Failure to Diligently Pursue the Project Sample Clauses

Failure to Diligently Pursue the Project. Recipient fails to diligently pursue the Project to completion by the Project Completion Deadline in accord with the timeline set forth in Exhibit A or fails to obtain Other Financing sufficient to complete the Project.
AutoNDA by SimpleDocs
Failure to Diligently Pursue the Project. Xxxxxxxx fails to diligently pursue the Project during the Construction Loan Period, including the lease-up. .
Failure to Diligently Pursue the Project. Borrower fails to diligently pursue the Project during the Construction Loan Period, including the lease-up. .
Failure to Diligently Pursue the Project. Grantor fails to diligently pursue the Project during the Construction Period, including the Lease-up Period.
Failure to Diligently Pursue the Project. Grantor fails to diligently pursue the Project during the Construction Period, including the Lease-up Period. Xxxxxxx agrees to comply with the Project schedule approved by Beneficiary and attached to the Loan Agreement.
Failure to Diligently Pursue the Project. Recipient fails to diligently pursue the Project to completion.

Related to Failure to Diligently Pursue the Project

  • Failure to Vacate If the Resident does not vacate the Residence on the expiry or early termination of this Agreement, (i) the Resident is liable for any financial loss sustained or incurred by the Institution or the Manager, and (ii) the Manager may remove the property of the Resident from the Room (whether or not the Resident is present at the time), and place the property in temporary storage in a location in the Residence of the Manager’s choice, at the Resident’s expense, without notice to the Resident and without liability to the Manager for any damage to or loss of the Resident’s property.

  • Failure to Achieve Commercial Operation If the Large Generating Facility fails to achieve Commercial Operation, but it or another generating facility is later constructed and makes use of the Network Upgrades, the Participating TO shall at that time reimburse Interconnection Customer for the amounts advanced for the Network Upgrades. Before any such reimbursement can occur, the Interconnection Customer, or the entity that ultimately constructs the generating facility, if different, is responsible for identifying and demonstrating to the Participating TO the appropriate entity to which reimbursement must be made in order to implement the intent of this reimbursement obligation.

  • Development of the Property Except as modified by this Agreement, the Development and the Property will be developed in accordance with all applicable local, state, and federal regulations, including but not limited to the City’s ordinances and the zoning regulations applicable to the Property, and such amendments to City ordinances and regulations that that may be applied to the Development and the Property under Chapter 245, Texas Local Government Code, and good engineering practices (the “Applicable Regulations”). If there is a conflict between the Applicable Regulations and the Development Standards, the Development Standards shall control.

  • Completion of Concrete Pours and Emergency Work 24.14.1 Except as provided in this sub-clause an employee shall not work or be required to work in the rain.