Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”): (a) The Supplier fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten (10) Business Days after written notice of such failure from the Buyer. (b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period. (c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
Appears in 4 contracts
Samples: Long Term Reliability Services Contract, E Lt 1 Contract, E Lt 1 Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten (10) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.. Draft
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
Appears in 2 contracts
Samples: E Lt 1 Contract, Long Term Reliability Services Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due payment, or deliver and/or maintain the Completion and Performance Security as required under this AgreementAgreement when due, if such failure is not remedied within ten five (105) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer. For certainty, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure periodmaterial covenants include Section 2.6(f).
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended .
(d) Any representation made by a further the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days if after receipt by the Supplier of written notice of such fact from the Buyer.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable, or unless there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement.
(f) The Supplier amalgamates with, or merges with or into, or transfers all or substantially all of its assets to, another Person unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within thirty (30) days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is diligently remedying such failure adjudicated bankrupt or cessation insolvent or any substantial part of the Supplier’s property is sequestered, and such failure decree continues undischarged and unstayed for a period of thirty (30) days after the entry thereof. A petition, proceeding or cessation filing is capable made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of being corrected during any of their respective debts pursuant to the provisions of any Insolvency Legislation, and such extended cure periodpetition, proceeding or filing is not dismissed or withdrawn within thirty (30) days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation, or consents to the appointment of a receiver, manager, receiver-manager, monitor, trustee in bankruptcy, or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provision of any Insolvency Legislation.
(i) The Supplier has defaulted under one or more obligations for indebtedness to other Persons, resulting in obligations for indebtedness in an aggregate amount of more than the greater of 5% of its Tangible Net Worth and $2,000,000 becoming immediately due and payable, unless: (A) such default is remedied within fifteen
Appears in 1 contract
Samples: Demand Response Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as if required under this Agreement, if such failure is not remedied within ten five (105) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.period or such other period as the Parties may agree in their discretion.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days or such reasonable period of time as the Parties agree may be required in the circumstances to remedy the default if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure periodperiod or such other period as the Parties may agree in their discretion.
(d) Any representation made by the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days after receipt by the Supplier of written notice of such fact from the Buyer, provided that such cure period (i) shall be extended for a further period of thirty (30) Business Days and (ii) may be extended by such further period of time as the Buyer in its sole and absolute discretion determines is reasonable, if, in each case, the Supplier is diligently correcting such breach and such breach is capable of being corrected during such extended cure period or such other period as the Parties may agree in their discretion. For certainty, notwithstanding the receipt by the Buyer of a qualified representation by the Supplier with respect to any statement referred to in Sections 7.1(a) to 7.1(h) inclusive, the Buyer may, in its sole and absolute discretion, require the Supplier, within the time limits set out in this Section 10.1(d), to cure or remove any such qualification to such statement.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable, or unless, in the case of the Supplier, there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement.
(f) The Supplier amalgamates with, or merges with or into, or transfers the Facility or all or substantially all of its assets to, another Person unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within thirty (30) days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is adjudicated bankrupt or insolvent or any substantial part of the Supplier’s property is sequestered, and such decree, judgment or order continues undischarged and unstayed for a period of thirty (30) days after the entry thereof. A petition, proceeding or filing is made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of any of its debts pursuant to the provisions of any Insolvency Legislation, and such petition, proceeding or filing is not dismissed or withdrawn within thirty (30) days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation, or consents to the appointment of a receiver, manager, receiver-manager, monitor, trustee in bankruptcy or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provisions of any Insolvency Legislation.
(i) [intentionally deleted]
(j) The Supplier has made a Facility Amendment that has not first been consented to by the Buyer and that has not been removed within ten (10) Business Days after such Facility Amendment occurred.
(k) Any of the defaults described in Sections 15.6(d), 15.6(f)(i) or 15.7(d).
(l) If at any time the OCRF is less than 0.95.
