CONTRACT NO.: MOPU-0035 CONTRACT TITLE: INSTALLATION OF AUTOCLAVE BRICK LINING AND TITANIUM COMPONENTS CONTRACTOR: KOCH AUSTRALIA PTY LTD.
CONTRACT NO.:
|
MOPU-0035 | |
CONTRACT TITLE:
|
INSTALLATION OF AUTOCLAVE | |
BRICK LINING AND TITANIUM | ||
COMPONENTS | ||
CONTRACTOR:
|
XXXX AUSTRALIA PTY LTD. |
(Major Expansion — Work Packages)
1. INSTRUMENT OF AGREEMENT |
2. CONTRACT DOCUMENT |
3. OTHER DOCUMENTS FORMING PART OF THE AGREEMENT |
1 | In this agreement words and expressions shall, unless the context otherwise require, have the same meaning | |
2 | The following documents shall be deemed to form and be read and construed as part of this agreement: |
a) | Contract Documents Volumes 3A, 3B, and 3C as issued by LGL, during the tender, and amended in accordance with post tender / Pre-Award meetings and Contractor completed appendices | ||
b) | Minutes of Post-Tender / Pre-Award Meetings including: |
Minutes of Meeting 1st April, 2009
Minutes of Meeting 3rd June, 2009
Minutes of Meeting 9th and 10th June, 2009
c) | Contract Schedule dated 20th May, 2009 | ||
d) | Contractor’s Tender dated 26th June, 2009 | ||
e) | Contractor’s Quality Plans dated 24th February, 2009 (Xxxx) and 16th June, 2008 (York Forter) | ||
f) | Contractor’s supplied drawing “Q-1270-C REV 1 REVISED” | ||
g) | The Letter of Acceptance, dated 29th June, 2009. |
3 | In consideration of the agreements on the part of LGL in this agreement the Contractor will undertake and complete the work in conformity in all respects with the provisions of the contract and will perform, fulfil, comply with, submit to and observe all and singular the provisions, conditions, stipulations, and requirements and all matters and things expressed or shown in or reasonable to be inferred from the contract and which are to be performed, fulfilled, complied with, submitted to or observed by or on the part of the Contractor. | |
4 | In consideration of the agreements on the part of the Contractor in this agreement LGL, will make payments to the contractor in accordance with the provisions of this agreement and will perform, fulfil, comply with, submit to and observe all and singular the provisions conditions stipulations and requirements and all matters and things expressed or shown in or reasonably to be inferred from the contract and which are to be performed, fulfilled, complied with, submitted to or observed by, or on the part of LGL. |
5 | If any party to this agreement consists of one or more persons or one or more corporations or two or more persons or two or more corporations this agreement shall bind such person or persons and such corporation or corporations or such persons or corporations (as the case may be) and their respective executors, administrators, successors and permitted assigns (in the case of the Contractor) and assigns (in the case of LGL) jointly and severally and the person or persons and or corporation or corporations included in the term ‘Contractor’ or the term ‘LGL’ in this agreement shall jointly be entitled to the benefit of this agreement and this agreement shall be read and construed accordingly. | |
6 | This agreement shall take effect according to its tenor notwithstanding any prior agreement in conflict or at variance with it or any correspondence or documents relating to the subject matter of the contract which may have passed between the parties to the agreement prior to its execution. | |
7 | The undersigned authorised representatives of each party have initialled each page of this document and each change appearing on the face thereof. | |
Initialled by (For and on behalf of the Contractor) and by (For and on behalf of LGL) |
VOLUME 3A | ||||
Section 1 | General Project Details |
|||
Section 2 | Conditions of Tendering |
|||
Section 3 | Appendices to Conditions of Tendering |
|||
Section 4 | General Conditions of Contract |
|||
Section 5 | Appendices to General Conditions of Contract |
|||
Section 6 | Special Conditions of Contract |
|||
Section 7 | Appendices to Special Conditions of Contract |
|||
VOLUME 3B | ||||
Section 8 | Scope of Work |
|||
Section 9 | Tender Conditions of Particular Application |
|||
Section 10 | Appendices to Tender Conditions of Particular Application
|
|||
Section 11 | Special Conditions of Particular Application |
|||
Section 12 | Appendices to Special Conditions of Particular Application
|
|||
Section 13 | Technical Specifications |
|||
Section 14 | General Specifications |
|||
Section 15 | Total Project Program |
|||
VOLUME 3C | ||||
Contract Drawings | ||||
Reference Drawings | ||||
Other Reference Information |
Section 1
|
General Project Details | |
Section 2
|
Conditions of Tendering | |
Section 3
|
Appendices to Conditions of Tendering | |
Section 4
|
General Conditions of Contract | |
Section 5
|
Appendices to General Conditions of Contract | |
Section 6
|
Special Conditions of Contract | |
Section 7
|
Appendices to Special Conditions of Contract |
1.1 | Introduction |
|
1.2 | Description of the Total Project and Site |
|
1.3 | Access |
|
1.4 | Climate |
|
1.5 | Open Site Policy |
|
1.6 | Site Facilities |
|
1.7 | Total Project Program |
|
1.8 | Total Project Data |
1.1 | INTRODUCTION | |
1.1.1 | Lihir Gold Limited (ARBN 069 803 998), a company incorporated in Papua New Guinea, of Xxxxx 0, Xxxxxxx Xxxxx, Xxxx Xxxxxxx, Papua New Guinea (hereinafter referred to as “LGL”) is the owner and operator of the Lihir Mine located on Lihir Island (hereinafter referred to as the “Mine”) and is carrying out expansion work, generally described as the Million Ounce Project (hereinafter referred to as the “Total Project”). | |
1.1.2 | To manage the Total Project, LGL will be entering into a number of Contracts (“Work Packages”), with various contractors, to carry out sections of the Total Project in individual Work Packages. It is essential for the successful completion of the Total Project that all Contractors work together with LGL as a team, and contribute positively to the resolution of problems and to the completion of the Total Project on time and on budget. | |
1.1.3 | The conditions and procedures by which the Contracts will be managed are based on the following general principles: |
a. | The Contractors awarded Work Packages shall be experienced and proficient in the specific Work Package field and shall therefore be conversant with the day-to-day problems encountered on a project of this size, and shall have made adequate allowance in their Tender Price to overcome such problems by efficient management, supervision, and co-ordination. Accordingly, only major issues will require resolution/ direction at the project management level. | ||
b. | During the course of performing the Work, it is unlikely that idyllic work conditions will exist. The interface between related contracts, and ongoing mining operations, necessary changes to the Work, material deliveries, the terrain, and the prevailing weather conditions will all contribute to varying the programmed flow of work. The Contractor’s Tender shall recognize this and shall include the necessary flexibility, including alterations of resource levels and workforce relocations to optimize productivity and progress, in the Tender Price. | ||
c. | This Work Package is an integral part of the Total Project. Therefore, it is essential that the Contract be completed in accordance with the Contract Schedule to ensure that the Total Project is completed in accordance with the Total Project Program. Accordingly, time is of the essence of this Contract. | ||
d. | In order to ensure the resolution of issues as they occur, and to afford LGLLGL the opportunity to investigate alternative options, all matters involving extra payment will be subject to strict notification requirements which will be rigidly enforced as LGLLGL should not be required to pay for anything it has not had the opportunity to approve, avoid, or minimise. |
1.2 | DESCRIPTION OF THE TOTAL PROJECT AND SITE | |
1.2.1 | To assist the Contractor in becoming familiar with the Total Project, this section contains a brief description of the Total Project and other general information. Some aspects of this information may change, or be inaccurate, therefore no reliance should be placed upon it. It is simply offered by way of general introduction. | |
1.2.2 | The Mine is located on Lihir Island within the Lihir Island Group. The Lihir Island Group consists of four islands, of which Niolam Island (commonly known as Lihir Island) is the largest. Lihir Island is located at longitude 152°38’ E, latitude 3°07’ S, and approximately 700 kilometres North-East of the PNG capital of Port Moresby. The Mine is located approximately 50 metres above sea level. The temperature at the Mine ranges from +19°C to +35°C and the average precipitation is 4,800 millimetres per year. |
3A Issue 1 October 2006 version 3 | Section 1 Page No 1 |
Lihir Group Location map.
Niolam (Lihir) Island map.
1.2.3 | Lihir Island is a volcanic sea mountain which rises steeply from sea level to about 600 metres above sea level. It is roughly 22 kilometres long from North to South, and 14.5 kilometres from East to West at its widest points. The Xxxxx Xxxxxxx, in which all of the known ore deposits on Lihir Island are located, is on the east coast of the island, and both the Mine and Processing Plants are located there. An aircraft landing strip is located on the northern tip of the island, about 9.5 kilometres from the Mine. | |
1.3 | ACCESS | |
1.3.1 | Lihir Island is serviced daily by Air Niugini from Port Moresby. | |
1.3.2 | LGL’s freight arrives at Putput harbour, adjacent to the process plant, on regularly scheduled shipping services from either Brisbane, Port Moresby or Lae. General freight for Lihir Island arrives at a small harbour located at the township of Londolovit. |
3A Issue 1 October 2006 version 3 | Section 1 Page No 2 |
1.4 | CLIMATE | |
1.4.1 | Lihir Island experiences a high level of rainfall, averaging about 3,700 millimetres per year, and has an annual mean relative humidity of about 80%. The temperature generally varies between 20°C and 30°C (68°F and 86°F) with a recorded maximum of 34.7°C (94.5°F) and a recorded minimum of 19.3°C (66.7°F). Lihir Island is north of the area most affected by cyclones, which occur mainly in a belt from latitudes 10°S to 20°S. Natural vegetation on the island is mostly rain forest. | |
1.5 | OPEN SITE POLICY | |
1.5.1 | The construction of the Total Project will be carried out under an open site policy. | |
1.5.2 | Workers who are represented by different trade unions and workers who are not represented by any trade union may be working along side each other or supplying, delivering, and/or removing materials to and from the site at the same time. | |
1.6 | SITE FACILITIES | |
1.6.1 | LGL may establish some facilities that can be utilised by Contractors on site, subject to the conditions nominated. The provision of all other services necessary for the execution of Work will be the responsibility of the Contractor. Refer to Section 6 “Special Conditions of Contract” for further details. Refer to Volume 3C for site service drawings. | |
1.7 | TOTAL PROJECT PROGRAM | |
1.7.1 | The Work described in this document is part of the Total Project. Completion of the Work described herein in accordance with the Contract Schedule is essential to the completion of the Total Project in accordance with the Total Project program. | |
1.7.2 | LGL may identify to the Contractor certain milestone dates for the Work that are to be incorporated into the Contract Schedule (Refer to Section 9) | |
1.7.3 | The Contractor’s attention is drawn to Clauses 2.5.4 (j), 2.11 and 4.2.4, with respect to the preparation of Tender and Contract Schedules. | |
1.8 | TOTAL PROJECT DATA | |
1.8.1 | The following information lists data relevant to the Total Project and which is referred to and referenced in the Contract. |
a. | The Total Project will by managed by the owner and operator of Lihir Mine (or its appointed delegate): |
Xxxx Xxxxxxx,
Xxxxx Xxx Xxxxxx
Xxxxx 0, Xxxxxxx Xxxxx
Xxxx Xxxxxxx,
Papua New Guinea
3A Issue 1 October 2006 version 3 | Section 1 Page No 3 |
Fax No. x000 000 0000
b. | Construction of Contract: | ||
Clause 4.5.1 This Agreement shall be construed and governed in accordance with the laws of Queensland, Australia. | |||
c. | Currency: | ||
Clause 2.4.1 The Contract currency shall be in Australian Dollars. | |||
d. | Place for Payments: | ||
Clause 4.2.6.9 Payments shall be made at Xxxxxxxx, Xxxxxxxxxx, Xxxxxxxxx. | |||
e. | Units of Measurements: | ||
Clause 4.5.1.3 The units of measurement are metric (SI). |
3A Issue 1 October 2006 version 3 | Section 1 Page No 4 |
2.1 | Acceptance of Conditions of Tendering |
|
2.2 | Tender Documents |
|
2.3 | Tenderer to Inform Itself |
|
2.4 | Tender Price |
|
2.5 | Submission of Tender |
|
2.6 | Lodgement of Tender |
|
2.7 | Tender Validity Period |
|
2.8 | Informal Tenders |
|
2.9 | Additional Information |
|
2.10 | Post Tender Pre-award Meeting |
|
2.11 | Detailed Construction Schedule |
|
2.12 | Complementary Documents |
|
2.13 | Acceptance of Tender |
|
2.14 | Return of Tender Documents |
2.1 | ACCEPTANCE OF CONDITIONS OF TENDERING | |
2.1.1 | The Tenderer, by submission of its Tender, unconditionally agrees, in consideration of LGL evaluating and considering its Tender, to be bound by the Conditions of Tendering set out herein. | |
2.2 | TENDER DOCUMENTS | |
2.2.1 | The Tender Documents shall be the entire contents of Volumes 3A, 3B and 3C hereof, and any schedules, addenda or other documents issued by LGL for the purpose of tendering. | |
2.3 | TENDERER TO INFORM ITSELF | |
2.3.1 | The Tenderer understands and acknowledges that it has, and in any event, that it is reasonable to deem that it has: |
a. | examined carefully and acquired actual knowledge of the Tender Documents and any other information made available in writing by LGL to the Tenderer for the purpose of tendering; | ||
b. | inspected the Site and its surroundings and as a result of careful examination, has satisfied itself as to any and all restrictions resulting from carrying out the Work on an operating mine site, the nature, extent and location of the Work, the formation and geology of the ground, the character, quality and quantity of the surface or sub-surface materials and structures to be encountered, the character of equipment and facilities needed preliminary to and during the prosecution of the Work, the availability of labour, water, power, communications, roads and means of transportation, disposal, handling and storage of materials, the general local conditions, including weather conditions, and all other matters or things which may affect the execution of the Work; | ||
c. | examined all information and made all necessary inquiries relevant to the risks, contingencies and other circumstances having an effect or which could have an effect on its Tender, including making inquiries regarding all geotechnical information produced for exploration and/or mine development, and satisfied itself that it has examined sufficient information for the purpose of preparing its Tender; | ||
d. | satisfied itself as to the correctness and sufficiency of its Tender and that its Tender Price covers the cost of complying with all the obligations of the Contract and of all matters and things necessary for the due and proper performance and completion of the Work described in the Tender Documents including any risks and contingent liabilities related thereto. |
2.3.2 | LGL will not bear the cost of any errors, misunderstandings or deficiencies of the Tenderer. Therefore, no claims will be accepted based on the assertion of the Tenderer that it was not aware of the provisions or conditions covered by the Tender Documents or had otherwise omitted to make some provision in its Tender Price. | |
2.3.3 | Should any Tenderer find any discrepancies, inconsistencies, errors or omissions in the Tender Documents or should it be in doubt as to their meaning, it shall at once notify LGL in writing and LGL will explain or amend the Tender Documents. No explanation or amendment to the Tender Documents will be recognised, unless in the form of a written notice of explanation or addendum issued by LGL in the form set out in Tender Form Appendix 3/A or 3/B, respectively. | |
2.3.4 | Verbal advice or information given or obtained in respect of this Tender shall not constitute a warranty or a statement to the Tenderer on which the Tenderer may rely and shall not be binding on LGL. LGL shall be bound only by written advice or written information furnished by LGL to the Tenderer. |
3A Issue 1 October 2006 version 3 | Section 2 Page No 1 |
2.4 | TENDER PRICE | |
2.4.1 | The Tender Price submitted in accordance with these Conditions of Tendering shall be expressed in the currency stated in Clause 1.8 (Total Project Data). | |
2.4.2 | The Tender Price shall be fixed in wage rates or allowances, material costs, transportation costs, primage, fees, taxes and all other costs or expenses of whatsoever kind, whether or not of the forgoing nature unless specifically provided for in Section 9. Where unit rates are tendered, a complete detailed breakdown showing all components that make up each rate shall be provided. | |
2.4.3 | The Tender Price shall be expressed as either: |
a. | a total lump sum, or | ||
b. | a schedule of all-inclusive Tender Rates, extended by the provisional unit quantities to give an Estimated Total Cost, |
as nominated in Volume 3B, Section 9, Tender Conditions of Particular Application. | ||
2.4.4 | For Lump Sum contracts, the Tenderer shall provide a breakdown of its Tender Price in accordance with the items listed in Tender Form Appendix 10/A. Each item must be priced and the quantity, material and erection components for each item provided. No items shall be “included” or merged in other items. Tender Form Appendix 10/A is required for budget control and the assessment of Progress Claims, and therefore must accurately reflect the Tenderers estimate. If LGL considers that the Tenderer has ‘loaded’ Tender Form Appendix 10/A to artificially increase the value of the earliest items of Work to be executed, it may amend Tender Form Appendix 10/A as it thinks appropriate and such amended Tender Form Appendix 10/A shall be used for the assessment of Progress Claims. Any such amendment shall not be subject to dispute by the Tenderer / Contractor. The Tenderer shall add to Tender Form Appendix 10/A any additional item for which it requires payment and shall ensure the total of Tender Form Appendix 10/A equals the Tender Price. | |
2.4.5 | For Unit Rate contracts, the Tenderer shall submit Tender Rates as required by Tender Form Appendix 10/A, which shall be used to pay the Contractor for the actual Work done. The Tender Rates shall be either Unit Rates covering the entire cost of performing identifiable units of Work (such as cubic meters of excavation) or shall be all-inclusive Hourly Hire Rates for personnel and equipment where units of Work cannot be readily identified, or may be a combination of both, depending upon the nature of Work required. Tender Form Appendix 10/A may, where appropriate, also include some items for which a Lump Sum is required. The Tenderer shall extend each Tender Rate in the Tender Form Appendix 10/A by the number of units estimated to be required to execute the provisional Scope of Work, if any, set out in the Tender Documents, and shall add to Tender Form Appendix 10/A any additional Tender Rate or Lump Sum item for which it will require payment. The extended Tender Rates, additional Tender Rates and Lump Sums shall then be totalled to give an Estimated Tender Price. The Estimated Tender Price will only be used for LGL budget purposes and to monitor the performance of the Tenderer if it is awarded the Contract. It shall not be taken to imply a guaranteed scope of work, a minimum or maximum price, or any other such thing of whatsoever nature. The extent of work to be performed will be solely determined by LGL during the course of the Contract. | |
2.4.6 | Where plant and equipment Hourly Hire Rates are tendered on Tender Form Appendix 10/A, the rates shall exclude plant operators and shall only apply to the period which such plant and equipment actually executes work or is necessarily retained at the location of a specific item of work to perform periodic tasks necessary for the execution of the Work (Stand By). Labour Hourly Hire Rates tendered on Tender Form Appendix 10/A including plant operators, shall apply to the full hours, days or weeks that such labour is engaged in performing Work at the direction of LGL excluding public holidays, |
3A Issue 1 October 2006 version 3 | Section 2 Page No 2 |
rostered leave periods and any non-working periods due to such things as sick leave, absenteeism or strikes. | ||
2.5 | SUBMISSION OF TENDER | |
2.5.1 | The Tender shall be submitted on the form of Tender set out in Tender Form Appendix 3/C. | |
2.5.2 | If the Tenderer is a natural person, the Tenderer shall sign the Tender, clearly indicating his/her full name together with his/her signature. If the Tenderer is a corporation or company, it shall affix its common seal, in the manner prescribed by its articles, by-laws or other constituting documents, or shall otherwise have the Tender formally executed. | |
2.5.3 | Where the Tenderer is a corporation that is directly or indirectly a subsidiary of another corporation or is a corporation that is directly of indirectly related to another corporation, the Tenderer shall submit details of the relationship between the respective corporations on Tender Form Appendix 3/D. If the Tenderer’s Tender is accepted, the Tenderer shall, if requested in writing by LGL, lodge a document of guarantee, undertaking and substitution for the performance of the obligations and the discharge of the liabilities of the Contractor under the Contract in the form set out in Tender Form Appendix 3/E, duly executed by the corporation(s) nominated in the request in writing from LGL. For the purpose of this Clause: |
a. | A Tenderer is a “subsidiary” of another corporation, where that corporation, directly or indirectly, owns more than 50% of the equity of the Tenderer; and | ||
b. | A Tenderer is “related” to another corporation where the Tenderer, directly or indirectly, controls, is controlled by, or is under common control with, such other corporation, and for that purpose, “control” means control in fact. |
2.5.4 | The Tenderer, in addition, as part of its Tender, shall submit the Tender Forms and other’ information as set out hereunder: | |
Tenders shall not be accepted which do not include all of these Tender Forms or which contain Tender Forms which have not been properly completed and any such Tender may be excluded from the Tender evaluation process. | ||
In the event that any Tenderer reproduces any of the Tender Forms for the purpose of submitting its Tender, such forms shall be deemed to be identical in every respect to the Tender Forms issued in the Tender Documents and no variation or omission on any such reproduced form shall effect or alter the terms, conditions or obligations of the Contract unless listed and priced on Tender Form Appendix 3/F. |
a. | Departure from Tender Documents — Tender Form Appendix 3/F | ||
A Tenderer must submit its Tender strictly in accordance with the Tender Documents, however, should the Tenderer, in addition to its conforming Tender, wish to submit alternative offers based on departures from the Tender Documents, it shall list the offered departures and the resultant variation to the conforming Tender Price for each departure. If the Tenderer has no departures from the Tender Documents, then it shall insert on Tender Form Appendix 3/F “no departures” and shall duly sign Tender Form Appendix 3/F in acknowledgment that its Tender strictly complies with the requirements of the Tender Documents. For design and construct Tenders, the submission and acceptance of design drawings shall not constitute acceptance or agreement to any departures from the requirements of the Tender Documents unless such departures are specifically listed in Tender Form Appendix 3/F and accepted by LGL. |
3A Issue 1 October 2006 version 3 | Section 2 Page No 3 |
b. | Key Personnel — Tender Form Appendix 3/G | ||
The Tenderer shall list the on-Site and head office management and supervision personnel to be engaged on the Work (Key Personnel) and shall attach thereto, the curriculum vitae thereof, which shall include the projects upon which they are currently engaged or, if not currently engaged, the projects upon which they were last engaged. The Tenderer shall also nominate on this Tender Form the position of persons on Site who will be authorised to act in all respects for and on behalf of the Tenderer / Contractor. At least one full-time position on Site must be nominated. | |||
c. | List of Current Projects — Tender Form Appendix 3/H | ||
The Tenderer shall list the ten largest projects currently being undertaken by the Tenderer. If the Tenderer has less than 10 current projects, the balance shall be made up of the most current completed projects. By submission of its Tender, the Tenderer unconditionally authorizes LGL to make whatever inquiries it wishes in relation to the Tenderer’s performance on these projects, and the accuracy of the information provided. | |||
d. | Wages, Allowances and Employment Conditions — Tender Form Appendix 3/I | ||
Notwithstanding that the Tender is a fixed price Tender, the Tenderer shall list the wages, allowances and employment conditions of the on-Site management, supervision and labour force to be engaged on the Work. This information shall be treated as confidential and shall not form part of the Contract. | |||
e. | Tenderer’s Plant and Equipment — Tender Form Appendix 3/J | ||
The Tenderer shall list the plant and equipment to be committed to the Contract on Tender Form Appendix 3/J, Sheet 1 of 2, and shall provide an Equipment Inspection Report for each item of plant and equipment, on Sheet 2 of 2. If awarded the Contract, the listed plant and equipment or plant and equipment of equal or better standard must be supplied. | |||
f. | Work to be Subcontracted — Tender Form Appendix 3/K | ||
The Tenderer shall list all sections of the Work to be executed by Subcontractors to the Tenderer. Approval to Subcontract any section of the Work will not be given unless nominated herein. Subject to the provisions of Clause 4.2.11 of the General Conditions of Contract, the Tenderer shall list, if known, the names of proposed Subcontractors. | |||
Acceptance of a Tender shall not constitute acceptance of any Subcontractors listed on this Tender Form. | |||
Tenderers intending to utilize Subcontractors for sections of the Work at an early stage of the Contract, should include requests for approval of these Subcontractors with all appropriate documentation (as required by Clause 4.2.11.2) with their Tender. | |||
g. | Cash Flow Program — Tender Form Appendix 3/L | ||
The Tenderer shall submit a detailed cumulative cash flow program, as per Tender Form Appendix 3/L. The total progress payments shall not exceed this cash flow program, adjusted for any variations in the Scope of Work. |
3A Issue 1 October 2006 version 3 | Section 2 Page No 4 |
h. | Components of Tender Price — Tender Form Appendix 10/A (Volume 3B, Section 10) | ||
For Lump Sum Tenders, the Tender Price (as shown on Tender Form Appendix 3/C) shall be broken into its constituent parts on Tender Form Appendix 10/A. (Refer to Clause 2.4.4). | |||
For Unit Rate Tenders, the Tender Rates, additional Tender Rates or Lump Sum items shall be set out on Tender Form Appendix 10/A. and totalled to give an Estimated Total Cost (Refer to Clause 2.4.5) | |||
i. | Schedule of Tender Rates for Variations & Dayworks — Tender Form Appendix 10/B, Sheets 1, 2 & 3. (Volume 3B, Section 10) | ||
On Sheet 1, Tenderers shall submit all-inclusive Tender Rates for executing the units of Work. | |||
On Sheet 2, Tenderers shall submit all-inclusive Hourly Hire Rates for labour, including plant operators. These Tender Rates shall include for all tools of trade and consumables. | |||
On Sheet 3, Tenderers shall submit all-inclusive Hourly, Daily, weekly and monthly Hire Rates for Constructional Plant (excluding any operators cost). These Tender Rates shall include provision for all fuels, lubricants and consumables. | |||
A detailed breakdown of each Tender Rate shall be attached showing clearly the derivation of each Tender Rate. | |||
The above Tender Rates shall be applied to determine the value of Variations (additions and deductions) to the Contract and for valuing Dayworks. For Variations, the tendered Unit Rates shall take precedence over the tendered Hire Rates. | |||
j. | Tender Schedule — Tender Form Appendix 10/C (Volume 3B, Section 10) | ||
The Tenderer shall submit a Tender Schedule in bar chart form, similar to Tender Form Appendix 10/C, to show commencement and completion dates of all major activities of the Work, including the completion and milestone dates, if any, set out in section 9 (Tender Conditions of Particular Application). The Tenderer shall include in its Tender provision for loss of working time due to inclement weather. No variation to either the Contract Sum or the Contract Schedule will be allowed for inclement weather. The Tender Schedule shall assume award of the Contract seven (7) days after the closing date of Tenders. The purpose of the Tender Schedule is to demonstrate the Tenderer’s ability to properly program the Work and for LGL’s assistance in the evaluation of Tenders. The Tender Schedule shall not, however, form part of the Contract as a detailed Contract Schedule will be agreed upon in the post-tender pre-award period. | |||
k. | Projected Construction Weekly Manpower — Tender Form Appendix 10/D (Volume 3B, Section 10) | ||
The Tenderer shall show its projected weekly manpower requirements on Tender Form Appendix 10/D and shall note therein its preferred roster and leave periods. Acceptance of a Tender shall not constitute acceptance by LGL that the projected manpower is sufficient. It shall be the Contractor’s responsibility to provide whatever manpower is necessary to meet the requirements of the Contract. |
