FOR UNIT PRICE ITEMS Clause Samples

FOR UNIT PRICE ITEMS. The Engineering Manager and Contractor shall determine and agree the number of items completed up to the time of the termination of the Contract and they Contractor shall be paid for the number of items so determined at the unit prices listed in the Contract.” 11.7.18.3 Replace clause 4.5.5.1, sub clause iii) with:
FOR UNIT PRICE ITEMS. The Engineering Manager shall determine the number of items completed up to the time of the termination of the Contract and the Contractor shall be paid for the number of items so determined at the unit prices listed in the Contract.