Diversion Orders. The Authority shall notify the Contractor at the earliest practicable opportunity if it becomes aware that a Contractor Deliverable is likely to be subject to a Diversion Order. Where necessary the Authority may issue (or having issued cancel) a Diversion Order for urgent Delivery of the Contractor Deliverables identified in it: where a Diversion Order is issued the Contractor Deliverables are to be Delivered by the quickest means available, unless otherwise directed; any Diversion Order which is beyond the scope of the Contract is to be returned immediately to the Authority’s Representative (Commercial) with an appropriate explanation; if the terms of the Diversion Order are unclear, the Contractor shall contact the Authority’s Representative who issued it immediately for clarification or further instruction, copying the Authority’s Representative (Commercial) in on all correspondence; the Contractor shall be entitled to any additional Delivery and Packaging costs generated in complying with the Diversion Order or cancellation thereof, claims for which are to be submitted by the Contractor to the Authority’s Representative (Commercial) together with appropriate receipts and shall be priced and agreed in writing as a amendment to the Contract in accordance with clause A2. The Contractor shall not delay complying with the Diversion Order whilst awaiting agreement of any additional Delivery and Packaging costs.
Appears in 40 contracts
Samples: Contract, Supply Agreement, Procurement Agreement
Diversion Orders. The Authority shall notify the Contractor at the earliest practicable opportunity if it becomes aware that a Contractor Deliverable is likely to be subject to a Diversion Order. Where necessary the Authority may issue (or having issued cancel) a Diversion Order for urgent Delivery of the Contractor Deliverables identified in it: where a Diversion Order is issued the Contractor Deliverables are to be Delivered by the quickest means available, unless otherwise directed; any Diversion Order which is beyond the scope of the Contract is to be returned immediately to the Authority’s Representative (Commercial) with an appropriate explanation; if the terms of the Diversion Order are unclear, the Contractor shall contact the Authority’s Representative who issued it immediately for clarification or further instruction, copying the Authority’s Representative (Commercial) in on all correspondence; the Contractor shall be entitled to any additional Delivery and Packaging costs generated in complying with the Diversion Order or cancellation thereof, claims for which are to be submitted by the Contractor to the Authority’s Representative (Commercial) together with appropriate receipts and shall be priced and agreed in writing as a amendment to the Contract in accordance with clause condition A2. The Contractor shall not delay complying with the Diversion Order whilst awaiting agreement of any additional Delivery and Packaging costs.
Appears in 5 contracts
Samples: Supply Agreement, Contract for the Supply of Transport Equipment and Auxiliary Products, Supply Agreement
Diversion Orders. a. The Authority shall notify the Contractor at the earliest practicable opportunity if it becomes aware that a Contractor Deliverable is likely to be subject to a Diversion Order. Where necessary the .
b. The Authority may issue (or having issued cancel) a Diversion Order for the urgent Delivery delivery of the Contractor Deliverables identified in it: where a Diversion Order is issued the . These Contractor Deliverables are to be Delivered delivered by the Contractor using the quickest means available, unless otherwise directed; any Diversion Order which is beyond the scope of the Contract is to be returned immediately to available as agreed by the Authority’s Representative (Commercial) with an appropriate explanation; if .
c. The Authority reserves the right to cancel the Diversion Order.
d. If the terms of the Diversion Order are unclear, the Contractor shall immediately contact the Representative of the Authority who issued it for clarification and/or further instruction.
e. If the Diversion Order increases the quantity of Contractor Deliverables beyond the scope of the Contract, it is to be returned immediately to the Authority’s Representative who issued it immediately for clarification or further instruction, copying the Authority’s Representative (Commercial) in on all correspondence; the Commercial Officer with an appropriate explanation.
f. The Contractor shall be entitled to any reasonable additional Delivery delivery and Packaging packaging costs generated incurred in complying with the Diversion Order or cancellation thereof, claims for which cancellation. Claims are to be submitted by the Contractor to the Authority’s Representative (Commercial) Commercial Officer together with appropriate applicable receipts and shall be priced and agreed in writing as a an amendment to the Contract in accordance with clause A2Condition 6 (Formal Amendments to the Contract). The Contractor shall not delay complying comply with the requirements of the Diversion Order whilst awaiting agreement upon receipt of any additional Delivery and Packaging coststhe Diversion Order.
Appears in 5 contracts
Samples: Contract for SFJHQ Deployable Acoustic Rooms, Provision of Typhoon Mids Bu2 Servicing Support, Contract
Diversion Orders. a. The Authority shall notify the Contractor at the earliest practicable opportunity if it becomes aware that a Contractor Deliverable is likely to be subject to a Diversion Order. Where necessary the .
b. The Authority may issue (or having issued cancel) a Diversion Order for the urgent Delivery delivery of the Contractor Deliverables identified in it: where a Diversion Order is issued the . These Contractor Deliverables are to be Delivered delivered by the Contractor using the quickest means available, unless otherwise directed; any Diversion Order which is beyond the scope of the Contract is to be returned immediately to available as agreed by the Authority’s Representative (Commercial) with an appropriate explanation; if .
c. The Authority reserves the right to cancel the Diversion Order.
d. If the terms of the Diversion Order are unclear, the Contractor shall immediately contact the Authority’s Representative of the Authority who issued it immediately for clarification or and/or further instruction.
e. If the Diversion Order increases the quantity of Contractor Deliverables beyond the scope of the Contract, copying it is to be returned immediately to the Authority’s Representative (Commercial) in on all correspondence; the 's Commercial Officer with an appropriate explanation.
f. The Contractor shall be entitled to any reasonable additional Delivery delivery and Packaging packaging costs generated incurred in complying with the Diversion Order or cancellation thereof, claims for which cancellation. Claims are to be submitted by the Contractor to the Authority’s Representative (Commercial) 's Commercial Officer together with appropriate applicable receipts and shall be priced and agreed in writing as a an amendment to the Contract in accordance with clause A2condition 6 (Amendments to Contract). The Contractor shall not delay complying comply with the requirements of the Diversion Order whilst awaiting agreement upon receipt of any additional Delivery and Packaging coststhe Diversion Order.
Appears in 4 contracts
Samples: Contract, Intelligent Ship Phase 3 Contract, Contract
Diversion Orders.
a. The Authority shall notify the Contractor at the earliest practicable opportunity if it becomes aware that a Contractor Deliverable is likely to be subject to a Diversion Order. .
b. Where necessary the Authority may issue (or having issued cancel) a Diversion Order for urgent Delivery of the Contractor Deliverables identified in it: :
(1) where a Diversion Order is issued the Contractor Deliverables are to be Delivered by the quickest means available, unless otherwise directed; ;
(2) any Diversion Order which is beyond the scope of the Contract is to be returned immediately to the Authority’s Representative (Commercial) with an appropriate explanation; ;
(3) if the terms of the Diversion Order are unclear, the Contractor shall contact the Authority’s Representative who issued it immediately for clarification or further instruction, copying the Authority’s Representative ,
(Commercial4) in on all correspondence; the Contractor shall be entitled to any additional Delivery and Packaging costs generated in complying with the Diversion Order or cancellation thereof, claims for which are to be submitted by the Contractor to the Authority’s Representative (Commercial) together with appropriate receipts and shall be priced and agreed in writing as a amendment to the Contract in accordance with clause A2. The Contractor shall not delay complying with the Diversion Order whilst awaiting agreement of any additional Delivery and Packaging costs.
Appears in 1 contract
Samples: Procurement Agreement
Diversion Orders.
a. The Authority shall notify the Contractor at the earliest practicable opportunity if it becomes aware that a Contractor Deliverable is likely to be subject to a Diversion Order. .
b. Where necessary the Authority may issue (or having issued cancel) a Diversion Order for urgent Delivery of the Contractor Deliverables identified in it: :
(1) where a Diversion Order is issued the Contractor Deliverables are to be Delivered by the quickest means available, unless otherwise directed; ;
(2) any Diversion Order which is beyond the scope of the Contract is to be returned immediately to the Authority’s Representative (Commercial) with an appropriate explanation; ;
(3) if the terms of the Diversion Order are unclear, the Contractor shall contact the Authority’s Representative who issued it immediately for clarification or further instruction, copying the Authority’s Representative (Commercial) in on all correspondence; ;
(4) the Contractor shall be entitled to any additional Delivery and Packaging costs generated in complying with the Diversion Order or cancellation thereof, claims for which are to be submitted by the Contractor to the Authority’s Representative (Commercial) together with appropriate receipts and shall be priced and agreed in writing as a amendment to the Contract in accordance with clause A2. The Contractor shall not delay complying with the Diversion Order whilst awaiting agreement of any additional Delivery and Packaging costs.
Appears in 1 contract
Samples: Purchase Agreement
Diversion Orders. a. The Authority shall notify the Contractor at the earliest practicable opportunity if it becomes aware that a Contractor Deliverable is likely to be subject to a Diversion Order. .
b. Where necessary the Authority may issue (or having issued cancel) a Diversion Order for urgent Delivery of the Contractor Deliverables identified in it: :
(1) where a Diversion Order is issued the Contractor Deliverables are to be Delivered by the quickest means available, unless otherwise directed; ;
(2) any Diversion Order which is beyond the scope of the Contract is to be returned immediately to the Authority’s Representative (Commercial) with an appropriate explanation; ;
(3) if the terms of the Diversion Order are unclear, the Contractor shall contact the Authority’s Representative who issued it immediately for clarification or further instruction, copying the Authority’s Representative (Commercial) in on all correspondence; ;
(4) the Contractor shall be entitled to any additional Delivery and Packaging costs generated in complying with the Diversion Order or cancellation thereof, claims for which are to be submitted by the Contractor to the Authority’s Representative (Commercial) together with appropriate receipts and shall be priced and agreed in writing as a amendment to the Contract in accordance with clause A2. The Contractor shall not delay complying with the Diversion Order whilst awaiting agreement of any additional Delivery and Packaging costs.
Appears in 1 contract
Samples: Contract for Repair Services