Common use of Delay in Submission of Deliverables Clause in Contracts

Delay in Submission of Deliverables. Subject to the terms set forth in Section 4.12, if the Design-Builder fails to provide any of the deliverables set forth in Exhibit C, the Design-Builder shall pay to the Department liquidated damages in the amount set forth in the Project Information Section of this Agreement for each such deliverable that is not timely submitted.

Appears in 5 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Delay in Submission of Deliverables. Subject to the terms set forth in Section Sections 3.1.2 and 4.12, if the Design-Builder fails to provide any of the deliverables set forth in Exhibit C, the Design-Builder shall pay to the Department liquidated damages in the amount set forth in the Project Information Section of this Agreement for each such deliverable that is not timely submitted.

Appears in 4 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs