Duties and Responsibilities of the PJM Board. In accordance with this Agreement, the PJM Board shall supervise and oversee all matters pertaining to the Interconnection and the LLC, and carry out such other duties as are herein specified, including but not limited to the following duties and responsibilities: i) As its primary responsibility, ensure that the President, the other officers of the LLC, and Office of the Interconnection perform the duties and responsibilities set forth in this Agreement, including but not limited to those set forth in Sections 9.2 through 9.4 and Section 10.4 in a manner consistent with (A) the safe and reliable operation of the Interconnection, (B) the creation and operation of a robust, competitive, and non- discriminatory electric power market in the PJM Control Area, and (C) the principle that a Member or group of Members shall not have undue influence over the operation of the Interconnection; ii) Select the Officers of the LLC; iii) Adopt budgets for the LLC; iv) Approve the Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning Protocol set forth in Schedule 6 of this Agreement. v) On its own initiative or at the request of a User Group as specified herein, submit to the Members Committee such proposed amendments to this Agreement or any Schedule hereto, or a proposed new Schedule, as it may deem appropriate; vi) Petition FERC to modify any provision of this Agreement or any Schedule or practice hereunder that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory under Section 206 of the Federal Power Act, subject to the right of any Member or the Members to intervene in any resulting proceedings; vii) Review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Control Area any change to rate design or to non-rate terms and conditions proposed by Transmission Owners for filing under Section 205 of the Federal Power Act. viii) If and to the extent it shall deem appropriate, intervene in any proceeding at FERC initiated by the Members in accordance with Section 11.5(b), and participate in other state and federal regulatory proceedings relating to the interests of the LLC; ix) Review, in accordance with Section 15.1.3, determinations of the Office of the Interconnection with respect to events of default; x) Assess against the other Members in proportion to their Weighted Interest an amount equal to any payment to the Office of the Interconnection, including interest thereon, as to which a Member is in default; xi) Establish reasonable sanctions for failure of a Member to comply with its obligations under this Agreement; xii) Direct the Office of the Interconnection on behalf of the LLC to take appropriate legal or regulatory action against a Member (A) to recover any unpaid amounts due from the Member to the Office of the Interconnection under this Agreement and to make whole any Members subject to an assessment as a result of such unpaid amount, or (B) as may otherwise be necessary to enforce the obligations of this Agreement; xiii) Resolve claims by a Member that the Reliability Committee established by the Reliability Assurance Agreement has exercised its responsibilities in a manner inconsistent with the creation and operation of a robust, competitive and non- discriminatory electric power market in the PJM Control Area, upon due consideration of the views of the Member and of the Reliability Committee, and of the need to preserve the reliability of electric service in the PJM Control Area. xiv) Solicit the views of Members on, and commission from time to time as it shall deem appropriate independent reviews of, (A) the performance of the PJM Interchange Energy Market, (B) compliance by Market Participants with the rules and requirements of the PJM Interchange Energy Market, and (C) the performance of the Office of the Interconnection under performance criteria proposed by the Members Committee and approved by the PJM Board; and xv) Terminate a Member as may be appropriate under the terms of this Agreement.
Appears in 2 contracts
Samples: Operating Agreement (Pp&l Inc), Operating Agreement (Pp&l Resources Inc)
Duties and Responsibilities of the PJM Board. In accordance with this Agreement, the PJM Board shall supervise and oversee all matters pertaining to the Interconnection and the LLC, and carry out such other duties as are herein specified, including but not limited to the following duties and responsibilities:
i) As its primary responsibility, ensure that the President, the other officers of the LLC, and Office of the Interconnection perform the duties and responsibilities set forth in this Agreement, including but not limited to those set forth in Sections 9.2 through 9.4 and Section 10.4 in a manner consistent with (A) the safe and reliable operation of the Interconnection, (B) the creation and operation of a robust, competitive, and non- non-discriminatory electric power market in the PJM Control Area, and (C) the principle that a Member or group of Members shall not have undue influence over the operation of the Interconnection;
ii) Select the Officers of the LLC;
iii) Adopt budgets for the LLC;
iv) Approve the Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning Protocol set forth in Schedule 6 of this Agreement.
