ESTIMATED COSTS OF INTERCONNECTION FACILITIES. SERVICE AGREEMENT NO. 2591 The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below. As described in the Facilities Study for the Small Generating Facility, the estimates provided herein: Assume: • 5X10 construction work week; • outages are available; • permitting is not required; and • existing equipment to remain is functional. Exclude (as applicable): • discussions and negotiations of issued interconnection study; • application fees; • applicable surcharges;