Documents for Technical Inspections Sample Clauses
Documents for Technical Inspections. At least five (5) Business Days before commencing the Technical Inspections, the Contractor is obliged to prepare and submit to the Client, in clear and self-contained format, all of the Contractor’s necessary documents, in particular:
(a) documentation of the as-built performance of the Facility with duly depicted Changes and manually demarked discrepancies depicting the as-built performance of construction;
(b) records and certificates of performed tests and revisions;
(c) geodetic surveying of the Facility, including the geometric plan;
(d) original construction daybook and assembly daybooks of the Subcontractors;
(e) necessary documentation for launching operation of the Facility (warranty certificates, operating manuals, attests, records from tests, revision reports, draft operating rules for the entire facility, which will include the individual operating rules of the Technological Equipment, etc.);
(f) documents proving the due training of the Client’s Personnel in operating the individual units of Technological Equipment and their maintenance and repair (including the handover of detailed instructions for use and operation). The Contractor’s documents listed above must always be handed over in four (4) hardcopy counterparts and in electronic form, unless stipulated otherwise in the Contract.