Determination of Reasonableness of Steps Taken to Cure or Resolve Effects of a Force Majeure Event Sample Clauses

Determination of Reasonableness of Steps Taken to Cure or Resolve Effects of a Force Majeure Event. Any disagreements between IID and CVWD concerning the reasonableness of steps taken by CVWD or IID to cure or resolve the effects of a Force Majeure event shall be resolved pursuant to Sections 17.1 and 17.3.
AutoNDA by SimpleDocs

Related to Determination of Reasonableness of Steps Taken to Cure or Resolve Effects of a Force Majeure Event

  • Available Relief for a Force Majeure Event 11.7.1 Subject to this Article 11: (a) no Party shall be in breach of its obligations pursuant to this Agreement except to the extent that the performance of its obligations was prevented, hindered or delayed due to a Force Majeure Event; (b) every Party shall be entitled to claim relief in relation to a Force Majeure Event in regard to its obligations, including but not limited to those specified under Article 4.5; (c) For avoidance of doubt, neither Party’s obligation to make payments of money due and payable prior to occurrence of Force Majeure events under this Agreement shall be suspended or excused due to the occurrence of a Force Majeure Event in respect of such Party. (d) Provided that no payments shall be made by either Party affected by a Force Majeure Event for the period of such event on account of its inability to perform its obligations due to such Force Majeure Event.

  • Notification of Force Majeure Event 11.5.1 The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) day after such reinstatement. Provided that, such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under this Agreement. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular reports on the progress of those remedial measures and such other information as the other Party may reasonably request about the Force Majeure. 11.5.2 The Affected Party shall give notice to the other Party of (i) the cessation of the relevant event of Force Majeure; and (ii) the cessation of the effects of such event of Force Majeure on the performance of its rights or obligations/ roles under this Agreement, as soon as practicable after becoming aware of each of these cessations.

  • FORCE MAJEURE; OTHER CHANGES IN CONDITIONS 19.1 In the event of and as soon as possible after the occurrence of any cause constituting force majeure, the affected Party shall give notice and full particulars in writing to the other Party, of such occurrence or cause if the affected Party is thereby rendered unable, wholly or in part, to perform its obligations and meet its responsibilities under the Contract. The affected Party shall also notify the other Party of any other changes in condition or the occurrence of any event which interferes or threatens to interfere with its performance of the Contract. Not more than fifteen (15) days following the provision of such notice of force majeure or other changes in condition or occurrence, the affected Party shall also submit a statement to the other Party of estimated expenditures that will likely be incurred for the duration of the change in condition or the event of force majeure. On receipt of the notice or notices required hereunder, the Party not affected by the occurrence of a cause constituting force majeure shall take such action as it reasonably considers to be appropriate or necessary in the circumstances, including the granting to the affected Party of a reasonable extension of time in which to perform any obligations under the Contract. 19.2 If the Contractor is rendered unable, wholly or in part, by reason of force majeure to perform its obligations and meet its responsibilities under the Contract, UNDP shall have the right to suspend or terminate the Contract on the same terms and conditions as are provided for in Article 20, “Termination,” except that the period of notice shall be seven (7) days instead of thirty (30) days. In any case, UNDP shall be entitled to consider the Contractor permanently unable to perform its obligations under the Contract in case the Contractor is unable to perform its obligations, wholly or in part, by reason of force majeure for any period in excess of ninety (90) days. 19.3 Force majeure as used herein means any unforeseeable and irresistible act of nature, any act of war (whether declared or not), invasion, revolution, insurrection, terrorism, or any other acts of a similar nature or force, provided that such acts arise from causes beyond the control and without the fault or negligence of the Contractor. The Contractor acknowledges and agrees that, with respect to any obligations under the Contract that the Contractor must perform in areas in which UNDP is engaged in, preparing to engage in, or disengaging from any peacekeeping, humanitarian or similar operations, any delays or failure to perform such obligations arising from or relating to harsh conditions within such areas, or to any incidents of civil unrest occurring in such areas, shall not, in and of itself, constitute force majeure under the Contract.

