DELAYS IN CONSTRUCTION. Subject to outside date set forth in Article 4 of the Lease, the Commencement Date under the Lease shall be postponed for each day that Landlord fails to substantially complete the Work thereby as a result of strikes, acts of God, shortages of materials or labor, governmental approvals or requirements, the various causes set forth below, or any other causes beyond Landlord's reasonable control, in such case, the commencement of Rent shall be similarly postponed, except to the extent that delays occur as a result of one or more of the following, (collectively called "Tenant Delays"); (a) Tenant's requests for changes to the Work or Change Orders under Section V, or otherwise, (b) Tenant's failure to furnish an amount equal to Landlord's reasonable estimate of Tenant's Cost (if any) within 10 days, as described in Section X111 (which shall give Landlord the absolute right to postpone the Work until such amount is furnished to Landlord), (c) any upgrades, special work or other non-building standard items, or items not customarily provided by Landlord to office tenants, to the extent that the some involve longer lead times, installation times, delays or difficulties in obtaining building permits, requirements for any governmental approval, permit or action beyond the issuance of normal building permits (as described in Section IV), (d) the performance by Tenant or Tenant's contractors, agents or employees of any work at or about the Premises or Property, or (e) any act or omission of Tenant or Tenant's contractors, agents or employees, or any breach by the Tenant of any provisions contained in this Agreement or in the Lease, or any failure of Tenant to cooperate with Landlord, or otherwise act in good faith in order to cause the Work to be designed and performed in a timely manner.
Appears in 1 contract
Samples: Office Lease (Corechange Inc)
DELAYS IN CONSTRUCTION. Subject to outside date set forth in Article 4 of the Lease, the The Commencement Date under the Lease shall be postponed for each day that Landlord fails to substantially complete the Work thereby as a result of strikes, acts of God, shortages of materials or labor, governmental approvals or requirements, the various causes set forth below, or any other causes beyond Landlord's reasonable control, in . In such case, the commencement of Rent shall be similarly postponed, except to the extent that delays occur as a result of one or more of the following, following (collectively called "Tenant Delays");):
(a) Delays in Planning as described above (except for Landlord Delays), or
(b) Tenant's requests for changes to the Work or Change Orders under Section VVII, or otherwise,
(bc) Tenant's failure to furnish an amount equal to Landlord's reasonable estimate of Tenant's Cost (if any) within 10 days, as described in Section X111 IX (which shall give Landlord the absolute right to postpone the Work until such amount is furnished to Landlord),
(cd) any upgrades, special work or other non-building standard items, or items not customarily provided by Landlord to office tenants, to the extent that the some same involve longer lead times, installation times, delays or difficulties in obtaining building permits, requirements for any governmental approval, permit or action beyond the issuance of normal building permits (as described in Section IVVI), or other delays not typically encountered in connection with Landlord's standard office improvements,
(de) the performance by Tenant or Tenant's contractors, agents or employees of any work at or about the Premises or Property, or
(ef) any act or omission of Tenant or Tenant's contractors, agents or employees, or any breach by the Tenant of any provisions contained in this Agreement or in the Lease, or any failure of Tenant to cooperate with Landlord, Landlord or otherwise act in good faith in order to cause the Work to be designed and performed in a timely manner.
Appears in 1 contract
DELAYS IN CONSTRUCTION. Subject to outside date set forth in Article 4 of the Lease, the Commencement Date under the A. Lease shall be postponed for each day that Landlord fails to substantially complete the Work thereby as a result of strikes, acts of God, shortages of materials or labor, governmental approvals or requirements, the various causes set forth below, or any other causes beyond Landlord's reasonable control.