(m) The ALLOP UCAP is less than 1750 MW in respect of any Settlement Month during the Term.
(n) The Supplier undergoes a change in Control (except as contemplated pursuant to Sections 16.6).
(o) The Supplier assigns this Agreement except in accordance with Section 16.5.
(p) More than ten (10) Must-Offer Non-Performance Days occur cumulatively during the Term.
Appears in 1 contract
Samples: Energy Supply Agreement
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten (10) Business Days after written notice of such failure from the Buyer.Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.period.
Appears in 1 contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):): Draft
(a) The Supplier fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten (10) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
Appears in 1 contract
Samples: E Lt 1 Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due due, or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten five (105) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
(d) Any representation made by the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days after receipt by the Supplier of written notice of such fact from the Buyer, provided that such cure period (i) shall be extended for a further period of thirty (30) Business Days and (ii) may be extended by such further period of time as the Buyer in its sole and absolute discretion determines is reasonable, if, in each case, the Supplier is diligently correcting such breach and such breach is capable of being corrected during such extended cure period. For certainty, notwithstanding the receipt by the Buyer of a qualified representation by the Supplier with respect to any statement referred to in Sections 7.1(a) to 7.1(h) inclusive, the Buyer may, in its sole and absolute discretion, require the Supplier, within the time limits set out in this Section 10.1(d), to cure or remove any such qualification to such statement.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable, or unless, in the case of the Supplier, there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement.
(f) The Supplier amalgamates with, or merges with or into, or transfers the Facility or all or substantially all of its assets to, another Person other than the Buyer or its nominee unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within thirty (30) days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is adjudicated bankrupt or insolvent or any substantial part of the Supplier’s property is sequestered, and such decree, judgment or order continues undischarged and unstayed for a period of thirty (30) days after the entry thereof. A petition, proceeding or filing is made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of any of its debts pursuant to the provisions of any Insolvency Legislation, and such petition, proceeding or filing is not dismissed or withdrawn within thirty (30) days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation, or consents to the appointment of a receiver, manager, receiver-manager, monitor, trustee in bankruptcy, or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provisions of any Insolvency Legislation.
(i) The Supplier has defaulted under one or more obligations for indebtedness to other Persons, resulting in obligations for indebtedness in an aggregate amount of more than the greater of: (1) five percent (5%) of its Tangible Net Worth and (2) $50,000/MW multiplied by the Annual Average Contract Capacity becoming immediately due and payable, unless: (A) such default is remedied within fifteen
Appears in 1 contract
Samples: Clean Energy Supply Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due payment, or deliver and/or maintain the Completion and Performance Security as required under this AgreementAgreement when due, if such failure is not remedied within ten five (105) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except other than the covenant set forth in Section 3.1(b) or to the extent constituting that such failure to perform constitutes a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer. For greater certainty, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure periodmaterial covenants include Section 2.6(d).
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended .
(d) Any representation made by a further the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days if after receipt by the Supplier of written notice of such fact from the Buyer.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable, or unless there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement.
(f) The Supplier amalgamates with, or merges with or into, or transfers all or substantially all of its assets to, another Person unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within thirty (30) days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is diligently remedying such failure adjudicated bankrupt or cessation insolvent or any substantial part of the Supplier’s property is sequestered, and such failure decree continues undischarged and unstayed for a period of thirty (30) days after the entry thereof. A petition, proceeding or cessation filing is capable made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of being corrected during any of their respective debts pursuant to the provisions of any Insolvency Legislation, and such extended cure periodpetition, proceeding or filing is not dismissed or withdrawn within thirty (30) days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation, or consents to the appointment of a receiver, manager, receiver-manager, monitor, trustee in bankruptcy, or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provision of any Insolvency Legislation.
