Term and Time of Performance The effective date of this Agreement shall begin November 1, 2020 and will continue through June 30, 2025, subject to appropriation of funds, notwithstanding any other provision in this agreement.
DELIVERY AND TITLE A. The place of delivery for all Products sold pursuant to this Agreement shall be FOB Plant. Buyer and Buyer’s agents shall be given access to Seller’s Plant in a manner and at all times reasonably necessary and convenient for Buyer to take delivery as provided herein. Buyer shall schedule the loading and shipping of all outbound Products purchased hereunder which is shipped by rail. All labor and equipment necessary to load rail cars shall be supplied by Seller without charge to Buyer. Seller agrees to handle all Products in a good and workmanlike manner in accordance with Buyer’s reasonable requirements and in accordance with normal industry practice. Seller shall maintain the rail loading facilities in safe operating condition in accordance with normal industry standards. B. Seller shall be responsible at all times for the quantity, quality and condition of any Products in storage at the Plant. Seller shall not be responsible for the quantity, quality and condition of any of Products stored by Buyer at locations other than the Plant. C. Buyer shall give to Seller a schedule of quantities of the Products to be removed by rail with sufficient advance notice reasonably to allow Seller to provide the required services. Seller shall provide the labor, equipment and facilities necessary to meet Buyer’s loading schedule and, except for any consequential or indirect damages, shall be responsible for Buyer’s actual costs or damages resulting from Seller’s failure to do so. Buyer shall order and supply rail cars as scheduled for rail shipments. All freight charges shall be the responsibility of Buyer and shall be billed directly to Buyer. D. Buyer shall provide loading orders as necessary to permit Seller to maintain Seller’s usual production schedule, provided, however, that Buyer shall not be responsible for failure to schedule removal of the DDGS unless Seller shall have provided to Buyer production schedules as follows: Five (5) days prior to the beginning of each calendar month during the term hereof, Seller shall provide to Buyer a tentative schedule for production in the next calendar month which is to be shipped by railcar. Seller shall inform Buyer daily of inventory and production status. For purposes of this paragraph, notification will be sufficient if made by e-mail or facsimile as follows: If to Buyer, to the attention of Xxxxx Xxxxxxx, Facsimile number 000-000-0000 or email to xxxxxxxx@xxx-xxxxx.xxx, and If to Seller, to the attention of Xxxxx Xxxxxx, Facsimile number 000-000-0000 or email to xxxxx.xxxxxx@xxxxxxxxxxxxxxxxxxxxxxxxx.xxx, Or to such other representatives of Buyer and Seller as they may designate to the other in writing. E. Title, risk of loss and full shipping responsibility shall pass to Buyer upon loading the DDGS into rail cars and delivering to Buyer of the xxxx of lading for each such shipment.
Delivery and Risk 7.1 Unless otherwise stated in the Order, the price quoted includes delivery to the address specified in the Order.
Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv); (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13); (c) occurrence of a Force Majeure Event; (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and (e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement. (ii) The Contractor shall, no later than 15 (fifteen) business days from the occurrence of an event or circumstance specified in Clause 10.5 (i), inform the Authority’s Engineer by notice in writing, with a copy to the Authority, stating in reasonable detail with supporting particulars, the event or circumstances giving rise to the claim for Time Extension in accordance with the provisions of this Agreement. Provided that the period of 15 (fifteen) business days shall be calculated from the date on which the Contractor became aware, or should have become aware, of the occurrence of such an event or circumstance. Provided further that notwithstanding anything to the contrary contained in this Agreement, Time Extension shall be due and applicable only for the Works which are affected by the aforesaid events or circumstances and shall not in any manner affect the Project Completion Schedule for and in respect of the Works which are not affected hereunder. (iii) On the failure of the Contractor to issue to the Authority’s Engineer a notice in accordance with the provisions of Clause 10.5 (ii) within the time specified therein, the Contractor shall not be entitled to any Time Extension and shall forfeit its right for any such claims in future. For the avoidance of doubt, in the event of failure of the Contractor to issue notice as specified in this clause 10.5 (iii), the Authority shall be discharged from all liability in connection with the claim. (iv) The Authority’s Engineer shall, on receipt of the claim in accordance with the provisions of Clause 10.5 (ii), examine the claim expeditiously within the time frame specified herein. In the event the Authority’s Engineer requires any clarifications to examine the claim, the Authority’s Engineer shall seek the same within 15 (fifteen) days from the date of receiving the claim. The Contractor shall, on receipt of the communication of the Authority’s Engineer requesting for clarification, furnish the same to the Authority’s Engineer within 10 (ten) days thereof. The Authority’s Engineer shall, within a period of 30 (thirty) days from the date of receipt of such clarifications, forward in writing to the Contractor its determination of Time Extension. Provided that when determining each extension of time under this Clause 10.5, the Authority’s Engineer shall review previous determinations and may increase, but shall not decrease, the total Time Extension. (v) If the event or circumstance giving rise to the notice has a continuing effect: (a) a fully detailed claim shall be considered as interim; (b) the Contractor shall, no later than 10 (ten) days after the close of each month, send further interim claims specifying the accumulated delay, the extension of time claimed, and such further particulars as the Authority’s Engineer may reasonably require; and (c) the Contractor shall send a final claim within 30 (thirty) days after the effect of the event or the circumstance ceases. Upon receipt of the claim hereunder, the Authority’s Engineer shall examine the same in accordance with the provisions of Clause 10.5 (iv) within a period of 30 (thirty) days of the receipt thereof