Volume 3A Issue 1 October 2006 version 3 | Section 2 Page No 5 |
l. | Quality Control Procedures | ||
The Tenderer shall submit details of its quality management and quality control systems that it intends to implement on the Work. Such systems shall be subject to the approval of LGL and consistent with the complexity of Work. | |||
m. | Safety and Environment | ||
The Tenderer shall include in its Tender: |
a. | Statements of its safety and environmental management policy, including any incentive/recognition programs; | ||
b. | Details of its proposed program and resources to manage safety and environmental matters on Site; | ||
c. | Statements of the safety and environmental protection practices employed as standard operating procedures; and | ||
d. | Statements of safety and environmental protection record (including statistics for the past three (3) years) and expertise to carry out the Work safely and with due regard to protecting the environment. Any safety or environmental violations, charges, proceedings or orders issued against the Tenderer, any affiliate of the Tenderer, any Subcontractor or any of their respective directors, officers, employees, agents or consultants who will be engaged in the Work, shall be fully disclosed to LGL in these statements. |
Safety and environmental record and practices are considered as factors in selecting contractors. | |||
n. | Other Requirements | ||
The Tenderer shall submit as part of its Tender, all other information (if any) as required by Volumes 3A, 3B and 3C of the Tender Documents. | |||
The Tenderer shall submit with its Tender, a copy of the last audited Balance Sheet of the Tenderer and notes thereof. If this Balance Sheet is more than 7 months old, the Tenderer shall also submit an updated Balance Sheet authenticated by a consistent criteria review indicating if there have been variations thereof, made by the same auditor certifying the former Balance Sheet. |
2.6 | LODGMENT OF TENDER | |
2.6.1 | Tenders shall be submitted in duplicate and enclosed in a sealed envelope marked with the description and number of the Work Package. The Tender shall be lodged in the Tender Box at, or sent by prepaid post and delivered to, the place named in the Invitation to tender, by the date and time for closing of Tenders nominated therein. | |
2.6.2 | If advised in writing by LGL, tenders may be submitted via email to the specific Tender Email Address provided by LGL for the purpose of the tender. Upon sending of a Tender via email, the Tenderer shall contact the person nominated in section 9 for “INQUIRIES DURING TENDER PERIOD” via telephone and advise that the Tender has been sent. | |
2.7 | TENDER VALIDITY PERIOD | |
The Tender shall remain valid for a period of sixty (60) calendar days from the expiration of the date of closing of Tenders. |
Volume 3A Issue 1 October 2006 version 3 | Section 2 Page No 6 |
2.8 | INFORMAL TENDERS | |
2.8.1 | Any Tender which does not comply with the requirements of or which contains provisions not required or allowed by the Tender Documents shall be considered an informal Tender and may be rejected. | |
2.8.2 | Unless a departure or other commercial exception is accepted in writing by LGL (either through correspondence or at a post-tender briefing), it will have no affect under the contract and will not bind LGL despite being incorporated into the contract under the formal instrument of agreement. | |
2.9 | ADDITIONAL INFORMATION | |
2.9.1 | Notwithstanding any other requirements of the Tender Documents, LGL may require a Tenderer to submit additional information before any Tender is accepted. Should the Tenderer fail to submit any of the information required by the date and time stipulated by LGL, the Tender shall be considered an informal Tender and may be rejected. | |
2.10 | POST TENDER PRE-AWARD MEETING | |
2.10.1 | Following submission of Tenders, a Tenderer may be required to attend a post tender pre-award meeting at a place and time notified in writing by LGL. In addition to any other personnel the Tenderer may wish to be present, such meeting shall be attended by: |
a. | A person with the authority to contractually bind the Tenderer; | ||
b. | The principal person(s) who prepared the Tender; | ||
c. | The person(s) who visited the Site; and | ||
d. | The nominated Key Personnel. |
A draft agenda for the post tender pre-award meeting is set out in Appendix 3/M. | ||
2.11 | DETAILED CONSTRUCTION SCHEDULE | |
2.11.1 | Tenderers required to attend a post tender pre-award meeting shall prepare for presentation at the meeting, a detailed construction schedule, in critical path / precedence form, listing all activities, dependencies, resources and durations. The construction schedule shall take into account the necessary preliminary and concurrent work of others, the requirement for co-ordination of the Work with the work of others and the operation of the mine, the requirement to allow for loss of working time due to inclement weather, and for delays other than those caused by acts, omissions or defaults of LGL. The construction schedule shall also show the completion and milestone dates (Key Dates), if any, set out in section 9 (Tender Conditions of Particular Application). | |
2.11.2 | If the Contract involves any LGL-supplied material or equipment, this shall be clearly shown on the construction schedule. The Tenderer shall confirm all delivery dates with LGL at the post tender pre-award meeting. | |
2.11.3 | When approved, the construction schedule shall form part of the Contract and shall be considered the “Contract Schedule”. | |
2.11.4 | Approval of the construction schedule shall not constitute acceptance by LGL that any activities, resources, durations or allowances are sufficient but shall establish the time performance obligations of the Contractor irrespective of the means necessary to achieve progress in accordance with the Contract Schedule. | |
2.12 | COMPLEMENTARY DOCUMENTS |
Volume 3A Issue 1 October 2006 version 3 | Section 2 Page No 7 |
2.12.1 | The Tender Documents are complementary and each shall be read in conjunction with one another to explain each other and subject to any clauses providing for order of precedence in case of inconsistencies, with the intention of making the whole package of Tender Documents consistent. | |
2.13 | ACCEPTANCE OF TENDER | |
2.13.1 | LGL shall not be bound to accept the lowest or any Tender. | |
2.13.2 | A Tender shall not be deemed to have been accepted unless and until notice in writing of such acceptance is issued by LGL to the Tenderer in a form similar to that set out in Appendix 3/N or through the execution of a Formal Instrument of Agreement. | |
2.13.3 | Tenders will not be opened in public or made public. | |
2.14 | RETURN OF TENDER DOCUMENTS | |
2.14.1 | All unsuccessful Tenderers shall return to LGL the Tender Documents issued to them. |
Volume 3A Issue 1 October 2006 version 3 | Section 2 Page No 8 |
3/A | Form of Notice of Explanation |
|
3/B | Form of Addendum |
|
3/C | Tender Form |
|
3/D | Inter-Relationship of Corporations |
|
3/E | Deed of Guarantee, Undertaking and Substitution |
|
3/F | Departures from Tender Documents |
|
3/G | Key Personnel |
|
3/H | List of Current Projects |
|
3/I | Wages, Allowances & Employment Conditions |
|
3/J | Tenderer’s Plant and Equipment (2 sheets) |
|
3/K | Work to be Subcontracted |
|
3/L | Cash Flow Program |
|
3/M | Agenda for Post Tender, Pre-award meeting (2 sheets) |
|
3/N | Form of Letter of Acceptance |
To all Tenderers
|
Work Package | MOPU-0035 | ||
Xxxx Australia Pty Ltd, Xxxx Knight Division
|
Notice No | X | ||
###-##-####A4
|
Date | 12-June-2009 |
Tender For
|
Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island |
and Conditions Negotiation Table meetings. See applicable meeting notes issued.
Special Terms and Conditions will be issued to document the agreement.
Signed | Engineering Manager |
Signed | (Tenderer) | Date 12-June-2009 | ||
BUSINESS DIRECTOR, XXXX XXXXXX DIVISION XXXX AUSTRALIA |
To all Tenderers
|
Work Package | MOPU-0035 | ||
Xxxx Australia Pty Ltd, Xxxx Knight Division
|
Addendum No | X | ||
###-##-####A4
|
Date | 12-Jun-2009 |
Tender For
|
Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island |
all questions discussed at 19 February preaward meeting and subsequent MOPU Terms and Conditions Negotiation Table meetings. See applicable meeting notes issued. Special Terms and Conditions will be issued to document the agreement. |
Signed | Engineering Manager |
Signed | Date 12-Jun-09 |
To all Tenderers
|
Work Package | MOPU-0035 | ||
Xxxx Australia Pty Ltd, Xxxx Xxxxxx Division
|
Addemdum No | X | ||
###-##-####A4
|
Date | 12-Jun-09 |
Tender For
|
Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island |
USD | AUD | |||||||
York subcontract |
||||||||
Knignit services |
$ |
Signature of Tenderer: |
||
MANAGING DIRECTOR, XXXX AUSTRALIA | ||
Signature of Witness: |
||
Name of Witness:
|
BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA | |
Address of Witness: |
||
Tenderer’s address for service of notices:
|
XXXX AUSTRALIA, XX XXX 0000, XXXXXXXXXX XXX 0000 XXX | |
Facsimile
|
Telephone | |
Email address |
||
Tenderer’s Bank (Name)
|
Branch |
1 |
||
2 |
||
3 |
||
4 |
||
To all Tenderers
|
Work Package | MOPU-0035 | ||
Xxxx Australia Pty Ltd, Xxxx Knight Division
|
Addendum No | X | ||
###-##-####A4
|
Date | 12-Jun-09 |
Tender For
|
Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island |
Affiliated Corporations | Form Of Relationship | Shares Held | ||
XXXX CHEMICAL TECHNOLOGY GROUP |
OWNS XXXX AUSTRALIA PTY LTD AND XXXX XXXXXX LLC |
100% | ||
BEROA GROUP | OWNS YORK FORTER AUSTRALASIA PTY LTD | 100% |
Dated this
12TH
Day of JUNE 2009 |
||
Signature
of Tenderer:
|
||
MANAGING DIRECTOR, XXXX AUSTRALIA | ||
Signature of Witness: |
||
Name of Witness:
|
BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA | |
Address of Witness: |
||
To all Tenderers
|
Work Package | MOPU-0035 | ||
Xxxx Australia Pty Ltd, Xxxx Xxxxxx Division
|
Addendum No | X | ||
###-##-####A4
|
Date | 12-Jun-09 |
Tender For
|
Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island |
Signature and Seal of Guarantor |
||
Signature of Witness: |
||
Name of Witness:
|
BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA | |
Address of Witness: |
||
Guarantor’s address for service of notices: |
||
Facsimile
|
Telephone | |
Email address |
To all Tenderers
|
Work Package | MOPU-0035 | ||
Xxxx Australia Pty Ltd, Xxxx Xxxxxx Division
|
Addendum No | X | ||
###-##-####A4
|
Date | 12-Jun-09 |
Tender For
|
Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island |
