Draft Timeline Clause Samples
Draft Timeline. The table below summarises the key activities and anticipated milestones for the project covering the period from Strategic Initial Agreement completion through to the proposed facility becoming operational. Note that for the purposes of the timeline presented, this is based on the work undertaken in relation to the “purchase and refurbishment of alternative facilities” implementation option. It is anticipated that the other options would have a longer overall duration. Strategic Initial Agreement completed 27/08/2021 NHS Ayrshire and Arran internal governance 02/09/2021 Strategic Initial Agreement to Capital Investment Group 10/09/2021 Capital Investment Group meeting 06/10/2021 OBC / FBC development Sep 2021 to Feb 2022 Appointment of Contractor Sept / Oct 2021 NHS Ayrshire and Arran internal governance Feb 2022 OBC / FBC to Capital Investment Group Feb 2022 Capital Investment Group meeting Feb 2022 Construction programme Mar 2022 to Oct 2022 Commissioning and go live Oct 2022