(i) The Supplier has defaulted under one or more obligations for indebtedness to other Persons, resulting in obligations for indebtedness in an aggregate amount of more than the greater of 5% of its Tangible Net Worth and $2,000,000 becoming immediately due and payable, unless: (A) such default is remedied within fifteen
Appears in 1 contract
Samples: Demand Side Management Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten (10) Business Days after written notice of such failure from the BuyerSponsor.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the BuyerSponsor, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the BuyerSponsor, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
(d) Any representation made by the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days after receipt by the Supplier of written notice of such fact from the Sponsor, provided that such cure period (i) shall be extended for a further period of thirty (30) Business Days and (ii) may be extended by such further period of time as the Sponsor in its sole and absolute discretion determines is reasonable, if, in each case, the Supplier is diligently correcting such breach and such breach is capable of being corrected during such extended cure period. For certainty, notwithstanding the receipt by the Sponsor of a qualified representation by the Supplier with respect to any statement referred to in Sections 7.1(a) to 7.1(h) inclusive, the Sponsor may, in its sole and absolute discretion, require the Supplier, within the time limits set out in this Section 10.1(d), to cure or remove any such qualification to such statement.
Appears in 1 contract
Samples: Energy Storage Facility Agreement
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due or due, or, subject to Section 10.1(r), deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten five (105) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
(d) Any representation made by the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days after receipt by the Supplier of written notice of such fact from the Buyer, provided that such cure period (i) shall be extended for a further period of thirty (30) Business Days and (ii) may be extended by such further period of time as the Buyer in its sole and absolute discretion determines is reasonable, if, in each case, the Supplier is diligently correcting such breach and such breach is capable of being corrected during such extended cure period. For certainty, notwithstanding the receipt by the Buyer of a qualified representation by the Supplier with respect to any statement referred to in Sections 7.1(a) to 7.1(h), inclusive, the Buyer may, in its sole and absolute discretion, require the Supplier, within the time limits set out in this Section 10.1(d), to cure or remove any such qualification to such statement.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable, or unless, in the case of the Supplier, there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement.
(f) The Supplier amalgamates with, or merges with or into, or transfers the Facility or all or substantially all of its assets to, another Person unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within thirty (30) days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is adjudicated bankrupt or insolvent or any substantial part of the Supplier’s property is sequestered, and such decree, judgment or order continues undischarged and unstayed for a period of thirty (30) days after the entry thereof. A petition, proceeding or filing is made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of any of its debts pursuant to the provisions of any Insolvency Legislation, and such petition, proceeding or filing is not dismissed or withdrawn within thirty (30) days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation, or consents to the appointment of a receiver, manager, receiver-manager, monitor, trustee in bankruptcy, or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provisions of any Insolvency Legislation.
(i) The Supplier has defaulted under one or more obligations for indebtedness to other Persons, resulting in obligations for indebtedness in an aggregate amount of more than the greatest of: (1) five percent (5%) of its Tangible Net Worth, (2) $50,000/MW multiplied by the Annual Average Contract Capacity (as would be determined from and after the Contract Facility COD), and (3) $2,000,000, becoming immediately due and payable, unless: (A) such default is remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such default and such default is capable of being cured during such extended cure period; or (B) the Supplier has satisfied the Buyer that such default does not have a Material Adverse Effect on the Supplier’s ability to perform its obligations under this Agreement.
(j) The Supplier has made a Contract Facility Amendment that has not first been consented to by the Buyer and that has not been removed within ten (10) Business Days after such Contract Facility Amendment occurred.
(k) The Contract Facility COD has not occurred on or before the date which is one
(1) year after the Milestone Date for Commercial Operation of the Contract Facility, unless the Supplier has, on or prior to such one year date, paid all liquidated damages accruing to such one year date pursuant to Section 2.5 and the full amount of the required Completion and Performance Security is being held by the Buyer in accordance with Section 6.1.
(l) The Contract Facility COD has not occurred on or before the date which is eighteen (18) months after the Milestone Date for Commercial Operation of the Contract Facility.
