DELIVERY, INSTALLATION AND ACCEPTANCE. 9.1 The Seller shall transport the Equipment at its own cost to the place of delivery. If the shipment is intact, the Buyer shall issue delivery note for the Seller. 9.2 The Buyer shall perform the installation of the Equipment and verify whether the Equipment is functional and meets the technical requirements of Annexes No. 1 and 2 hereof. 9.3 The Buyer undertakes to perform the installation of the Equipment and verification whether the Equipment is functional and meets the technical requirements within 3 working days of the delivery of the Equipment. 9.4 The delivery shall include all technical documentation pertaining to the Equipment, user manuals and certificate of compliance of the Equipment and all its parts and accessories with approved standards. 9.5 The procedure shall be completed by acceptance of the Equipment confirmed by the acceptance protocol containing specifications of all performed tests. The protocol shall contain the following information: 9.5.1 Information about the Seller, the Buyer and any subcontractors, 9.5.2 Description of the Equipment including description of all components and serial numbers, 9.5.3 Description of performed tests including achieved parameters, 9.5.4 List of technical documentation including the manuals, 9.5.5 Date and signature of the representative of the Buyer specified in 11.2 hereof. 9.6 Acceptance of the Equipment does not release the Seller from liability for damage caused by product defects. 9.7 The Buyer shall not be obliged to accept an Equipment, which would show defects or unfinished work and which would otherwise not form a barrier, on their own or in connection with other defects, to using the Equipment. In this case, the Buyer shall issue a record containing the reason for its refusal to accept the Equipment.
Appears in 2 contracts
Samples: Purchase Contract, Purchase Contract
DELIVERY, INSTALLATION AND ACCEPTANCE. 9.1 The Seller shall transport the Equipment at its own cost to the place of delivery. If the shipment is intact, the Buyer shall issue delivery note for the Seller.
9.2 . The Buyer shall perform the installation of the Equipment and verify whether the Equipment is functional and meets the technical requirements of Annexes No. 1 and 2 hereof.
9.3 . The Buyer undertakes to perform the installation of the Equipment and verification whether the Equipment is functional and meets the technical requirements within 3 working days 2 weeks of the delivery of the Equipment.
9.4 . The delivery shall include all technical documentation pertaining to the Equipment, the protocol about the preliminary testing of the Equipment, user manuals and certificate of compliance of the Equipment and all its parts and accessories with approved standards.
9.5 . The procedure shall be completed by acceptance of the Equipment confirmed by the acceptance protocol containing specifications of all performed tests. The protocol shall contain the following information:
9.5.1 : Information about the Seller, the Buyer and any subcontractors,
9.5.2 , Description of the Equipment including description of all components and serial numbers,
9.5.3 , Description of performed tests including achieved parameters,
9.5.4 ; in case the parameters achieved are different from the parameters achieved at the place of manufacture during the testing according to Article 9.. hereof, the parameters measured by the Buyer shall be decisive, List of technical documentation including the manuals,
9.5.5 , Date and signature of the representative of the Buyer specified in 11.2 12.2 hereof.
9.6 . Acceptance of the Equipment does not release the Seller from liability for damage caused by product defects.
9.7 defects that were not detected during the acceptance procedure. The Buyer shall not be obliged to accept an Equipment, Equipment which would show defects or unfinished work and which would otherwise not form a barrier, on their own or in connection with other defects, to using the Equipment. In this case, the Buyer shall issue a record containing the reason for its his refusal to accept the Equipment.
Appears in 2 contracts
Samples: Purchase Contract, Purchase Contract
DELIVERY, INSTALLATION AND ACCEPTANCE. 9.1 The Seller shall transport the Equipment at its own cost to the place of delivery. If the shipment is intact, the Buyer shall issue delivery note for the Seller.
9.2 The Buyer shall Seller undertakes to perform the installation of the Equipment on-site and verify whether the Equipment is functional and meets the technical requirements of Annexes No. 1 and 2 hereof.
9.3 The Buyer undertakes to perform the installation of the Equipment and verification whether the Equipment is functional and meets the technical requirements hereof within 3 14 working days of the delivery of the Equipment. In case the Seller will be unable to install the Equipment properly directly on-site, the Seller undertakes to perform all steps needed to make the Equipment meet the technical requirements of Annexes No. 1 and 2 by 28 February 2018.
9.4 9.3 The delivery shall include all technical documentation pertaining to the Equipment, user manuals and certificate of compliance of the Equipment and all its parts and accessories with approved standards.
9.5 9.4 The procedure shall be completed by acceptance of the Equipment confirmed by the acceptance protocol containing specifications of all performed tests. The protocol shall contain the following information:
9.5.1 9.4.1 Information about the Seller, the Buyer and any subcontractors,
9.5.2 9.4.2 Description of the Equipment including description of all components and serial numbers,
9.5.3 9.4.3 Description of performed tests including achieved parameters,
9.5.4 9.4.4 List of technical documentation including the manuals,
9.5.5 9.4.5 Date and signature of the representative of the Buyer specified in 11.2 hereof.
9.6 9.5 Acceptance of the Equipment does not release the Seller from liability for damage caused by product defects.
9.7 9.6 The Buyer shall not be obliged to accept an the Equipment, which would show defects or unfinished work and which would otherwise not form a barrier, on their own or in connection with other defects, to using the Equipment. In this case, the Buyer shall issue a record containing the reason for its refusal to accept the Equipment.
Appears in 1 contract
Samples: Purchase Contract
DELIVERY, INSTALLATION AND ACCEPTANCE. 9.1 10.1 The Seller shall transport the Equipment at its own cost to the place of delivery. If the shipment is intact, the Buyer shall issue delivery note for the Seller.
9.2 10.2 The Buyer shall perform the installation of the Equipment and verify whether the Equipment is functional and meets the technical requirements of Annexes No. 1 and 2 hereof.
9.3 10.3 The Buyer undertakes to perform the installation of the Equipment and verification whether the Equipment is functional and meets the technical requirements within 3 working days 2 weeks of the delivery of the Equipment.
9.4 10.4 The delivery shall include all technical documentation pertaining to the Equipment, the protocol about the preliminary testing of the Equipment, user manuals and certificate of compliance of the Equipment and all its parts and accessories with approved standards.
9.5 10.5 The procedure shall be completed by acceptance of the Equipment confirmed by the acceptance protocol containing specifications of all performed tests. The protocol shall contain the following information:
9.5.1 10.5.1 Information about the Seller, the Buyer and any subcontractors,
9.5.2 10.5.2 Description of the Equipment including description of all components and serial numbers,
9.5.3 10.5.3 Description of performed tests including achieved parameters; in case the parameters achieved are different from the parameters achieved at the place of manufacture during the testing according to Article 9. hereof, the parameters measured by the Buyer shall be decisive,
9.5.4 10.5.4 List of technical documentation including the manuals,
9.5.5 10.5.5 Date and signature of the representative of the Buyer specified in 11.2 12.2 hereof.
9.6 10.6 Acceptance of the Equipment does not release the Seller from liability for damage caused by product defectsdefects that were not detected during the acceptance procedure.
9.7 10.7 The Buyer shall not be obliged to accept an Equipment, Equipment which would show defects or unfinished work and which would otherwise not form a barrier, on their own or in connection with other defects, to using the Equipment. In this case, the Buyer shall issue a record containing the reason for its his refusal to accept the Equipment.
Appears in 1 contract
Samples: Purchase Contract