v) On its own initiative or at the request of a User Group as specified herein, submit to the Members Committee such proposed amendments to this Agreement or any Schedule hereto, or a proposed new Schedule, as it may deem appropriate;
vi) Petition FERC to modify any provision of this Agreement or any Schedule or practice hereunder that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory under Section 206 of the Federal Power Act, subject to the right of any Member or the Members to intervene in any resulting proceedings;
vii) Review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Control Area any change to rate design or to non-rate terms and conditions proposed by Transmission Owners for filing under Section 205 of the Federal Power Act.
viii) If and to the extent it shall deem appropriate, intervene in any proceeding at FERC initiated by the Members in accordance with Section 11.5(b), and participate in other state and federal regulatory proceedings relating to the interests of the LLC;
ix) Review, in accordance with Section 15.1.3, determinations of the Office of the Interconnection with respect to events of default;
x) Assess against the other Members in proportion to their Weighted Interest an amount equal to any payment to the Office of the Interconnection, including interest thereon, as to which a Member is in default;
xi) Establish reasonable sanctions for failure of a Member to comply with its obligations under this Agreement;
xii) Direct the Office of the Interconnection on behalf of the LLC to take appropriate legal or regulatory action against a Member (A) to recover any unpaid amounts due from the Member to the Office of the Interconnection under this Agreement and to make whole any Members subject to an assessment as a result of such unpaid amount, or (B) as may otherwise be necessary to enforce the obligations of this Agreement;
xiii) Resolve claims by a Member that the Reliability Committee established by the Reliability Assurance Agreement has exercised its responsibilities in a manner inconsistent with the creation and operation of a robust, competitive and non- non-discriminatory electric power market in the PJM Control Area, upon due consideration of the views of the Member and of the Reliability Committee, and of the need to preserve the reliability of electric service in the PJM Control Area.
xiv) Solicit the views of Members on, and commission from time to time as it shall deem appropriate independent reviews of, (A) the performance of the PJM Interchange Energy Market, (B) compliance by Market Participants with the rules and requirements of the PJM Interchange Energy Market, and (C) the performance of the Office of the Interconnection under performance criteria proposed by the Members Committee and approved by the PJM Board; and
xv) Terminate a Member as may be appropriate under the terms of this Agreement.
Appears in 2 contracts
Samples: Operating Agreement (Pp&l Resources Inc), Operating Agreement (PPL Electric Utilities Corp)
Duties and Responsibilities of the PJM Board. In accordance with this Agreement, the PJM Board shall supervise and oversee all matters pertaining to the Interconnection and the LLC, and carry out such other duties as are herein specified, including but not limited to the following duties and responsibilities:
i) As its primary responsibility, ensure that the President, the other officers of the LLC, and Office of the Interconnection perform the duties and responsibilities set forth in this Agreement, including but not limited to those set forth in Sections 9.2 through 9.4 and Section 10.4 in a manner consistent with (A) the safe and reliable operation of the Interconnection, (B) the creation and operation of a robust, competitive, and non- non-discriminatory electric power market in the PJM Control Area, and (C) the principle that a Member or group of Members shall not have undue influence over the operation of the Interconnection;
ii) Select the Officers of the LLC;
iii) Adopt budgets for the LLC;
iv) Approve the Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning Protocol set forth in Schedule 6 of this Agreement.
v) On its own initiative or at the request of a User Group as specified herein, submit to the Members Committee such proposed amendments to this Agreement or any Schedule hereto, or a proposed new Schedule, as it may deem appropriate;
vi) Petition FERC to modify any provision of this Agreement or any Schedule or practice hereunder that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory under Section 206 of the Federal Power Act, subject to the right of any Member or the Members to intervene in any resulting proceedings;
vii) Review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Control Area any change to rate design or to non-rate terms and conditions proposed by Transmission Owners for filing under Section 205 of the Federal Power Act.
