Delayed NTP. In the event Owner fails to issue the NTP in accordance with Section 5.2B by March 31, 2012, then Contractor shall, at the end of every three Month period thereafter until NTP (if any) is issued by Owner, notify Owner in writing of any impacts such delay has on Contractor’s costs of performance of the Work, including Subcontractor prices, and Contractor’s ability to perform the Work in accordance with the Agreement, including the Project Schedule and other Changed Criteria. Contractor shall not be entitled to the relief in this Section 5.2C to the extent the reason for Owner failing to issue NTP is because Contractor failed to provide the Letter of Credit in accordance with Section 9.2A.
Appears in 4 contracts
Samples: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC)
Delayed NTP. In the event Owner fails to issue the NTP in accordance with Section 5.2B by March 31June 1, 20122013, then Contractor shall, at the end of every three Month period thereafter until NTP (if any) is issued by Owner, notify Owner in writing of any impacts such delay has on Contractor’s costs of performance of the Work, including Subcontractor prices, and Contractor’s ability to perform the Work in accordance with the Agreement, including the Project Schedule and other Changed Criteria. Contractor shall not be entitled to the relief in this Section 5.2C to the extent the reason for Owner failing to issue NTP is because Contractor failed to provide the Letter of Credit in accordance with Section 9.2A.
Appears in 4 contracts
Samples: Lump Sum Turnkey Agreement, Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC)
Delayed NTP. 1. In the event Owner fails to issue the NTP in accordance with Section 5.2B by March 31July 1, 20122014, then Contractor shall, at the end of every three Month period thereafter until NTP (if any) is issued by Owner, notify Owner in writing of any impacts such delay has on Contractor’s costs of performance of the Work, including Subcontractor prices, and Contractor’s ability to perform the Work in accordance with the Agreement, including the Project Schedule and other Changed Criteria. Contractor shall not be entitled to the relief in this Section 5.2C to the extent the reason for Owner failing to issue NTP is because Contractor failed to provide the Letter of Credit in accordance with Section 9.2A.
Appears in 2 contracts
Samples: Fixed Price Separated Turnkey Agreement (Cheniere Energy Inc), Fixed Price Separated Turnkey Agreement (Cheniere Energy Inc)
Delayed NTP. In the event Owner fails to issue the NTP in accordance with Section 5.2B by March 31June 30, 20122015, then Contractor shall, at the end of every three Month period thereafter until NTP (if any) is issued by Owner, notify Owner in writing of any impacts such delay has on Contractor’s costs of performance of the Work, including Subcontractor prices, and Contractor’s ability to perform the Work in accordance with the Agreement, including the Project Schedule and other Changed Criteria. Contractor shall not be entitled to the relief in this Section 5.2C to the extent the reason for Owner failing to issue NTP is because Contractor failed to provide the Letter of Credit in accordance with Section 9.2A.
Appears in 2 contracts
Samples: Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.), Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)