(m) Either of the defaults described in Sections 15.6(d) and 15.6(f)(i) has occurred.
(n) The Availability is less than: (i) seventy percent (70%) in the second year after Contract Facility COD, (ii) seventy-five percent (75%) during the third year after Contract Facility COD, or (iii) eighty percent (80%) during the fourth and each succeeding year thereafter.
(o) The Supplier undergoes a change in Control without first obtaining the written approval of the Buyer if required pursuant to Sections 16.6 or 16.7.
(p) The Supplier assigns this Agreement without first obtaining the consent of the Buyer, if required pursuant to this Agreement.
(q) The Supplier has not disclosed each actual or potential Conflict of Interest (as that term is defined in the RFP) and, if any such actual or potential Conflict of Interest is capable of being remedied, it has not been remedied within fifteen (15) Business Days after written notice of such nondisclosure from the Buyer.
(r) The Supplier has failed to provide the First Period Amount, the Second Period Amount, the Third Period Amount, the Fourth Period amount or the Fifth Period Amount by the dates required in Sections 6.1(b)(i)-6.1(b)(v) respectively.
Appears in 1 contract
Samples: Peking Generation Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten (10) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
Appears in 1 contract
Samples: Medium Term Capacity Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due payment, or deliver and/or maintain the Completion and Performance Security as required under this AgreementAgreement when due, if such failure is not remedied within ten five (105) Business Days after written notice of such failure from the Buyer.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the Buyer, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, in a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the Buyer, provided that such cure period shall be extended .
(d) Any representation made by a further the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days if after receipt by the Supplier of written notice of such fact from the Buyer.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable or unless there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement. York Region DR Contract Released November 30, 2005
(f) The Supplier amalgamates with, or merges with or into, or transfers all or substantially all of its assets to, another Person unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within thirty (30) days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is diligently remedying such failure adjudicated bankrupt or cessation insolvent or any substantial part of the Supplier’s property is sequestered, and such failure decree continues undischarged and unstayed for a period of thirty (30) days after the entry thereof. A petition, proceeding or cessation filing is capable made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of any of their respective debts pursuant to the provisions of any Insolvency Legislation, and such petition, proceeding or filing is not dismissed or withdrawn within thirty (30) days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation or consents to the appointment of a receiver, manager, receiver-manager, monitor, trustee in bankruptcy, or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provision of any Insolvency Legislation.
(i) The Supplier has made a Proposal Amendment that has not first been consented to by the Buyer.
(j) The first Commercial Operation Date for the Project has not occurred on or before the first day of the Season that follows the Season in which the first Commercial Operation Milestone Date is scheduled to occur, unless the Supplier has, on or prior to such date, paid all liquidated damages accruing to such date pursuant to Section 2.3 and the full amount of the required Completion and Performance Security is being corrected during held by the Buyer in accordance with Section 5.1.
(k) The first Commercial Operation Date has not occurred on or before the last day of the Season that follows the Season in which the first Commercial Operation Milestone Date is scheduled to occur.
(l) Either of the defaults described in Sections 13.6(d) and 13.6(f) has occurred.
(m) The Availability is less than ninety-five percent (95%).
(n) The Supplier fails to deliver any Curtailment whatsoever in response to an Operational Directive as required by Section 2.6(c). York Region DR Contract Released November 30, 2005
(o) The Supplier undergoes a change in Control without first obtaining the written approval of the Buyer if required pursuant to Section 14.6.
(p) The Supplier assigns this Agreement without first obtaining such extended cure periodconsent of the Buyer if required pursuant to this Agreement.
(q) The Supplier amends or modifies the Measurement and Verification Plan without the consent of the Buyer or replaces the Verification Consultant without the consent of the Buyer.