Item | Departure | Variation to Tender Price/Rate | ||||
Addition | Deduction |
PLEASE REFER TO THE NOTED XXXX AUSTRALIA OFFER LETTER | ||||||
FOR DETAILS OF OUR PROPOSAL. THE FORTHCOMING SPECIAL CONDITIONS | ||||||
SECTION 11, DEVELOPED FROM THE TERMS AND CONDITIONS NEGOTIATING TABLES | ||||||
PREPARED OVER SEVERAL MEETINGS, WILL NOTE ALL VARIATIONS FROM THE | ||||||
TENDER DOCUMENTS AS ISSUED. |
Signature of Tenderer: |
||
MANAGING DIRECTOR, XXXX AUSTRALIA | ||
Signature of Witness: |
||
Name of Witness: |
||
BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA | ||
Address of Witness: |
||
To all Tenderers
|
Work Package | MOPU-0035 | ||
Xxxx Knight Division, Xxxx Australia Pty Ltd
|
Notice No | X | ||
###-##-####A4
|
Date | 12-June-2009 |
Tender For
|
Autoclave Internal Equipment Installation |
Location | Time Allocated To | Proposed Dates | ||||||||||||||||||
Name | Position | On/Off Site | Contract (%) | Start | Finish | |||||||||||||||
VP ENGINEERING & CONSTRUCTION, XXXX KNIGHT LLC | ||||||||||||||||||||
offsite | 5 | % | Oct-08 | ONGOING | ||||||||||||||||
BUSINESS DIRECTOR, XXXX AUSTRALIA XXXX KNIGHT DIVISION | ||||||||||||||||||||
offsite | 15 | % | Oct-08 | ONGOING | ||||||||||||||||
SITE SUPERVISORS (2 to 4) | ||||||||||||||||||||
onsite | 100 | % | Apr-10 | Sep-11 | ||||||||||||||||
PROJECT MANAGER AUSTRALIA | ||||||||||||||||||||
offsite | 60 | % | Oct-08 | Sep-11 | ||||||||||||||||
onsite | 40 | % | Apr-10 | Sep-11 | ||||||||||||||||
MANAGING DIRECTOR YORK-FORTER, SUBCONTRACTOR | ||||||||||||||||||||
offsite | 1 | % | Oct-08 | Sep-11 | ||||||||||||||||
onsite | 1 | % | Nov-10 | Sep-11 | ||||||||||||||||
TBD | PROJECT MANAGERS AND SUPERVISORS OF YORK-FORTER, SUBCONTRACTOR | |||||||||||||||||||
offsite | 60 | % | Oct-08 | Sep-11 | ||||||||||||||||
onsite | 40 | % | Apr-10 | Sep-11 |
Dated this 12TH Day of JUNE 2009
|
Signature of Tenderer: |
||
MANAGING DIRECTOR, XXXX AUSTRALIA | ||
Signature of Witness: |
||
Name of Witness: |
BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA | |
Address of Witness: |
||
Tender For
|
Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island | Work Package MOPU-0035 | ||||
Date 12-Jun-09 |
Tenderer
|
Xxxx Knight Division, Xxxx Australia Pty Ltd ###-##-####A4 |
Xxxx Knight Projects ordered, constructed or completed in 2008, 2009 |
Approximate | Tenderers | Contact At Supervising Body | Current % | Start | Completion | |||||||||||
Project | Project Value | Original Contract | Supervising Body | Name | Telephone | Complete | Date | Date | ||||||||
Dated this 12TH Day of JUNE 2009
|
Signature of Tenderer: |
||
MANAGING DIRECTOR, XXXX AUSTRALIA | ||
Signature of Witness: |
||
Name of Witness: |
||
BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA | ||
Address of Witness: |
||
To all Tenderers
|
Work Package | MOPU-0035 | Work Package | |||
Xxxx Knight Division, Xxxx Australia Pty Ltd
|
Notice No | X | ||||
###-##-####A4
|
Date | 12-June-2009 |
1. Salaried Personnel — Position PROJECT MANAGER |
Per Working Day | |||
Per Travel, Standby Day | ||||
(a) Base Rate |
X | Per Month | ||
(b) Other Allowances (Specify) |
X | Per Month | ||
X | Per Month | |||
X | Per Month | |||
Total |
X | Per Month | ||
2. Wages Personnel — Position / Category |
||||
(a) Base Rate for hours |
X | Per Hour | ||
(b) Hourly Adjustedr Allowances (Specify) |
X | Per Hour | ||
X | Per Hour | |||
X | Per Hour | |||
Subtotal |
X | Per Hour | ||
(c) Other Hourly Payments (Specify) |
X | Per Hour | ||
X | Per Hour | |||
Total for hours |
X | Per Week | ||
(d) Adjustments for site working hours & roster |
X | Per Week | ||
(e) Weekly allowances (Specify) |
X | Per Week | ||
X | Per Week | |||
Subtotal |
X | Per Week | ||
(f) Total gross hourly wages for site working hours |
X | Per Hour | ||
Dated this 12TH Day of JUNE 2009
|
Signature of Tenderer: |
||
MANAGING DIRECTOR, XXXX AUSTRALIA | ||
Signature of Witness: |
||
Name of Witness: |
||
BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA | ||
Address of Witness: |
||
To all Tenderers | Work Package MOPU-0035 | |||
Xxxx Knight Division, Xxxx Australia Pty Ltd | Notice No X | |||
###-##-####A4 | Date 12-June-2009 |
Item | Plant & Equipment General | Proposed | ||||||||
No | Description | Model / Type | Age | Start Date | Finish Date | |||||
The exact equipment that will be used in construction cannot be determined (eg - serial number, etc) this far ahead of the construction period. YFA hold an extensive list of equipment, maintained in excellent working order, on site or oncall for emergencies. |
||||||||||
Bricksaw | Clipper 18" | 1 yr | Full Duration |
|||||||
Bricksaw | Clipper 18" | 1 yr | Full Duration |
|||||||
Bricksaw | Clipper 14" | 1 yr | Full Duration |
|||||||
Distribution Boards | Full Duration |
|||||||||
Distribution Boards | Full Duration |
|||||||||
Festo Mixers | Protool MXP 1602 B | 1 yr | Full Duration |
|||||||
Festo Mixers | Protool MXP 1602 B | 1 yr | Full Duration |
|||||||
Festo Mixers | Full Duration |
|||||||||
Festo Mixers | Full Duration |
|||||||||
Hobart Mixers | Hobart D 300 T | 3 yr | Full Duration |
|||||||
Hobart Mixers | Full Duration |
|||||||||
Positive Air Helmets | RaKel 3M | 1 yr | Full Duration |
|||||||
415V Fan | Bluw Wizard | 3 yr | Full Duration |
Dated this 12TH Day of JUNE 2009 |
TENDERER’S PLANT & EQUIPMENT
EQUIPMENT INSPECTION REPORT
To all Tenderers | Work Package MOPU-0035 | Work Package | ||
Xxxx Xxxxxx Division, Xxxx Australia Pty Ltd | Notice No X | |||
###-##-####A4 | Date 12-June-2009 |
Sheet 1 Item No
|
General Description | |
Unit
|
Attachment(s) | |
Make
|
Replacement Cost | F.O.B. | ||
Model
|
Serial No | Engine | ||
Hours
|
Expected Life | |||
(Hours) (Years) |
Ownership
|
Estimated Value | |
Tires
|
Hydraulics | |
Dimensions | Length | Width | Height |
Operating Test
|
Rating |
Dated this 12TH Day of JUNE 2009 | ||||||||
To all Tenderers
|
Work Package MOPU-0035 | |
Xxxx Knight Division, Xxxx Australia Pty Ltd
|
Notice No X | |
###-##-####A4
|
Date 12-June-2009 |
Section Of The Work | Value | Proposed Subcontractor | ||
BRICK LINING, TITANIUM INTERNALS INSTALLATION LABOUR |
||||
AUD |
||||
NOTE: Personnel from Xxxx Knight LLC USA will be seconded to Xxxx Australia for this work. |
Dated this 12TH Day of JUNE 2009 | ||||||||
Tender For Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island | Work Package MOPU-0035 | ||||
Tenderer |
Xxxx Xxxxxx Division, Xxxx Australia Pty Ltd ###-##-####A4 |
Date 12-Jun-09 |
Week | |||||||||||||||||||||||||||||||||||||||||||
Event | 1 | 74 | 78 | 82 | 86 | 90 | 94 | 98 | Totals USD | Totals AUD | |||||||||||||||||||||||||||||||||
PO | |||||||||||||||||||||||||||||||||||||||||||
Begin Work | |||||||||||||||||||||||||||||||||||||||||||
Progress |
|||||||||||||||||||||||||||||||||||||||||||
Progress |
|||||||||||||||||||||||||||||||||||||||||||
Progress |
|||||||||||||||||||||||||||||||||||||||||||
Progress |
• | ||||||||||||||||||||||||||||||||||||||||||
Progress |
|||||||||||||||||||||||||||||||||||||||||||
Complete |
|||||||||||||||||||||||||||||||||||||||||||
From Xxxx proposal noted, | |||||||||||||||||||||||||||||||||||||||||||
Tenderer’s Proposed Terms of Payment now | |||||||||||||||||||||||||||||||||||||||||||
Totals |
Dated this 12TH Day of JUNE 2009 | ||||||||
1 | Safety & Environment |
|
Review of Tenderers Safety & Environment Systems |
||
Discuss Training |
||
2 | Tender Form 3/A — Notice of Explanation |
|
Inclusion of Form of Notice of Explanation in Tender Price |
||
3 | Tender Form 3/B — Addendum |
|
Inclusion of Addendum in Tender Price |
||
4 | Tender Form 3/C — Tender Form |
|
Confirmation of Tender Price |
||
5 | Tender Form 3/D — Interrelationship Of Corporation |
|
Confirmation of full disclosure |
||
6 | Tender Form 3/E — Deed Of Guarantee, Undertaking & Substitution |
|
Required / Not Required |
||
7 | Tender Form 3/F — Departures From Tender Documents |
|
Details Discussion — Additional Information — Acceptance / rejection / further consideration |
||
8 | Tender Form 3/G — Key Personnel |
|
Introduction. Confirmation of availability — Confirmation of Positions of Authorisation |
||
9 | Tender Form 3/H — List Of Current Projects |
|
Update of Project Status / Progress. Discuss interference with / by other Projects |
||
10 | Tender Form 3/I — Wages Allowances & Employment Conditions |
|
Confirm preference for local employees — Confirm working week and R & R provision-Transportation of personnel — Meals for personnel — Sanitary installations |
||
11 | Tender Form 3/J — Sheets 1 & 2 — Tenders Plant & Equipment |
|
Adequacy / sufficiency of resources — Alternative resources — Current uncommitted
resource-Transportation to Site of plant and equipment |
||
12 | Tender Form 3/K — Work To Be Subcontracted |
|
Urgent approval required. Date required for submission of request and Approval |
||
13 | Tender Form 3/L — Cash Flow Program |
|
Review against Tender Program. Confirm Tender Price |
||
14 | Tender Form 10/A — Components Of Tender Price |
|
Accuracy of Tender break-up — Correctness of Rates—Adjustments /Additions required |
||
15 | Tender Form 10/B — Rates For Variations & Dayworks |
|
Adequacy / correctness of rates. Confirmation of detailed break-up of each rate—Confirmation of work week and site hours. Adjustments /Additions required—Accepted /
Rejected |
||
Detailed Construction Schedule |
Page 14 of 15
Submission of Detailed Construction Schedule — Consideration of Activities,
Dependencies,Resources, Durations, float / delay periods — Review of LGL supplied materials
and equipment — Approval / Rejection as Contract Schedule — Discussion of Clause 4.2.4 |
||
17 | Tender Form 10/D — Projected Manpower |
|
Comparison to Tender Form 10/C — Accepted / Rejected |
||
18 | Quality Control Procedures |
|
Review of Tenderers Quality Management System |
||
19 | Confirmation Of Site Inspection |
|
Acknowledgement of Site Inspection and Adequacy of Inspection made — Acknowledgement that
Tenderer has informed itself as required by Clause 2.3 |
||
20 | Insurances |
|
Confirmation of arrangement of insurances as per Section 6 — Confirmation of any LGL insurances and excesses |
||
21 | Financial Considerations |
|
Confirm currency of Tender, inclusion of Holdback and Security |
||
22 | Tender Letter |
|
Confirmation of rejection of any conditions in Tenderer’s submission or Post-Tender correspondence |
||
23 | Specification / Scope Of Work |
|
Detailed discussion to determine understanding of Specifications — Confirmation of
inclusion of all work in Scope Of Work — Alternative specification if any |
||
24 | Alternative Tender Submission |
|
Detailed discussion of alternative tender submission (if any) — Acceptance / Rejection |
||
