DOCUMENTS AND SAMPLES AT PROJECT SITE. 3.11.1 Contractor shall maintain one (1) set of As-Built Documents at the Site, which shall be kept up to date on a daily basis during the performance of the Work. All performed changes, deletions or additions in the Work from that shown in the Contract Documents shall be recorded accurately and completely in the Record Documents. Upon Final Completion and as a condition to Final Payment, each sheet of the As-Built Documents and other Record Documents shall be signed and attested to by the Contractor’s Superintendent as being complete and accurate. 3.11.2 Contractor shall, at all times during performance of the Work, also maintain the following at the Site: (i) The latest updated Construction Schedule approved by City; (ii) Shop Drawings, product data, and samples; and (iii) All other required Submittals. At all times during the course of the Project, these documents shall be available to City, the Construction Manager and the Design Consultant to audit, excerpt, or copy as they see fit. Upon Final Completion or termination of the Construction Contract, these documents shall be delivered to City in the format requested by the City. 3.11.3 It shall be the responsibility of Contractor to maintain a current and complete record of all Changes performed during the progress of the Project construction. The record shall be in the form of a complete set of prints of the As-Built Documents on which daily recordings are made by Contractor, indicating in detail and dimension each variation from the original set of Contract Documents for all of the Work. At the completion of construction, Contractor shall, as a requirement of the Final Completion of the Work, certify that to the best of its knowledge, the As-Built Documents are true and accurate, and that the indications thereon represent all Changes performed during the construction of the Project. At Final Completion, the As-Built and other Record Documents shall become the property of City. 3.11.4 Contractor, in concert with the Design Consultant and the Construction Manager, shall review Contractor's As-Built Documents for conformance with all current Changes prior to presenting its monthly Application For Payment. The monthly progress payment statement will not be accepted or processed by City unless the As-Built Documents are current and complete, and Approved by City.
Appears in 30 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
DOCUMENTS AND SAMPLES AT PROJECT SITE.
3.11.1 Contractor shall maintain one (1) set of As-Built Documents at the Site, which shall be kept up to date on a daily basis during the performance of the Work. All performed changes, deletions or additions in the Work from that shown in the Contract Documents shall be recorded accurately and completely in the Record Documents. Upon Final Completion and as a condition to Final Payment, each sheet of the As-Built Documents and other Record Documents shall be signed and attested to by the Contractor’s Superintendent as being complete and accurate.
3.11.2 Contractor shall, at all times during performance of the Work, also maintain the following at the Site:
(i) The latest updated Construction Schedule approved by City;
(ii) Shop Drawings, product data, and samples; and
(iii) All other required Submittals. At all times during the course of the Project, these documents shall be available to City, the Construction Manager and the Design Consultant to audit, excerpt, or copy as they see fit. Upon Final Completion or termination of the Construction Contract, these documents shall be delivered to City in the format requested by the City.
3.11.3 It shall be the responsibility of Contractor to maintain a current and complete record of all Changes performed during the progress of the Project construction. The record shall be in the form of a complete set of prints of the As-Built Documents on which daily recordings are made by Contractor, indicating in detail and dimension each variation from the original set of Contract Documents for all of the Work. At the completion of construction, Contractor shall, as a requirement of the Final Completion of the Work, certify that to the best of its knowledge, the As-Built Documents are true and accurate, and that the indications thereon represent all Changes performed during the construction of the Project. At Final Completion, the As-Built and other Record Documents shall become the property of City.
3.11.4 Contractor, in concert with the Design Consultant and the Construction Manager, shall review Contractor's As-Built Documents for conformance with all current Changes prior to presenting its monthly Application For Payment. The monthly progress payment statement will not be accepted or processed by City unless the As-Built Documents are current and complete, and Approved by City.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
DOCUMENTS AND SAMPLES AT PROJECT SITE.
3.11.1 Contractor shall maintain one (1) set of As-Built Documents at the Site, which shall be kept up to date on a daily basis at all times during the performance of the Work. All performed changes, deletions or additions in the Work from that shown in the Contract Documents shall be recorded accurately and completely in the Record Documents. Upon Final Completion and as a condition to Final Paymentfinal payment, each sheet of the As-Built Documents and other Record Documents shall be signed and attested to by the Contractor’s Superintendent a representative of Contractor as being complete and accurate.
3.11.2 Contractor shall, at all times during performance of the Work, also maintain the following at the Site:
(i) The latest updated Construction Schedule approved by CityDistrict;
(ii) Shop Drawings, product data, and samples; and
(iii) All other required Submittals. At all times during the course of the Project, these documents shall be available to CityDistrict, the Construction Manager and the Design Consultant to audit, excerpt, or copy as they see fit. Upon Final Completion or termination of the Construction Contract, these documents shall be delivered to City in the format requested by the CityDistrict.
3.11.3 It shall be the responsibility of Contractor to maintain a current and complete record of all Changes performed during the progress of the Project construction. The record shall be in the form of a complete set of prints of the As-Built Documents on which daily recordings are made by Contractor, indicating in detail and dimension each variation from the original set of Contract Documents for and including all of the construction Work. At the completion of construction, Contractor shall, as a requirement of the Final Completion of the Work, certify that to the best of its knowledge, the As-Built Documents are true and accurate, and that the indications thereon represent all Changes performed during the construction of the Project. At the Final CompletionCompletion of the Work, the As-Built and other Record Documents shall become the property of CityDistrict.
