3.2.1 If NTP2 has not been issued by the later of 270 days after the Proposal Due Date or 90 days following issuance of NTP1, and this delay is not caused in whole or in part by an act, omission, negligence, intentional misconduct, or breach of applicable Law, contract or Governmental Approval by any DB Contractor-Related Entity (including DB Contractor’s failure to satisfy any particular condition to NTP2), the Price shall be subject to adjustment, as described in this Section 4.3.2. 4.3.2.2. 4.3.2.2 The Price adjustment shall apply to the period beginning on the date of 4.3.2.3. 4.3.2.3 The Price for Work performed on and after the date of issuance of NTP2 willNTP2

Appears in 1 contract

Samples: Design Build Agreement