Common use of Delays during Development Clause in Contracts

Delays during Development. Without prejudice to the provisions of Clause 13.3.2, if the SPD does not achieve any of the Project Milestones or the Railway Electrical Engineer shall have reasonably determined that the rate of progress of development Work is such that the Solar Rooftop Power System is not likely to be completed by the Scheduled Completion Date, it shall notify the SPD and Railways to this effect, and the SPD shall, within 15 (fifteen) days of such notice, by a communication inform the Railway Electrical Engineer and Railways in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Delays during Development. Without prejudice to the provisions of Clause 13.3.2, if the SPD does not achieve any of the Project Milestones or the Railway Electrical Engineer shall have reasonably determined that the rate of progress of development Work is such that the Solar Rooftop land based Power System is not likely to be completed by the Scheduled Completion Date, it shall notify the SPD and Railways to this effect, and the SPD shall, within 15 seven (fifteen07) days of such notice, by a communication inform the Railway Electrical Engineer and Railways in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Delays during Development. Without prejudice to the provisions of Clause 13.3.2, if the SPD does not achieve any of the Project Milestones or the Railway Electrical Engineer or nominated official by CWM/PR shall have reasonably determined that the rate of progress of development Work is such that the Solar Rooftop Power System is not likely to be completed by the Scheduled Completion Date, it shall notify the SPD and Railways to this effect, and the SPD shall, within 15 07 (fifteenseven) days of such notice, by a communication inform the Railway Electrical Engineer or nominated official by CWM/PR and Railways in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 1 contract

Samples: Power Purchase Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.