Delays in Commissioning. 12.3.1.1 If the Plant has not been Commissioned on or before the Required Commercial Operations Date, the Seller shall pay to the Purchaser an equivalent amount to the Energy charge that the Purchaser would require in order to source for an alternative source of energy for that delayed period. 12.3.1.2 Payments made in accordance with Clause Error! Reference source not found. above, shall be liquidated damages for the detrimental impact of such delay upon the Purchaser's generation planning.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Delays in Commissioning. 12.3.1.1 If the Plant has not been Commissioned on or before the Required Commercial Operations Date, the Seller shall pay to the Purchaser an equivalent amount to the Energy charge that the Purchaser would require in order to source for an alternative source of energy for that delayed period.
12.3.1.2 Payments made in accordance with Clause Error! Reference source not found. 12.3.1.1 above, shall be liquidated damages for the detrimental impact of such delay upon the Purchaser's generation planning.
Appears in 1 contract
Samples: Power Purchase Agreement
Delays in Commissioning. 12.3.1.1 If the Plant has not been Commissioned on or before the Required Commercial Operations Date, the Seller shall pay to the Purchaser an equivalent amount to the Energy charge that the Purchaser would require in order to source for an alternative source of energy for that delayed period.
12.3.1.2 period Payments made in accordance with Clause Error! Reference source not found. 12.3.1.1 above, shall be liquidated damages for the detrimental impact of such delay upon the Purchaser's generation planning.
Appears in 1 contract
Samples: Power Purchase Agreement
Delays in Commissioning. 12.3.1.1 12.2.1.1 If the Plant has not been Commissioned on or before the Required Commercial Operations Date, the Seller shall pay to the Purchaser an equivalent amount to the Energy charge that the Purchaser would require in order to source for an alternative source of energy for that delayed period...
12.3.1.2 12.2.1.2 Payments made in accordance with Clause Error! Reference source not found. 12.2.1.1 above, shall be liquidated damages for the detrimental impact of such delay upon the Purchaser's generation planning.
Appears in 1 contract
Samples: Power Purchase Agreement
Delays in Commissioning. 12.3.1.1 12.2.1.1 If the Plant has not been Commissioned on or before the Required Commercial Operations Date, the Seller shall pay to the Purchaser an equivalent amount to the Energy charge that the Purchaser would require in order to source for an alternative source of energy for that delayed period.
12.3.1.2 period Payments made in accordance with Clause Error! Reference source not found. 12.2.1.1 above, shall be liquidated damages for the detrimental impact of such delay upon the Purchaser's generation planning.
Appears in 1 contract
Samples: Power Purchase Agreement