Delivery of Draw Request and Certificate. On or about the thirtieth (30th) day of each month, Contractor shall submit to Owner five (5) copies of a Draw Request, in a form to be provided by Owner and agreed upon by Contractor (“Draw Request”). Each Draw Request shall be executed by a designated representative of Contractor appointed by Contractor to have such authority in accordance with Section 24.1. No Draw Request shall be considered complete unless it:
Appears in 4 contracts
Samples: Design Build Contract, www.mwaa.com, www.mwaa.com
Delivery of Draw Request and Certificate. On or about before the thirtieth (30th) day of each month, Contractor shall submit to Owner five (5) copies of a Draw Request, in a form to be provided by Owner and agreed upon by Contractor (“Draw Request”). Each Draw Request (or invoice) shall be executed by a designated representative of Contractor appointed by Contractor to have such authority in accordance with Section 24.1. No Draw Request shall be considered complete unless it:
Appears in 1 contract
Samples: metwashairports.com