Appears in 1 contract
Samples: Demand Response Contract
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier fails to make any payment when due or deliver deliver, and/or maintain maintain, the Completion and Performance Security as and if required under this Agreement, if such failure is not remedied within ten (10) 10 Business Days after written notice of such failure from the BuyerSponsor.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) 15 Business Days after written notice of such failure from the BuyerSponsor, provided that such cure period shall be extended by a further fifteen (15) 15 Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier or the Facility and is not remedied within thirty (30) 30 Business Days after receipt by the Supplier of written notice of such failure or cessation from the BuyerSponsor, provided that such cure period shall be extended by a further thirty (30) 30 Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
(d) Any representation made by the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within 30 Business Days after receipt by the Supplier of written notice of such fact from the Sponsor, provided that such cure period shall be extended by a further 30 Business Days if the Supplier, in the reasonable opinion of the Sponsor, is diligently correcting such breach and such breach is capable of being corrected during such extended cure period.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable, or unless there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement.
(f) The Supplier amalgamates with, or merges with or into, or transfers the Facility or all or substantially all of its assets to, another Person unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within 30 days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is adjudicated bankrupt or insolvent or any substantial part of the Supplier’s property is sequestered, and such decree, judgment or order continues undischarged and unstayed for a period of 30 days after the entry thereof. A petition, proceeding or filing is made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of any of its debts pursuant to the provisions of any Insolvency Legislation, and such petition, proceeding or filing is not dismissed or withdrawn within 30 days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation, or consents to the appointment of a receiver, manager, receiver- manager, monitor, trustee in bankruptcy or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provisions of any Insolvency Legislation.
(i) The Supplier has made a Facility Amendment that has not first been consented to by the Sponsor (other than in instances where such consent has been unreasonably withheld) and that has not been removed within ten (10) Business Days after such Facility Amendment occurred.
(j) The Supplier undergoes a change in Control without first obtaining the written approval of the Sponsor if required pursuant to this Agreement.
(k) The Supplier assigns this Agreement without first obtaining the consent of the Sponsor, if required pursuant to this Agreement.
Appears in 1 contract
Samples: Power Purchase Agreement
Events of Default by the Supplier. Each of the following will constitute an Event of Default by the Supplier (each, a “Supplier Event of Default”):
(a) The Supplier or the Guarantor fails to make any payment when due or deliver and/or maintain the Completion and Performance Security as required under this Agreement, if such failure is not remedied within ten five (105) Business Days after written notice of such failure from the BuyerSponsor.
(b) The Supplier fails to perform any material covenant or obligation set forth in this Agreement (except to the extent constituting a separate Supplier Event of Default) if such failure is not remedied within fifteen (15) Business Days after written notice of such failure from the BuyerSponsor, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such failure and such failure is capable of being cured during such extended cure period.
(c) The Supplier fails or ceases to hold a valid licence, permit, certificate, registration, authorization, consent or approval issued by a Governmental Authority where such failure or cessation results in, or could be reasonably expected to result in, a Material Adverse Effect on the Supplier and is not remedied within thirty (30) Business Days after receipt by the Supplier of written notice of such failure or cessation from the BuyerSponsor, provided that such cure period shall be extended by a further thirty (30) Business Days if the Supplier is diligently remedying such failure or cessation and such failure or cessation is capable of being corrected during such extended cure period.
(d) Any representation made by the Supplier in this Agreement is not true or correct in any material respect when made and is not made true or correct in all material respects within thirty (30) Business Days after receipt by the Supplier of written notice of such fact from the Sponsor, provided that such cure period (i) shall be extended for a further period of thirty (30) Business Days and (ii) may be extended by such further period of time as the Sponsor in its sole and absolute discretion determines is reasonable, if, in each case, the Supplier is diligently correcting such breach and such breach is capable of being corrected during such extended cure period. For certainty, notwithstanding the receipt by the Sponsor of a qualified representation by the Supplier with respect to any statement referred to in Sections 7.1(a) to 7.1(k) inclusive, the Sponsor may, in its sole and absolute discretion, require the Supplier, within the time limits set out in this Section 10.1(d), to cure or remove any such qualification to such statement.
