FAILURE TO CORRECT MATERIAL. If Contractor fails to initiate correction of Materials or Work having Defects or Deficiencies in accordance with Section 17.4 within five (5) Days of Notice from Owner, Owner may correct such Materials or Work without relieving Contractor of any of its warranty obligations hereunder, and Owner’s costs associated with such activities shall be included in the calculation of Total Costs.
Appears in 9 contracts
Samples: Engineering, Procurement and Construction Agreement (Venture Global, Inc.), Engineering, Procurement and Construction Agreement (Venture Global, Inc.), Engineering, Procurement and Construction Agreement (Venture Global, Inc.)