25 | Date For Re-submission Of Information |
|
Summary of information to be re-submitted — Date for re-submission |
To:
|
The Tenderer | Xxxx Australia Pty Ltd, Xxxx Xxxxxx Division | ||
###-##-####A4 | ||||
Re:
|
Tender For | Autoclave Internal Equipment Installation of Brick Lining and Titanium Walls, on Lihir Island | ||
Work Package | MOPU-0035 | |||
We are pleased to advise that LGL hereby accepts your Tender dated for | ||||
a) | Fixed price lump sum of | |||
b) | Estimated total cost of | |||
(Based on the Tendered unit rates) | ||||
The following documents have been incorporated into the Contract Documents and form part of the Contract: | ||||
a) | Addenda & Notices Of Explanation (list) | |||
b) | Tender Documents as issued by LGL including: Volumes 3A, 3B & 3C | |||
c) | Minutes of Post-Tender / Pre-Award meeting and post tender correspondence (list) | |||
d) | Contract Schedule (attach) | |||
e) | Contractor’s Tender | |||
Your attention is drawn to the following matters: | ||||
1 | Pursuant to Clause 4.1.2 of the General Conditions Of Contract you are advised that the supervision of your Work will be the responsibility of: | |||
a) | Construction Manager | |||
b) | Engineering Manager | |||
c) | Area Manager | |||
2 | Pursuant to Clause 4.1.6 of the General Conditions Of Contract you are required to lodge Security in the sum of on or before . | |||
3 | Pursuant to Clause 4.1.7 of the General Conditions Of Contract you are requested to lodge evidence of the Insurances effected by you for the purposes of the Contract within thirty (30) days of work commencing. | |||
4 | Pursuant to Clause 4.2.3.1 of the General Conditions Of Contract you are requested to contact the Engineering Manager two (2) days prior to your mobilisation to Site to arrange a suitable time for a Pre-Start meeting. | |||
5 | Pursuant to Clause 4.1.4 of the General Conditions Of Contract you are required to commence Work on Site by . |
LGL
Page 15 of 15
4.1 | Preliminaries |
|
4.1.1 | Introduction |
|
4.1.2 | Supervision of the Work |
|
4.1.3 | Contractor’s Superintendence |
|
4.1.4 | Commencement of the Work |
|
4.1.5 | Access to Site |
|
4.1.6 | Security |
|
4.1.7 | Inspection and Provision of Insurance Policies |
|
4.2 | Administration |
|
4.2.1 | Written Communications |
|
4.2.2 | Site Instructions |
|
4.2.3 | Site Meetings |
|
4.2.4 | Progress and Programming of the Work |
|
4.2.5 | Suspension of the Work |
|
4.2.6 | Progress Claims and Payments |
|
4.2.7 | Variations |
|
4.2.8 | Dayworks |
|
4.2.9 | Adjustments to the Schedule of Rates |
|
4.2.10 | Goods or Services Provided by LGL |
|
4.2.11 | Assignment and Sub-contracting |
|
4.2.12 | Practical Completion |
|
4.2.13 | Completion |
|
4.3 | Work Procedures |
|
4.3.1 | Setting Out of the Work |
|
4.3.2 | Materials, Workmanship and Quality Control |
|
4.3.3 | Compliance with Applicable Laws and Standards |
|
4.3.4 | Control of Contractor’s Employees and the Employees of Sub-contractors |
|
4.3.5 | Industrial Relations |
|
4.3.6 | Occupational Health and Safety |
|
4.3.7 | Protection of Persons, Property and Existing Services |
|
4.3.8 | Care of the Work |
|
4.3.9 | Cleaning Up |
|
4.3.10 | Environmental responsibilities |
|
4.4 | Liabilities |
|
4.4.1 | Defects |
|
4.4.2 | Royalties, Patents, Copyrights and Other Intellectual Property Rights |
|
4.4.3 | Accident or Injury to Employees |
|
4.4.4 | Property Damage and Public Risk |
|
4.4.5 | Taxes and Contributions |
|
4.4.6 | Survival of Indemnities |
|
4.5 | Legalities |
|
4.5.1 | Construction of The Contract |
|
4.5.2 | Evidence of The Contract |
|
4.5.3 | Documents |
|
4.5.4 | Default or Insolvency |
|
4.5.5 | LGL’s Right to Terminate the Contract |
|
4.5.6 | Disputes |
|
4.5.7 | Service of Documents |
|
4.5.8 | LGL’s Right to Audit |
4.5.9 | Definitions and Interpretations |
4.1 | PRELIMINARIES | |
4.1.1 | Introduction | |
This section sets out the general terms and conditions, which are to regulate the performance of the Work, and the obligations and requirements of the various parties involved in the execution of the Work. These general terms and conditions set out the procedures to be followed by the various parties in relation to standard tasks or in the event of common occurrences and should be strictly followed to ensure the efficient administration of the Contract. The terms and conditions have been set out herein under headings and subheadings to assist in the practical use of the document. However, such headings do not form part of the General Conditions of Contract and cannot be used in the interpretation of the Contract. For example, conditions relating to liabilities are not restricted to those terms and conditions headed “4.4 LIABILITIES”. | ||
4.1.2 | Supervision of the Work | |
4.1.2.1 | LGL shall generally supervise the Work. The purpose of this general supervision is to advise the Contractor of any observed deviations from the requirements of the Contract, to direct variations to the Work, to accept or reject Work or material, and to decide all questions which arise in the execution of the Work. Such general supervision shall not relieve the Contractor in any way from providing continuous superintendence for the detailed direction of the Work or from its obligation to complete the Work in accordance with the Contract. | |
4.1.2.2 | The operational structure of LGL will be generally as shown in Appendix 5/A and general supervision of the Work will occur on three levels: Area Manager, Engineering Manager and Construction Manager, in accordance with the guidelines set out hereunder: |
i) | Area Manager | ||
The Area Manager shall be directly responsible for the day-to-day general supervision of the Work and will be the Contractor’s communication link with LGL. The role of the Area Manager will be such that to ensure positive progress he or she will assist, direct and, if appropriate, offer advice to the Contractor both verbally and in writing but shall do so with the benefit of immunity from causing any liability or additional costs as a result of his or her actions. | |||
If the Contractor considers that any actions of the Area Manager could cause additional costs or create any liability, whether for negligence or otherwise, the Contractor shall ignore such actions and immediately seek directions from the Engineering Manager. By agreement to these conditions, the Contractor absolves the Area Manager and LGL from any such liability and accepts that such immunity is necessary for the effective day-to-day general supervision of the Work and that its rights are otherwise sufficiently protected by its access to the Engineering Manager for directions. | |||
In cases where the Contractor may be performing Work in more than one area, different Area Managers may be nominated for each area. | |||
ii) | Engineering Manager | ||
The Engineering Manager shall be responsible for the technical and engineering supervision of the Work, shall deal with all matters relative to design, testing and approval of the Work, and shall decide all questions which arise in the execution of the Work which cannot be resolved by the Area Manager or which may involve any extra cost. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 1 |
All directions issued by the Engineering Manager shall be in writing in the form of Site Instructions and where practical, shall be issued to the Contractor via the Area Manager. The Contractor shall comply with all such directions. | |||
iii) | Construction Manager | ||
The Construction Manager shall be responsible for the overall supervision and co-ordination of the Total Project. In relation to this Contract, that responsibility will involve attendance at meetings and discussions with the Contractor on overall performance. If the Contractor believes that any action or direction by the Construction Manager constitutes a variation to the Contract, or will involve it in any additional costs, it shall obtain a Site Instruction from the Engineering Manager, prior to proceeding with the variation or complying with the direction. |
4.1.3 | Contractor’s Superintendence | |
4.1.3.1 | Activities relating to the execution of the Work shall be directly supervised by the Contractor’s Key Personnel listed on Tender Form Appendix 3/G. Should the Contractor wish to substitute for any of these Key Personnel, such substitution shall be subject to the approval of LGL and shall be conditional upon the substituted Key Personnel being of equal experience and competence. The Contractor’s supervisory staff, such as foremen and leading hands, shall continuously superintend all Work (whether executed by Subcontractors or otherwise) to provide detailed direction of the Work at the location where Work is being executed. | |
4.1.3.2 | It shall be the responsibility of the Contractor to effectively organize its own internal communications, therefore any direction given to any person supervising the Work on behalf of the Contractor shall be deemed to have been given to the Contractor and any matters within the knowledge of such persons, shall be deemed to be within the knowledge of the Contractor. | |
4.1.3.3 | The Contractor’s Key Personnel shall be fluent in the English language. | |
4.1.4 | Commencement of the Work | |
4.1.4.1 | The Contractor shall commence Work on Site within seven (7) days of the date of issue of the Letter of Acceptance or within such extended period as may be nominated in the Letter of Acceptance. | |
4.1.5 | Access to Site | |
4.1.5.1 | LGL shall, on the date for the Contractor to commence Work on Site, give to the Contractor access to sufficient of the Site to enable it to commence Work and thereafter to execute the Work in accordance with the requirements of the Contract. As the Work is being carried out as part of an expansion to an operating mine, access will not be free and clear or unrestricted but will be subject to operating restrictions. At all times, operating requirements shall take precedence over access requirements for the Work. | |
4.1.5.2 | Should any delay take place in giving the Contractor initial access to the Site to commence Work, the delay shall be deemed not to constitute a breach of contract but the Contract Schedule shall be amended to the extent necessary to overcome such delay. The objective of any such amendment shall be to maintain completion dates. Should any |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 2 |
subsequent delay in providing ongoing access take place, the provisions of Clause 4.2.4 shall apply. | ||
4.1.5.3 | The Contractor shall not be entitled to unrestricted access or sole possession of any part of the Site as other contractors and persons will be carrying out work on the Site concurrently with the Contractor and in many instances in the same work area. The Contractor shall adopt all necessary measures to prevent and avoid conflicts. | |