viii) If and to the extent it shall deem appropriate, intervene in any proceeding at FERC initiated by the Members in accordance with Section 11.5(b), and participate in other state and federal regulatory proceedings relating to the interests of the LLC;
ix) Review, in accordance with Section 15.1.3, determinations of the Office of the Interconnection with respect to events of default;
x) Assess against the other Members in proportion to their Weighted Interest an amount equal to any payment to the Office of the Interconnection, including interest thereon, as to which a Member is in default;
xi) Establish reasonable sanctions for failure of a Member to comply with its obligations under this Agreement;
; xii) Direct the Office of the Interconnection on behalf of the LLC to take appropriate legal or regulatory action against a Member (A) to recover any unpaid amounts due from the Member to the Office of the Interconnection under this Agreement and to make whole any Members subject to an assessment as a result of such unpaid amount, or (B) as may otherwise be necessary to enforce the obligations of this Agreement;
xiii) Resolve claims by a Member that the Reliability Committee established by the Reliability Assurance Agreement has exercised its responsibilities in a manner inconsistent with the creation and operation of a robust, competitive and non- discriminatory electric power market in the PJM Control Area, upon due consideration of the views of the Member and of the Reliability Committee, and of the need to preserve the reliability of electric service in the PJM Control Area.
xiv) Solicit the views of Members on, and commission from time to time as it shall deem appropriate independent reviews of, (A) the performance of the PJM Interchange Energy Market, (B) compliance by Market Participants with the rules and requirements of the PJM Interchange Energy Market, and (C) the performance of the Office of the Interconnection under performance criteria proposed by the Members Committee and approved by the PJM Board; and
xv) Terminate a Member as may be appropriate under the terms of this Agreement.
Appears in 1 contract
Duties and Responsibilities of the PJM Board. In accordance with this Agreement, the PJM Board shall supervise and oversee all matters pertaining to the Interconnection and the LLC, and carry out such other duties as are herein specified, including but not limited to the following duties and responsibilities:
i) As its primary responsibility, ensure that the President, the other officers of the LLC, and Office of the Interconnection perform the duties and responsibilities set forth in this Agreement, including but not limited to those set forth in Sections 9.2 through 9.4 and Section 10.4 in a manner consistent with (A) the safe and reliable operation of the Interconnection, (B) the creation and operation of a robust, competitive, and non- non-discriminatory electric power market in the PJM Control Area, and (C) the principle that a Member or group of Members shall not have undue influence over the operation of the Interconnection;
ii) Select the Officers of the LLC;
iii) Adopt budgets for the LLC;
iv) Approve the Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning Protocol set forth in Schedule 6 of this Agreement.;
v) On its own initiative or at the request of a User Group as specified herein, submit to the Members Committee such proposed amendments to this Agreement or any Schedule hereto, or a proposed new Schedule, as it may deem appropriate;
vi) Petition FERC to modify any provision of this Agreement or any Schedule or practice hereunder that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory under Section 206 of the Federal Power Act, subject to the right of any Member or the Members to intervene in any resulting proceedings;
vii) Review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Control Area any change to rate design or to non-rate terms and conditions proposed by Transmission Owners for filing under Section 205 of the Federal Power Act.;
viii) If and to the extent it shall deem appropriate, intervene in any proceeding at FERC initiated by the Members in accordance with Section 11.5(b), and participate in other state and federal regulatory proceedings relating to the interests of the LLC;
ix) Review, in accordance with Section 15.1.3, determinations of the Office of the Interconnection with respect to events of default;
x) Assess against the other Members in proportion to their Weighted Interest an amount equal to any payment to the Office of the Interconnection, including interest thereon, as to which a Member is in default;
xi) Establish reasonable sanctions for failure of a Member to comply with its obligations under this Agreement;
xii) Direct the Office of the Interconnection on behalf of the LLC to take appropriate legal or regulatory action against a Member (A) to recover any unpaid amounts due from the Member to the Office of the Interconnection under this Agreement and to make whole any Members subject to an assessment as a result of such unpaid amount, or (B) as may otherwise be necessary to enforce the obligations of this Agreement;
xiii) Resolve claims by a Member that the Reliability Committee established by the Reliability Assurance Agreement has exercised its responsibilities in a manner inconsistent with the creation and operation of a robust, competitive and non- non-discriminatory electric power market in the PJM Control Area, upon due consideration of the views of the Member and of the Reliability Committee, and of the need to preserve the reliability of electric service in the PJM Control Area.;
xiv) Solicit the views of Members on, and commission from time to time as it shall deem appropriate independent reviews of, (Aa) the performance of the PJM Interchange Energy Market, (Bb) compliance by Market Participants with the rules and requirements of the PJM Interchange Energy Market, and (Cc) the performance of the Office of the Interconnection under performance criteria proposed by the Members Committee and approved by the PJM Board; and
xv) Terminate a Member as may be appropriate under the terms of this Agreement.