B. The Commencement Date, in such casebut not the Rental Commencement Date, the commencement of Rent shall be similarly postponed, except to the extent that delays occur postponed as a result of one or more of the following, following (collectively called "Tenant Delays"):
(1) Delays in Planning as described above (except for Landlord Delays);
(a2) Tenant's requests for changes to the Work or Change Orders under Section VVIII, or otherwise,or
(b3) Tenant's failure to furnish an amount equal to Landlord's reasonable estimate of Tenant's Cost (if any) within 10 days, as described in Section X111 IX (which shall give Landlord the absolute right to postpone the Work until such amount is furnished to Landlord),;
(c4) Tenant's requirement of any upgrades, special work or other non-non- building standard items, or items not customarily provided by Landlord to office tenants, to the extent that the some same involve longer lead times, installation times, delays or difficulties in obtaining building permits, requirements for any governmental approval, permit or action beyond the issuance of normal building permits (as described in Section IVVI),, or other delays not typically encountered in connection with Landlord's standard office improvements;
(d5) the The performance by Tenant or Tenant's contractors, agents or employees of any work at or about the Premises or PropertyPremises, or
(e6) any act or omission of Tenant or Tenant's contractors, agents or employees, or any breach by the Tenant of any provisions provision contained in this Agreement or in the Lease, or any failure of Tenant to cooperate with Landlord, Landlord or otherwise act in good faith in order to cause the Work to be designed and performed in a timely manner.
Appears in 1 contract
Samples: Lease Agreement (Webmd Inc)
DELAYS IN CONSTRUCTION. Subject to outside date set forth in Article 4 of the Lease, the Commencement Date under the Lease shall be postponed for each day that Landlord fails to substantially complete the Work thereby as a result of strikes, acts of God, shortages of materials or labor, governmental approvals or requirements, the various causes set forth below, or any other causes beyond Landlord's reasonable control, in . In such case, the commencement of Rent shall be similarly postponed, except to the extent that delays occur as a result of one or more of the following, (collectively called "Tenant Delays");
(a) Tenant's requests for changes to the Work or Change Orders under Section V, or otherwise,
(b) Tenant's failure to furnish an amount equal to Landlord's reasonable estimate of Tenant's Cost (if any) within 10 days, as described in Section X111 XIII (which shall give Landlord the absolute right to postpone the Work until such amount is furnished to Landlord),
(c) any upgrades, special work or other non-building standard items, or items not customarily provided by Landlord to office tenants, to the extent that the some same involve longer lead times, installation times, delays or difficulties in obtaining building permits, requirements for any governmental approval, permit or action beyond the issuance of normal building permits (as described in Section IV),
(d) the performance by Tenant or Tenant's contractors, agents or employees of any work at or about the Premises or Property, or
(e) any act or omission of Tenant or Tenant's contractors, agents or employees, or any breach by the Tenant of any provisions contained in this Agreement or in the Lease, or any failure of Tenant to cooperate with Landlord, Landlord or otherwise act in good faith in order to cause the Work to be designed and performed in a timely manner.
Appears in 1 contract
Samples: Office Lease (Corechange Inc)
DELAYS IN CONSTRUCTION. Subject to outside date set forth in Article 4 of the Lease, the The Commencement Date under the Lease shall be postponed for each day that Landlord fails to substantially complete the Work thereby as a result of strikes, acts of God, shortages of materials or labor, governmental approvals or requirements, the various causes set forth below, or any other causes beyond Landlord's reasonable control, in . In such case, the commencement of Rent shall be similarly postponed, except to the extent that delays occur as a result of one or more of the following, following (collectively called "Tenant Delays");):
(a) Delays in Planning as described above (except for Landlord Delays), or
(b) Tenant's requests for changes to the Work or Change Orders under Section VVII, or otherwise,
(bc) Tenant's failure to furnish an amount equal to Landlord's reasonable estimate of Tenant's Cost (if any) within 10 days, as described in Section X111 IX (which shall give Landlord the absolute right to postpone the Work until such amount is furnished to Landlord),
(cd) any upgrades, special work or other non-building standard items, or items not customarily provided by Landlord to office tenants, to the extent that the some same involve longer lead times, installation times, delays or difficulties in obtaining building permits, requirements for any governmental approval, permit or action beyond the issuance of normal building permits (as described in Section IVVI), or other delays not typically encountered in connection with Landlord's standard office improvements,
(de) the performance by Tenant or Tenant's contractors, agents or employees of any work at or about the Premises or Property, or
(ef) any act or omission of Tenant or Tenant's contractors, agents or employees, or any breach by the Tenant of any provisions contained in this Agreement or in the Lease, or any failure of Tenant to cooperate with Landlord, Landlord or otherwise act in good faith in order to cause the Work to be designed and performed in a timely manner.
Appears in 1 contract