Failure to Accept. To the extent that the Accepting Party fails in whole or in part to accept the Contract Quantity in accordance with the Contract and such failure is not excused by an event of Force Majeure or the other Party’s non-performance, the Accepting Party shall pay the Delivering Party as compensation for damages an amount for the quantity of non-accepted electricity equal to the product of: (a) the amount, if positive, by which the Contract Price exceeds the price at which the Delivering Party is or would be able to sell the quantity of non-accepted electricity in the market acting in a commercially reasonable manner; and (b) the quantity of the non-accepted electricity. Such amount shall be increased by any incremental transmission costs and other reasonable and verifiable costs and expenses incurred by the Delivering Party as a result of the Accepting Party's failure.
Appears in 2 contracts
Samples: Electricity Supply Agreement, Electricity Supply Agreement
Failure to Accept. To the extent that the Accepting Party fails in whole or in part to accept the Contract Quantity in accordance with the Contract and such failure is not excused by an event of Force Majeure or the other Party’s non-performance, the Accepting Party shall pay the Delivering Party as compensation for damages an amount for the quantity of non-accepted electricity equal to the product of:
: (a) the amount, if positive, by which the Contract Price exceeds the price at which the Delivering Party is or would be able to sell the quantity of non-accepted electricity in the market acting in a commercially reasonable manner; and
and (b) the quantity of the non-accepted electricity. Such amount shall be increased by any incremental transmission costs and other reasonable and verifiable costs and expenses incurred by the Delivering Party as a result of the Accepting Party's failure.
Appears in 1 contract
Samples: Agreement Concerning the Delivery and Acceptance of Electricity
Failure to Accept. To the extent that the Accepting Party fails in whole or in part to accept the Contract Quantity in accordance with the an Individual Contract and such failure is not excused by an event of Force Majeure or the other Party’s non-performance, the Accepting Party shall pay the Delivering Party as compensation for damages an amount for the quantity of non-accepted electricity equal to the product of:
(a) the amount, if positive, by which the Contract Price exceeds the price at which the Delivering Party is or would be able to sell the quantity of non-accepted electricity in the market acting in a commercially reasonable manner; and
(b) the quantity of the non-accepted electricity. Such amount shall be increased by any incremental transmission costs and other reasonable and verifiable costs and expenses incurred by the Delivering Party as a result of the Accepting Party's failure.
Appears in 1 contract
Samples: General Agreement
Failure to Accept. To the extent that the Accepting Party fails in whole or in part to accept the Contract Quantity in accordance with the an Individual Contract and such failure is not excused by an event of Force Majeure or the other Party’s non-performance, the Accepting Party shall pay the Delivering Party as compensation for damages an amount for the quantity of non-accepted electricity equal to the product of:
(a) the amount, if positive, by which the Contract Price exceeds the price at which the Delivering Party is or would be able to sell the quantity of non-accepted electricity in the market acting in a commercially reasonable manner; and
(b) the quantity of the non-accepted electricity. Such amount shall be increased by any incremental transmission costs and other reasonable and verifiable costs and expenses incurred by the Delivering Party as a result of the Accepting Party's ’s failure.
Appears in 1 contract
Samples: General Agreement