ESD Tests. Emergency shutdown (“ESD”) systems will be tested during precommissioning, commissioning or operation with LNG/Natural Gas in the system as follows. If unplanned inadvertent ESD trips occur during initial operations then the below corresponding ESD test will be deemed completed: a. Tanks will be loaded to test the high level shutdown function; the test shall be conducted to verify liquefaction shutdown; b. ESD shutdown will be initiated to ensure that each LNG Train is shutdown safely and in proper sequence during operation; and c. Power failure simulation shutdown will be initiated to ensure a safe, smooth shutdown sequence is achieved during LNG Train operation.
Appears in 12 contracts
Samples: Lump Sum Turnkey Agreement, Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.), Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)
ESD Tests. Emergency shutdown (“ESD”) systems will be tested during precommissioningpre-commissioning, commissioning or operation with LNG/Natural Gas in the system as follows. If unplanned inadvertent ESD trips occur during initial operations operations, then the below corresponding ESD test will be deemed completed:
a. Tanks will be loaded to test the high level shutdown function; the test shall be conducted to determine and verify liquefaction shutdown;
b. ESD shutdown will be initiated to ensure that each LNG Train Plant is shutdown safely and in proper sequence during operation; and
c. Power failure simulation shutdown will be initiated to ensure that a safe, smooth shutdown sequence is achieved during LNG Train Plant operation.
Appears in 4 contracts
Samples: Lump Sum Turnkey Agreement (Tellurian Inc. /De/), Lump Sum Turnkey Agreement (Tellurian Inc. /De/), Lump Sum Turnkey Agreement (Tellurian Inc. /De/)
ESD Tests. Emergency shutdown (“ESD”) systems will be tested during precommissioning, commissioning or operation with LNG/Natural Gas in the system as follows. If unplanned inadvertent ESD trips occur during initial operations then the below corresponding ESD test will be deemed completed:
a. Tanks LNG Tank B will be loaded to test the high level shutdown function; the test shall be conducted to verify liquefaction shutdown;
b. ESD shutdown will be initiated to ensure that each LNG Train 3 is shutdown shut down safely and in proper sequence during operation; and
c. Power failure simulation shutdown will be initiated to ensure a safe, smooth shutdown sequence is achieved during LNG Train operation.
Appears in 3 contracts
Samples: Fixed Price Separated Turnkey Agreement (Cheniere Corpus Christi Holdings, LLC), Fixed Price Separated Turnkey Agreement (Corpus Christi Pipeline GP, LLC), Fixed Price Separated Turnkey Agreement (Cheniere Energy Inc)
ESD Tests. Emergency shutdown (“ESD”) systems will be tested during precommissioningpre-commissioning, commissioning or operation with LNG/Natural Gas in the system as follows. If unplanned inadvertent ESD trips occur during initial operations then the below corresponding ESD test will be deemed completed:
a. Tanks will be loaded to test the high level shutdown function; the test shall be conducted to verify liquefaction shutdown;
b. ESD shutdown will be initiated to ensure that each LNG Train is shutdown safely and in proper sequence during operation; and
c. Power failure simulation shutdown will be initiated to ensure a safe, smooth shutdown sequence is achieved during LNG Train operation.
Appears in 1 contract
Samples: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC)