EXCAVATION OF ROAD CROSS SECTION. 1. All grubbing and clearing shall be completed prior to the beginning of any excavation. 2. Surface organic layer and ash cap (surface xxxxxxx-xxxxx soils with low gravel content) will be bladed to the side of the road and not incorporated into fills. 3. Wasted soils and organic layer will be shaped and spread to natural contours at locations approved by the Forest Officer. 4. When excavating on tangents and when balanced section construction is indicated, the following table will be used as a guideline to determine if sufficient excavation of road solid has occurred. Tolerances for road solid will be +1.0 feet and -0.5 feet.
Appears in 49 contracts
Samples: Timber Sale Contract, Timber Sale Contract, Timber Sale Contract
EXCAVATION OF ROAD CROSS SECTION. 1. All grubbing and clearing shall be completed prior to the beginning of any excavation.
2. Surface organic layer and ash cap (surface xxxxxxx-xxxxx soils with low gravel content) will be bladed to the side of the road and not incorporated into fills.
3. Wasted soils and organic layer will be shaped and spread to natural contours at locations approved by the Forest Officer.
4. When excavating on tangents and when balanced section construction is indicated, the following table will be used as a guideline to determine if sufficient excavation of road solid has occurred. Tolerances Xxxxx- xxxxx for road solid will be +1.0 feet and -0.5 feet.