(e) An effective resolution is passed or documents are filed in an office of public record in respect of, or a judgment or order is issued by a court of competent jurisdiction ordering, the dissolution, termination of existence, liquidation or winding up of the Supplier, unless such filed documents are immediately revoked or otherwise rendered inapplicable, or unless there has been a permitted and valid assignment of this Agreement by the Supplier under this Agreement to a Person which is not dissolving, terminating its existence, liquidating or winding up and such Person has assumed all of the Supplier’s obligations under this Agreement.
(f) The Supplier amalgamates with, or merges with or into, or transfers the Facility or all or substantially all of its assets to, another Person unless, at the time of such amalgamation, merger or transfer, there has been a permitted and valid assignment hereof by the Supplier under this Agreement to the resulting, surviving or transferee Person and such Person has assumed all of the Supplier’s obligations under this Agreement.
(g) A receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy of the Supplier or of any of the Supplier’s property is appointed by a Governmental Authority or pursuant to the terms of a debenture or a similar instrument, and such receiver, manager, receiver-manager, liquidator, monitor or trustee in bankruptcy is not discharged or such appointment is not revoked or withdrawn within thirty (30) days of the appointment. By decree, judgment or order of a Governmental Authority, the Supplier is adjudicated bankrupt or insolvent or any substantial part of the Supplier’s property is sequestered, and such decree, judgment or order continues undischarged and unstayed for a period of thirty (30) days after the entry thereof. A petition, proceeding or filing is made against the Supplier seeking to have the Supplier declared bankrupt or insolvent, or seeking adjustment or composition of any of its debts pursuant to the provisions of any Insolvency Legislation, and such petition, proceeding or filing is not dismissed or withdrawn within thirty (30) days.
(h) The Supplier makes an assignment for the benefit of its creditors generally under any Insolvency Legislation, or consents to the appointment of a receiver, manager, receiver-manager, monitor, trustee in bankruptcy, or liquidator for all or part of its property or files a petition or proposal to declare bankruptcy or to reorganize pursuant to the provisions of any Insolvency Legislation.
(i) The Supplier has defaulted under one or more obligations for indebtedness to other Persons, resulting in obligations for indebtedness in an aggregate amount of more than the greater of: (1) five percent (5%) of its Tangible Net Worth and (2) $50,000/MW multiplied by the Contract Capacity becoming immediately due and payable, unless: (A) such default is remedied within fifteen (15) Business Days after written notice of such failure from the Sponsor, provided that such cure period shall be extended by a further fifteen (15) Business Days if the Supplier is diligently remedying such default and such default is capable of being cured during such extended cure period; or (B) the Supplier has satisfied the Sponsor that such default does not have a Material Adverse Effect on the Supplier’s ability to perform its obligations under this Agreement.
(j) The Supplier has made a Facility Amendment that has not first been consented to by the Sponsor and that has not been removed within ten (10) Business Days after such Facility Amendment occurred.
(k) The COD has not occurred on or before the date which is eighteen (18) months after the Milestone Date for Commercial Operation of the Facility.
(l) The event of default described in Section 15.6(g) has occurred.
(m) The event of default described in Section 4 of Exhibit G has occurred.
(n) The Supplier undergoes a change in Control without first obtaining the written approval of the Sponsor if required pursuant to Sections 16.6 or 16.7.
(o) The Supplier assigns this Agreement without first obtaining the consent of the Sponsor, if required pursuant to this Agreement.
(p) The Supplier has not disclosed each actual or potential Conflict of Interest (as that term is defined in the RFP) and, if any such actual or potential Conflict of Interest is capable of being remedied, it has not been remedied within fifteen (15) Business Days after written notice of such nondisclosure from the Sponsor.
Appears in 1 contract
Samples: Energy Storage Facility Agreement