Appears in 1 contract
Duties and Responsibilities of the PJM Board. In accordance with this Agreement, the PJM Board shall supervise and oversee all matters pertaining to the Interconnection and the LLC, and carry out such other duties as are herein specified, including but not limited to the following duties and responsibilities:: Issued By: Xxxxxxx X. Drom Effective: November 10, 2000 Vice President, General Counsel Issued On: November 9, 2000 PJM Interconnection, L.L.C. Original Sheet No. 28 First Revised Rate Schedule FERC No. 24
i) As its primary responsibility, ensure that the President, the other officers of the LLC, and Office of the Interconnection perform the duties and responsibilities set forth in this Agreement, including but not limited to those set forth in Sections 9.2 through 9.4 and Section 10.4 in a manner consistent with (A) the safe and reliable operation of the Interconnection, (B) the creation and operation of a robust, competitive, and non- non-discriminatory electric power market in the PJM Control Area, and (C) the principle that a Member or group of Members shall not have undue influence over the operation of the Interconnection;
ii) Select the Officers of the LLC;
iii) Adopt budgets for the LLC;
iv) Approve the Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning Protocol set forth in Schedule 6 of this Agreement.;
v) On its own initiative or at the request of a User Group as specified herein, submit to the Members Committee such proposed amendments to this Agreement or any Schedule hereto, or a proposed new Schedule, as it may deem appropriate;
vi) Petition FERC to modify any provision of this Agreement or any Schedule or practice hereunder that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory under Section 206 of the Federal Power Act, subject to the right of any Member or the Members to intervene in any resulting proceedings;
vii) Review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Control Area any change to rate design or to non-rate terms and conditions proposed by Transmission Owners for filing under Section 205 of the Federal Power Act.;
viii) If and to the extent it shall deem appropriate, intervene in any proceeding at FERC initiated by the Members in accordance with Section 11.5(b), and participate in other state and federal regulatory proceedings relating to the interests of the LLC;
ix) Review, in accordance with Section 15.1.3, determinations of the Office of the Interconnection with respect to events of default;
x) Assess against the other Members in proportion to their Weighted Interest an amount equal to any payment to the Office of the Interconnection, including interest thereon, as to which a Member is in default;
xi) Establish reasonable sanctions for failure of a Member to comply with its obligations under this Agreement;
xii) Direct the Office of the Interconnection on behalf of the LLC to take appropriate legal or regulatory action against a Member (A) to recover any unpaid amounts due from the Member to the Office of the Interconnection under this Agreement and to make whole any Members subject to an assessment as a result of such unpaid amount, or (B) as may otherwise be necessary to enforce the obligations of this Agreement;
xiii) Resolve claims by a Member that the Reliability Committee established by the Reliability Assurance Agreement has exercised its responsibilities in a manner inconsistent with the creation and operation of a robust, competitive and non- discriminatory electric power market in the PJM Control Area, upon due consideration of the views of the Member and of the Reliability Committee, and of the need to preserve the reliability of electric service in the PJM Control Area.
