Common use of Executed Change Directive/Change Order Required Clause in Contracts

Executed Change Directive/Change Order Required. Only a written Change Directive or Change Order, executed by the Department, may make changes to the Contract. In particular, but without limitation, a written Change Directive or Change Order executed by the Department is the only means by which changes may be made to the Substantial or Final Completion Date, or the Lump Sum Price.

Appears in 12 contracts

Samples: Construction Agreement, Construction Agreement, Construction Agreement

AutoNDA by SimpleDocs

Executed Change Directive/Change Order Required. Only a written Change Directive or Change Order, executed by the Department, may make changes to the ContractAgreement. In particular, but without limitation, a written Change Directive or Change Order executed by the Department is the only means by which changes may be made to the Substantial or Final Completion DateDates, the Design-Build Fee, or the Lump Sum Guaranteed Maximum Price.

Appears in 4 contracts

Samples: Agreement, Agreement, Agreement

Executed Change Directive/Change Order Required. Only a written Change Directive or Change Order, executed by the Department, may make changes to the Contract. In particular, but without limitation, a written Change Directive or Change Order executed by the Department is the only means by which changes may be made to the Substantial or Final Completion Date, the Preconstruction Fee, the Design Budget the Design-Build Fee, the General Conditions Budget or the Lump Sum Guaranteed Maximum Price.

Appears in 3 contracts

Samples: Agreement, Agreement, Agreement

Executed Change Directive/Change Order Required. Only a written Change Directive or Change Order, executed by the Department, may make changes to the ContractAgreement. In particular, but without limitation, a written Change Directive or Change Order executed by the Department is the only means by which changes may be made to the Substantial or Final Completion Date, or the Lump Sum PriceContract Sum.

Appears in 2 contracts

Samples: Basic Ordering Agreement, Agreement

Executed Change Directive/Change Order Required. Only a written Change Directive or Change Order, executed by the Department, may make changes to the Contract. In particular, but without limitation, a written Change Directive or Change Order executed by the Department is the only means by which changes may be made to the Substantial or Final Completion Date, the Design Fee, the Design-Build Fee, or the Lump Sum Guaranteed Maximum Price.

Appears in 2 contracts

Samples: Agreement, Agreement

AutoNDA by SimpleDocs

Executed Change Directive/Change Order Required. Only a written Change Directive or Change Order, executed by the Department, may make changes to the Contract. In particular, but without limitation, a written Change Directive or Change Order executed by the Department is the only means by which changes may be made to the Substantial or Final Completion Date, the Preconstruction Fee, the Design-Build Fee, or the Lump Sum Guaranteed Maximum Price.

Appears in 2 contracts

Samples: Agreement, Agreement

Executed Change Directive/Change Order Required. Only a written Change Directive or Change Order, executed by the Department, may make changes to the ContractAgreement. In particular, but without limitation, a written Change Directive or Change Order executed by the Department is the only means by which changes may be made to the Substantial or Final Completion Date, or the Lump Sum Price.Directive

Appears in 1 contract

Samples: Design Build Agreement