3.11.4 Contractor, in concert with the Design Consultant and the Construction Manager, shall review Contractor's As-Built Documents for conformance with all current Changes prior to presenting its monthly Application For Payment. The monthly progress payment statement will not be accepted or processed by City District unless the As-Built Documents are current and complete, and Approved by CityDistrict.
3.11.5 At the Final Completion of the Work, all information annotated monthly on the As-Built Documents shall be fully incorporated by Contractor onto a set of mylar reproducibles furnished by Contractor. These As-Built Documents will become the permanent property of District at the Final Completion of the Work. If the As-Built Documents are prepared on a computer, then the revised computer files shall also be provided to District in the file format specified by District.
Appears in 2 contracts
Samples: Standard Construction Contract, Construction Contract
DOCUMENTS AND SAMPLES AT PROJECT SITE.
3.11.1 Contractor DBT shall maintain one (1) set of As-Built Documents at the Site, which shall be kept up to date on a daily basis during the performance of the Work. All performed changes, deletions or additions in the Work from that shown in the Contract Documents shall be recorded accurately and completely in the Record Documents. Upon Final Completion and as a condition to Final Payment, each sheet of the As-Built Documents and other Record Documents shall be signed and attested to by the ContractorDBT’s Superintendent as being complete and accurate.
3.11.2 Contractor DBT shall, at all times during performance of the Work, also maintain the following at the Site:
(i) The latest updated Construction Schedule approved by City;
(ii) Shop Drawings, product data, and samples; and
(iii) All other required Submittals. At all times during the course of the Project, these documents shall be available to City, the Construction Manager and the Design Consultant to audit, excerpt, or copy as they see fit. Upon Final Completion or termination of the Construction Design-Build Contract, these documents shall be delivered to City in the format requested by the City.
3.11.3 It shall be the responsibility of Contractor DBT to maintain a current and complete record of all Changes performed during the progress of the Project construction. The record shall be in the form of a complete set of prints of the As-Built Documents on which daily recordings are made by ContractorDBT, indicating in detail and dimension each variation from the original set of Contract Documents for all of the Work. At the completion of construction, Contractor DBT shall, as a requirement of the Final Completion of the Work, certify that to the best of its knowledge, the As-Built Documents are true and accurate, and that the indications thereon represent all Changes performed during the construction of the Project. At Final Completion, the As-Built and other Record Documents shall become the property of City.
3.11.4 ContractorDBT, in concert with the Design Consultant and the Construction Manager, shall review ContractorDBT's As-Built Documents for conformance with all current Changes prior to presenting its monthly Application For Payment. The monthly progress payment statement will not be accepted or processed by City unless the As-Built Documents are current and complete, and Approved by City.
3.11.5 At Final Completion, the DBT shall provided the fully As-Built Documents to the City. These As-Built Documents will become the permanent property of City at Final Completion. If the As-Built Documents are prepared on a computer, then the revised computer files shall also be provided to City in the file format specified by City.
Appears in 1 contract
Samples: Design Build Contract
DOCUMENTS AND SAMPLES AT PROJECT SITE.
3.11.1 (a) Contractor shall maintain one (1) 1 set of As-Built Documents Drawings at the Site, which shall be kept up to date on a daily basis during the performance of the Work. All performed changes, deletions or additions in the Work from that shown in the Contract Documents shall be recorded accurately and completely in the Record Documents. Upon Final Completion and as a condition to Final Paymentfinal payment, each sheet of the As-Built Documents Drawings and other Record Documents shall be signed and attested to by the Contractor’s Superintendent as being complete and accurate.
3.11.2 (b) Contractor shall, at all times during performance of the Work, also maintain the following at the Site:
: (i) The the latest updated Construction Schedule construction schedule approved by City;
HACLA; (ii) Shop Drawings, product data, and samples; and
and (iii) All all other required Submittalssubmittals. At all times during the course of the Project, these documents shall be available to CityHACLA, the Construction Project Manager and the Design Consultant Architect to audit, excerpt, or copy as they see fit. Upon Final Completion or termination of the Construction Contract, these documents shall be delivered to City HACLA in the format requested by the CityHACLA.
3.11.3 (c) It shall be the responsibility of Contractor to maintain a current and complete record of all Changes performed during the progress of the Project construction. The record shall be in the form of a complete set of prints of the As-Built Documents Drawings on which daily recordings are made by Contractor, indicating in detail and dimension each variation from the original set of Contract Documents for all of the Work. At the completion of construction, Contractor shall, as a requirement of the Final Completion of the WorkCompletion, certify that to the best of its knowledge, the As-Built Documents Drawings are true and accurate, and that the indications thereon represent all Changes performed during the construction of the Project. At Final Completion, the As-Built and other Record Documents shall become the property of CityHACLA.
3.11.4 Contractor, in concert with the Design Consultant and the Construction Manager, shall review Contractor's As-Built Documents for conformance with all current Changes prior to presenting its monthly Application For Payment. The monthly progress payment statement will not be accepted or processed by City unless the As-Built Documents are current and complete, and Approved by City.
Appears in 1 contract
Samples: Memorandum of Understanding