4.1.6 | Security | |
4.1.6.1 | The Contractor shall provide security equal to of the Contract Sum for the purpose of ensuring the due and proper performance of the Contract and of satisfying the obligations of the Contractor under the Contract. LGL may recover all debts due and owing from the Contractor to LGL from the security if not otherwise paid by or recovered from the Contractor. The security shall be in the form of cash, bank cheque, irrevocable letter of credit or Unconditional Bank Guarantee in the form set out in Appendix 5/B. | |
4.1.6.2 | The security shall be lodged by the Contractor with LGL within fourteen (14) days after the Date of Acceptance of Tender. | |
4.1.6.3 | If the Contractor fails to provide the security within the time prescribed in Clause 4.1.6.2, LGL may terminate the Contract, pursuant to Clause 4.5.4. | |
4.1.7 | Inspection and Provision of insurance Policies | |
4.1.7.1 | Before commencing the Work and whenever requested in writing, at any time and from time to time thereafter, so to do by LGL, the Contractor shall produce evidence to the satisfaction and approval of LGL of the insurances effected and maintained by the Contractor and its Subcontractors for the purposes of this Contract. | |
4.1.7.2 | The identity of the insurers and the form of the policies shall be subject to the approval of LGL. | |
4.1.7.3 | If, after being requested in writing by LGL so to do, the Contractor fails to produce evidence of compliance with its insurance obligations under this Contract, LGL may effect and keep in force any such insurance and pay such premiums as may be necessary for that purpose, and the amount so paid shall be a debt due from the Contractor to LGL. | |
4.1.7.4 | The Contractor shall, as soon as practicable, inform LGL in writing of the occurrence of any event that may give rise to a claim under a policy of insurance effected as required by this Contract. The Contractor shall ensure that LGL is kept fully informed of subsequent actions and developments concerning the claim. | |
4.1.7.5 | The effecting of insurance as required by this Contract shall not in any way limit the liabilities or obligations of the Contractor under the Contract. | |
4.1.7.6 | The insurance requirements of this Contract are set out in Section 6. | |
4.2 | ADMINISTRATION | |
4.2.1 | Written Communications | |
4.2.1.1 | All written communications from the Contractor to LGL shall be addressed to the Engineering Manager and shall have a reference code on the top right-hand corner. This code shall be: | |
C/Work Package No./ Reference No. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 3 |
The reference No. can be any consecutive series of numbers provided that the same number is never used twice. | ||
4.2.1.2 | All written communications from LGL to the Contractor shall be similarly referenced but prefixed with the letter L, i.e. L/Work Package No./Reference No. | |
4.2.1.3 | All communications shall be in the English language. | |
4.2.1.4 | The Contractor shall treat all information relating to the business, operations, practices, policies, procedures, notes, memorandums, reports or logs of LGL as strictly confidential and shall only disclose this information to a third party upon receipt of prior written approval from LGL. | |
4.2.2 | Site Instructions | |
4.2.2.1 | Ail written directions and on Site communications (other than verbal communications by the Area Manager pursuant to Clause 4.1.2.2) shall be issued to the Contractor by Site Instructions as detailed in Appendix 5/C and in accordance with the Site Instruction Flow Chart Appendix 5/D. | |
4.2.2.2 | All Site Instructions are issued subject to the condition that they are either: |
i) | No cost variation to the Contract; | ||
ii) | Issued with Quotation Price Request N° xx (work not to proceed until Contract Variation is issued); or | ||
iii) | Issued with Dayworks sheet N° xx (work to proceed on Dayworks basis). |
as indicated by the notation adjacent to the checked box. | ||
4.2.2.3 | The Contractor is required to sign the Site Instruction and return copy No. 4 to the Engineering Manager. By signing the Site Instruction, the Contractor agrees to the condition(s) as noted. In the event that any Site Instruction is inadvertently issued without any checked box it shall be deemed to be issued on the condition that it is a “No cost variation to the Contract”. If the Contractor does not agree with the conditions as noted, the Contractor shall immediately, and prior to taking any action in relation to the Site Instruction, arrange a meeting with the Engineering Manager to resolve the issue. If the Contractor fails to sign the Site Instruction but proceeds to comply with the Site Instruction, such action shall be deemed to constitute acceptance by the Contractor of the conditions. This deemed acceptance shall not affect LGL’s right to suspend payments due to the Contractor’s failure to sign the Site Instruction | |
4.2.2.4 | Notwithstanding the issue of any Site Instruction, Quotation Price Request, Contract Variation or Dayworks Sheet, in the event that any such document is subsequently found to authorize additional Work which is already within the Scope of Work, the Contractor shall not be entitled to any adjustment to the Contract Sum. | |
4.2.3 | Site Meetings | |
4.2.3.1 | LGL shall convene a pre-start meeting with the Contractor to correspond with the Contractor’s mobilization to Site. The purpose of this meeting will be to introduce the Contractor’s Key Personnel to LGL’s on-site personnel and to discuss Site procedures and the Contract Schedule. | |
4.2.3.2 | During the execution of the Work, LGL shall convene a weekly co-ordination meeting. Twenty-four (24) hours prior to this meeting, the Contractor shall submit its Progress |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 4 |
Reports required by Clause 4.2.4 and any subsequent revisions to the Contract Schedule. A draft agenda for this meeting is set out in Appendix 5/E. | ||
4.2.3.3 | The Contractor shall be represented at site meetings, as may be convened by LGL, by the attendance of its Key Personnel and any other personnel requested to be in attendance by LGL. | |
4.2.3.4 | The purpose of site meetings shall be to openly discuss all matters relative to the Work and the progress thereof. Minutes of the meetings shall be kept by LGL and issued to the Contractor as soon as possible thereafter. Should the Contractor not agree with the accuracy of the minutes, it shall notify LGL within forty-eight (48) hours of receipt thereof of any inaccuracy. Failure to so notify will be deemed acceptance by the Contractor of the minutes as a true and accurate record. | |
4.2.3.5 | Notwithstanding the recording of such minutes, nothing which transpires at any meeting, shall constitute a direction or an agreement of any kind unless and until the Engineering Manager has issued a Site Instruction confirming such direction or agreement. | |
4.2.4 | Progress and Programming of the Work | |
4.2.4.1 | The Contractor shall proceed with the Work in accordance with the Contract Schedule. | |
4.2.4.2 | If the Contractor is not achieving a rate of progress, which is in accordance with the Contract Schedule, LGL may proceed in accordance with Clause 4.5.4. | |
4.2.4.3 | The Contractor shall submit Progress Reports in the format set out in Appendix 5/F (Sheets 1 to 3). The Progress Report (Appendix 5/F, Sheet 1) shall be submitted to and agreed with the Area Manager, at least every seven (7) days (and at least twenty-four (24) hours prior to the weekly coordination meeting). Appendix 5/F, Sheet 2 “Daily manpower” and Sheet 3 “Plant and Equipment Usage” shall be submitted to and agreed with the Area Manager each day. | |
4.2.4.4 | If the Contractor’s weekly Progress Report shows any actual or predicted progress less than the progress required to maintain the Contract Schedule, then the Contractor shall, together with the Progress Report, submit a Revised Schedule showing the effect of the lack of progress and an Alternative Schedule showing how the lost time can be made up so that all Work can be completed in accordance with the Contract Schedule. If the Revised and/or Alternative schedules are relatively minor changes to the existing Contract Schedule they may, in the first instance, be marked up on a copy of the existing Contract Schedule in two distinctly different colours. | |
4.2.4.5 | If the Contractor considers that any delay in progress since its last Progress Report has or will be caused by an act or omission on the part of LGL, it shall, together with the weekly Progress Report (Appendix 5/F, Sheet 1), submit a statement of facts upon which it bases such an assertion and a quotation for the extra costs, if any, of proceeding in accordance with the Alternative Schedule. The Contractor shall have no entitlement to any extra costs incurred more than seven (7) Days prior to submission of the statement of facts. | |
4.2.4.6 | LGL shall direct the Contractor, by written Site Instruction, which schedule to follow and thereafter such schedule shall become the Contract Schedule. If the Contractor has submitted only a marked up copy of the existing Contract Schedule, it shall immediately produce a properly amended Contract Schedule to show either the Revised or Alternative form in accordance with the direction given by LGL. | |
4.2.4.7 | In the event that LGL directs the Contractor to proceed with the Alternative Schedule and considers that the lack of progress was or would have been caused wholly or in part |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 5 |
by an act or omission on the part of LGL, an appropriate Contract Variation shall be issued. | ||
4.2.4.8 | In the event that LGL directs the Contractor to proceed with the Revised Schedule and considers that the lack of progress was or would have been caused wholly or in part by an act or omission of LGL, no Contract Variation shall be issued at this time, however, the Site Instruction directing the use of the Revised Schedule shall record the extent to which LGL accepts responsibility for the delay. At Practical Completion, such Site Instructions shall be reviewed in accordance with the following principles: |
i) | The period of delay for which LGL has accepted responsibility shall be totalled (and where partial responsibility has been accepted a corresponding portion of the period by which the completion date changed shall be used). | ||