  • Reporting of Non-Force Majeure Events Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

  • Duty to report Force Majeure Event 21.5.1 Upon occurrence of a Force Majeure Event, the Affected Party shall by notice report such occurrence to the other Party forthwith. Any notice pursuant hereto shall include full particulars of: (a) the nature and extent of each Force Majeure Event which is the subject of any claim for relief under this Article 21 with evidence in support thereof; (b) the estimated duration and the effect or probable effect which such Force Majeure Event is having or will have on the Affected Party’s performance of its obligations under this Agreement; (c) the measures which the Affected Party is taking or proposes to take for alleviating the impact of such Force Majeure Event; and (d) any other information relevant to the Affected Party’s claim. 21.5.2 The Affected Party shall not be entitled to any relief for or in respect of a Force Majeure Event unless it shall have notified the other Party of the occurrence of the Force Majeure Event as soon as reasonably practicable, and in any event no later than 10 (ten) days after the Affected Party knew, or ought reasonably to have known, of its occurrence, and shall have given particulars of the probable material effect that the Force Majeure Event is likely to have on the performance of its obligations under this Agreement. 21.5.3 For so long as the Affected Party continues to claim to be materially affected by such Force Majeure Event, it shall provide the other Party with regular (and not less than weekly) reports containing information as required by Clause 21.5.1, and such other information as the other Party may reasonably request the Affected Party to provide.

  • Events of Force Majeure Neither Party shall be held liable or responsible to the other Party nor be deemed to be in default under, or in breach of any provision of, this Agreement for failure or delay in fulfilling or performing any obligation of this Agreement when such failure or delay is due to force majeure, and without the fault or negligence of the Party so failing or delaying. For purposes of this Agreement, force majeure is defined as causes beyond the control of the Party, including, without limitation, acts of God; acts, regulations, or laws of any government; war; civil commotion; destruction of production facilities or materials by fire, flood, earthquake, explosion or storm; labor disturbances; epidemic; and failure of public utilities or common carriers. In such event Medistem or Licensee, as the case may be, shall immediately notify the other Party of such inability and of the period for which such inability is expected to continue. The Party giving such notice shall thereupon be excused from such of its obligations under this Agreement as it is thereby disabled from performing for so long as it is so disabled and the 30 days thereafter. To the extent possible, each Party shall use reasonable efforts to minimize the duration of any force majeure.

  • Effect of Force Majeure Event If either party to this contract cannot meet an obligation under this contract because of an event outside the control of that party (‘a force majeure event’): (a) the obligation, other than an obligation to pay money, is suspended to the extent it is affected by the force majeure event for as long as the force majeure event continues; and (b) the affected party must use its best endeavours to give the other party prompt notice of that fact including full particulars of the event, an estimate of its likely duration, the extent to which the affected party’s obligations are affected and the steps being taken to remove, overcome or minimise those effects.