xiv) Solicit the views of Members on, and commission from time to time as it shall deem appropriate independent reviews of, (A) the performance of the PJM Interchange Energy Market, (B) compliance by Market Participants with the rules and requirements of the PJM Interchange Energy Market, and (C) the performance of the Office of the Interconnection under performance criteria proposed by the Members Committee and approved by the PJM Board; and
xv) Terminate a Member as may be appropriate under the terms of this Agreement.
Appears in 1 contract
Samples: Operating Agreement (PPL Corp)
Duties and Responsibilities of the PJM Board. In accordance with this Agreement, the PJM Board shall supervise and oversee all matters pertaining to the Interconnection and the LLC, and carry out such other duties as are herein specified, including but not limited to the following duties and responsibilities:
i) As its primary responsibility, ensure that the President, the other officers of the LLC, and Office of the Interconnection perform the duties and responsibilities set forth in this Agreement, including but not limited to those set forth in Sections 9.2 through 9.4 and Section 10.4 in a manner consistent with (A) the safe and reliable operation of the Interconnection, (B) the creation and operation of a robust, competitive, and non- non-discriminatory electric power market in the PJM Control Area, and (C) the principle that a Member or group of Members shall not have undue influence over the operation of the Interconnection;
ii) Select the Officers of the LLC;
iii) Adopt budgets for the LLC;
iv) Approve the Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning Protocol set forth in Schedule 6 of this Agreement.
v) On its own initiative or at the request of a User Group as specified herein, submit to the Members Committee such proposed amendments to this Agreement or any Schedule hereto, or a proposed new Schedule, as it may deem appropriate;
vi) Petition FERC to modify any provision of this Agreement or any Schedule or practice hereunder that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory under Section 206 of the Federal Power Act, subject to the right of any Member or the Members to intervene in any resulting proceedings;
vii) Review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Control Area any change to rate design or to non-rate terms and conditions proposed by Transmission Owners for filing under Section 205 of the Federal Power Act.
viii) If and to the extent it shall deem appropriate, intervene in any proceeding at FERC initiated by the Members in accordance with Section 11.5(b), and participate in other state and federal regulatory proceedings relating to the interests of the LLC;
; ix) Review, in accordance with Section 15.1.3, determinations of the Office of the Interconnection with respect to events of default;
x) Assess against the other Members in proportion to their Weighted Interest an amount equal to any payment to the Office of the Interconnection, including interest thereon, as to which a Member is in default;
xi) Establish reasonable sanctions for failure of a Member to comply with its obligations under this Agreement;
xii) Direct the Office of the Interconnection on behalf of the LLC to take appropriate legal or regulatory action against a Member (A) to recover any unpaid amounts due from the Member to the Office of the Interconnection under this Agreement and to make whole any Members subject to an assessment as a result of such unpaid amount, or (B) as may otherwise be necessary to enforce the obligations of this Agreement;
xiii) Resolve claims by a Member that the Reliability Committee established by the Reliability Assurance Agreement has exercised its responsibilities in a manner inconsistent with the creation and operation of a robust, competitive and non- discriminatory electric power market in the PJM Control Area, upon due consideration of the views of the Member and of the Reliability Committee, and of the need to preserve the reliability of electric service in the PJM Control Area.
xiv) Solicit the views of Members on, and commission from time to time as it shall deem appropriate independent reviews of, (A) the performance of the PJM Interchange Energy Market, (B) compliance by Market Participants with the rules and requirements of the PJM Interchange Energy Market, and (C) the performance of the Office of the Interconnection under performance criteria proposed by the Members Committee and approved by the PJM Board; and
xv) Terminate a Member as may be appropriate under the terms of this Agreement.