Design Approval Process. (a) Unless the Concessionaire receives written objections thereto from the FBR within four (4) weeks after the date of submission, the Design Proposal shall be deemed Approved and the Concessionaire shall carry out the Detailed Design. (b) The Concessionaire shall subsequently submit for the Approval of the FBR the Detailed Design, construction drawings, specifications and detailed construction schedule on or before the [•] Month from the Effective Date. The FBR shall not unreasonably withhold its Approval of the Detailed Design, construction drawings and specifications and shall promptly give its Approval if the same are in conformity with the minimum requirements prescribed in the RFP. Provided that the comments given by FBR or approval given shall not be construed that any construction risk has passed on to the FBR and the Concessionaire shall remain liable to all construction risks. (c) FBR shall inform Concessionaire in writing of its Approval, rejection, partial Approval or partial rejection of said Detailed Design, construction drawings and specifications proposed by Concessionaire, within thirty (30) Days from receipt of submittals. Should Concessionaire not receive said written acceptance, rejection, partial acceptance or partial rejection within the periods set forth, FBR shall be deemed to have accepted the Detailed Design, construction drawings and specifications and Concessionaire may proceed with the execution thereof.
Appears in 3 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Design Approval Process.
(a) Unless the Concessionaire receives written objections thereto from the FBR within four (4) weeks after the date of submission, the Design Proposal shall be deemed Approved and the Concessionaire shall carry out the Detailed Design.
(b) The Concessionaire shall subsequently submit for the Approval of the FBR the Detailed Design, construction drawings, specifications and detailed construction schedule on or before the [•] Month from the Effective Date. The FBR shall not unreasonably withhold its Approval of the Detailed Design, construction drawings and specifications and shall promptly give its Approval if the same are in conformity with the minimum requirements prescribed in the RFP. Provided that the comments given by FBR or approval given shall not be construed that any construction risk has passed on to the FBR and the Concessionaire shall remain liable to all construction risks.
(c) FBR shall inform Concessionaire in writing of its Approval, rejection, partial Approval or partial rejection of said Detailed Design, construction drawings and specifications proposed by Concessionaire, within thirty (30) Days from receipt of submittals. Should Concessionaire not receive said written acceptance, rejection, partial acceptance or partial rejection within the periods set forth, FBR shall be deemed to have accepted the Detailed Design, construction drawings and specifications and Concessionaire may proceed with the execution thereof.thirty
Appears in 1 contract
Samples: Concession Agreement