Differing Site Conditions. 1. During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.
Appears in 15 contracts
Differing Site Conditions. 1. 4.1.a During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.
Appears in 4 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Differing Site Conditions. (1. ) During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract Contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contractContract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is they are disturbed and before the affected work is performed.
Appears in 1 contract
Samples: biznet.ct.gov
Differing Site Conditions. 1. (i) During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.
Appears in 1 contract
Samples: Construction Services Agreement for Sidewalk Improvement Project
Differing Site Conditions. 1. During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party party, in writing writing, of the specific differing conditions before the site is they are disturbed and before the affected work is performed.
Appears in 1 contract
Samples: programs.iowadnr.gov