  • REMEDIES IN CASE OF AN EVENT OF DEFAULT If there shall have occurred and be continuing an Event of Default, then and in every such case, the Pledgee shall be entitled to exercise all of the rights, powers and remedies (whether vested in it by this Agreement, any other Secured Debt Agreement or by law) for the protection and enforcement of its rights in respect of the Collateral, and the Pledgee shall be entitled to exercise all the rights and remedies of a secured party under the Uniform Commercial Code as in effect in any relevant jurisdiction and also shall be entitled, without limitation, to exercise the following rights, which each Pledgor hereby agrees to be commercially reasonable: (i) to receive all amounts payable in respect of the Collateral otherwise payable under Section 6 hereof to the Pledgors; (ii) to transfer all or any part of the Collateral into the Pledgee’s name or the name of its nominee or nominees; (iii) to vote all or any part of the Collateral (whether or not transferred into the name of the Pledgee) and give all consents, waivers and ratifications in respect of the Collateral and otherwise act with respect thereto as though it were the outright owner thereof (each Pledgor hereby irrevocably constituting and appointing the Pledgee the proxy and attorney-in-fact of such Pledgor, with full power of substitution to do so); (iv) at any time and from time to time to sell, assign and deliver, or grant options to purchase, all or any part of the Collateral, or any interest therein, at any public or private sale, without demand of performance, advertisement or notice of intention to sell or of the time or place of sale or adjournment thereof or to redeem or otherwise (all of which are hereby waived by each Pledgor), for cash, on credit or for other property, for immediate or future delivery without any assumption of credit risk, and for such price or prices and on such terms as the Pledgee in its absolute discretion may determine, provided that at least 10 days’ written notice of the time and place of any such sale shall be given to the Pledgors. The Pledgee shall not be obligated to make any such sale of Collateral regardless of whether any such notice of sale has theretofore been given. Each Pledgor hereby waives and releases to the fullest extent permitted by law any right or equity of redemption with respect to the Collateral, whether before or after sale hereunder, and all rights, if any, of marshalling the Collateral and any other security for the Obligations or otherwise. At any such sale, unless prohibited by applicable law, the Pledgee on behalf of the Secured Creditors may bid for and purchase all or any part of the Collateral so sold free from any such right or equity of redemption. Neither the Pledgee nor any other Secured Creditor shall be liable for failure to collect or realize upon any or all of the Collateral or for any delay in so doing nor shall any of them be under any obligation to take any action whatsoever with regard thereto; and (v) to set-off any and all Collateral against any and all Obligations.

  • Termination Due to Force Majeure Event If the period of Force Majeure continues or is in the reasonable judgment of the Parties likely to continue beyond a period of 120 (one hundred and twenty) Days, the Parties may mutually decide to terminate this Agreement or continue this Agreement on mutually agreed revised terms. If the Parties are unable to reach an agreement in this regard, the Affected Party shall after the expiry of the said period of 120 (one hundred and twenty ) Days be entitled to terminate the Agreement in which event, the provisions of Articles 16 and 17 shall, to the extent expressly made applicable, apply.

  • Termination or Suspension Under Federal Law (i) If the Employee is removed and/or permanently prohibited from participating in the conduct of the Company’s affairs by an order issued under Sections 8(e)(iv) or 8(g)(i) of the Federal Deposit Insurance Act (“FDIA”) (12 U.S.C. 1818(e)(4) and (g)(1)), all obligations of the Company under this Agreement shall terminate, as of the effective date of the order, but vested rights of the Employee shall not be affected. (ii) If the Bank is in default (as defined in Section 3(x)(1) of the FDIA), all obligations under this Agreement shall terminate as of the date of default; but the vested rights of the Employee shall not be affected. (iii) All obligations under this Agreement shall terminate, except to the extent it is determined that the continuation of this Agreement is necessary for the continued operation of the Bank; (A) by the OCC or its designee, at the time that the Federal Deposit Insurance Corporation (“FDIC”) enters into an agreement to provide assistance to or on behalf of the Bank under the authority contained in Section 13(c) of FDIA; or (B) by the OCC, or its designee, at the time that the OCC or its designee approves a supervisory merger to resolve problems related to operation of the Bank or when the Bank is determined by the OCC to be in an unsafe or unsound condition. Such action shall not affect any vested rights of the Employee. (iv) If a notice served under Section 8(e)(3) or (g)(1) of the FDIA suspends and/or temporarily prohibits the Employee from participating in the conduct of the Bank’s affairs, the Bank’s obligations under this Agreement shall be suspended as of the date of such service, unless stayed by appropriate proceedings. However, the vested rights of the Employee as of the date of suspension will not be affected. If the charges in the notice are dismissed, the Bank may in its discretion (A) pay the Employee all or part of the compensation withheld while its contract obligations were suspended, and (B) reinstate (in whole or in part) any of its obligations which were suspended.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!