ii) | A credit period shall be determined for Variations and Dayworks by determining the percentage value of Contract Variations and Dayworks to the Contract Sum and applying this percentage to the Original Contract Period. | ||
iii) | The actual period of overrun (if any) of the Date for Practical Completion shall be determined by calculating the difference between the Date for Practical Completion and the date upon which the Contractor first applied for Practical Completion pursuant to Clause 4.2.12. | ||
iv) | The Reimbursable Period of delay (if any) shall be calculated by the following formula: | ||
Reimbursable Period = the lesser of: |
a) | actual period of overrun less credit period; or | ||
b) | total period of delay for which LGL has accepted responsibility. |
4.2.4.9 | A Contract Variation shall be issued for the Contractor’s Actual Onsite Overhead Costs (as defined by Clause 4.5.9.1) for the Reimbursable Period calculated by ascertaining the average of the Contractor’s Actual Onsite Overheads at the time of each accepted delay and applying this to the Reimbursable Period. | |
4.2.4.10 | It is specifically agreed that the amount of the Contract Variations issued pursuant to Clause 4.2.4.7 or 4.2.4.9 shall represent the Contractor’s total entitlement for the consequence of any delays for which LGL has accepted responsibility. | |
4.2.4.11 | Where the Contract Schedule makes provisions for delays by the inclusion of “float periods”, the use of such float periods in amended Contract Schedules shall be subject to the approval of LGL. | |
4.2.4.12 | Where two or more concurrent events cause delay, then the events, if any, caused by or which are the responsibility of the Contractor shall be regarded as the cause of delay for the purpose of Clauses 4.2.4.7 and 4.2.4.8. | |
4.2.4.13 | Each issue of the Contractor’s amended Contract Schedule shall be appropriately marked with the date of issue and an issue identification number or letter and shall list the amendments made from the previous issue. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 6 |
4.2.4.14 | The Contractor shall not be entitled to any additional payment for complying with the provisions of this Clause except as expressly set out herein, it being expressly agreed that such requirements form part of the Contractor’s offer to perform the Work for the Contract Sum and that any risks in relation thereto are accepted by the Contractor. | |
4.2.4.15 | The Contractor shall only be entitled to recover the costs of delay or acceleration in accordance with the procedures set out in this clause 4.2.4. | |
4.2.5 | Suspension of the Work | |
4.2.5.1 | LGL may instruct the Contractor to suspend the progress of the whole or any part of the Work, for such time or times as LGL may think fit. | |
4.2.5.2 | Should the Contractor wish to suspend the progress of the whole or any part of the Work, it shall, in writing, notify LGL and explain the reasons for the suspension. LGL shall thereupon, if it considers it necessary or reasonable so to do, grant permission for a suspension of the whole or any part of the Work for such time or times as it deems fit. | |
4.2.5.3 | When the reason for the suspension no longer exists, LGL shall instruct the Contractor to recommence work on the whole or on any relevant part of the Work and the Contractor shall comply with such direction promptly. | |
4.2.5.4 | The Contractor shall have no right to receive any additional payment by reason of any direction to suspend the progress of all or any part of the Work other than in accordance with the provisions of Clause 4.2.4. | |
4.2.5.5 | The suspension of the progress of the whole or any part of the Work shall not affect the obligation of the Contractor to execute the Work. | |
4.2.6 | Progress Claims and Payments | |
4.2.6.1 | The Contractor shall only be entitled to claim by way of progress payments for Work executed (excluding materials not incorporated in the works) comprising: |
i) | The Contract value of Work executed; | ||
ii) | The value of Work executed pursuant to any issued Contract Variations; and | ||
iii) | The value of Work executed pursuant to an issued Site Instruction authorising Work to proceed on a Dayworks basis and evidenced by Dayworks sheets signed by the Area Manager. |
4.2.6.2 | Once each month, the Contractor shall prepare and present to the Area Manager a Progress Claim in the form set out in Appendix 5/G (Sheets 1 to 4). The Area Manager shall then make an assessment of the value of Work done and completed and sign the appropriate sections of the Progress Claim forms noting any adjustments thereto. | |
4.2.6.3 | Should the Area Manager make any adjustments to the Contractor’s Progress Claim, the Area Manager and the Contractor shall jointly review the adjustments so that the Contractor may accept or reject the adjustment. Such acceptance or rejection shall be noted on the appropriate section of the Progress Claim forms and shall be signed by one of the Contractor’s Key Personnel holding a position of authorization as noted in Tender Form Appendix 3/G | |
4.2.6.4 | Should the Contractor not accept the adjustments, the matter shall be referred to the Engineering Manager who shall decide the extent or amount of Work for the purpose of the Progress Claim. In making this decision, the Engineering Manager shall not be under any obligation to measure or otherwise correctly determine the extent or amount of Work, |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 7 |
but shall merely make an expedient decision to resolve the issue. The Engineering Manager’s decision shall be final and binding for the purpose of the Progress Claim and the Contractor shall not be entitled to claim any additional monies, including interest, as a consequence of the Engineering Manager’s decision. | ||
4.2.6.5 | As soon as the extent of Work has been agreed upon by the Area Manager and the Contractor, or decided by the Engineering Manager, the Contractor shall submit the Progress Claim to the Engineering Manager complete with any statutory required documents and the originals of any Dayworks sheets claimed for. | |
4.2.6.6 | The Engineering Manager shall not accept and shall return to the Contractor any Progress Claim which is either not in the prescribed form, including cost codes, etc., not signed by the Area Manager (and Engineering Manager if required) or hot accompanied by the appropriate documentation. | |
4.2.6.7 | The Engineering Manager shall determine the amount of the progress payment, which shall be the total gross value of the Work, executed in accordance with Clause 4.2.6.1 less: |
i) | Any progress payments already made in respect of the Work for which the gross value was determined; | ||
ii) | hold back on the Adjusted Contract Sum; | ||
iii) | The amount of any payments which are overdue from the Contractor to any employees, agents, consultants, Subcontractors or Suppliers relating to the Work; and | ||
iv) | Any other proper withholding or deduction (including debts due from the Contractor to LGL). |
The Engineering Manager shall issue to the Contractor a copy of the Progress Claim showing the value certified and the adjustments (if any) made. | ||
4.2.6.8 | LGL shall pay the Contractor the net amount for payment to the Contractor shown on the Progress Claim within Thirty (30) days from the date of acceptance by the Engineering Manager of the Contractor’s Progress Claim. | |
4.2.6.9 | All amounts due and payable to the Contractor shall be paid to the Contractor either by cheque at the place for payment nominated in Clause 1.8 (Total Project Data) or via electronic funds transfer into the Contractor’s nominated bank account, | |
4.2.6.10 | If LGL shall be in default in making any payment, and if such default continues for seven (7) days after service of a notice in writing by the Contractor demanding such payment, then the Contractor shall be entitled to claim interest at the Contractor’s then current bank overdraft rate from seven (7) days after the date of such notice until payment is made. | |
4.2.6.11 | The payment of monies shall not be taken as evidence against, or as an admission by, LGL that any Work or item of Work has been constructed or executed in accordance with the Contract, or of the value thereof, but shall be taken to be payment on account only. | |
4.2.6.12 | By submission of each Progress Claim, the Contractor certifies that all employees, agents, consultants, Subcontractors and suppliers have been paid all amounts properly due to them relating to the Work and that the Contractor has notified LGL of all Claims of whatsoever nature that it may have against LGL arising out of circumstances occurring since submission of the Contractor’s previous Progress Claim. LGL shall not be liable to |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 8 |
the Contractor for any Claim of whatsoever nature with respect to which it has not been so notified. | ||
4.2.6.13 | If at any time the Contractor has not done something which it is required to do under the Contract (such as complied with a Site Instruction, provided Progress Reports, submitted Quotation Price Request forms or produced documents) LGL may withhold payments until such obligations are complied with and the provisions of Clause 4.2.6.10 shall not apply. | |
4.2.7 | Variations | |
4.2.7.1 | The Contractor shall vary the Work as directed in writing by LGL and no Variation shall vitiate this Contract. If at any time during the progress of the Work, LGL determines that the form, quality or quantity of the Work should be varied, LGL may require the Contractor to: |
i) | Increase, decrease or omit any part of the Work; | ||
ii) | Change the character or quality of the Work; | ||
iii) | Change the levels, lines, positions or dimensions of any part of the Work; or | ||
iv) | Execute additional work. |
4.2.7.2 | The Contractor shall vary the Work only upon receipt of a Contract Variation or a Site Instruction authorising the Variation to proceed on a Dayworks basis. | |
4.2.7.3 | If a Variation to the Work is required by LGL, the Contractor shall be issued with a Site Instruction as per Appendix 5/C (Site Instruction) together with either a Dayworks sheet or a Quotation Price Request. If the Site Instruction is issued with a Dayworks sheet, the requirements of Clause 4.2.8 shall be followed. If the Site Instruction is issued with a Quotation Price Request, the procedure to be followed shall be as set out in Clauses 4.2.7.4 to 4.2.7.6. | |
4.2.7.4 | Quotation Price Requests will be issued as per Appendix 5/H (Sheets 1 and 2) and generally in accordance with the Quotation Price Request flow chart, Appendix 5/I. | |
4.2.7.5 | Upon receipt of the Quotation Price Request, the Contractor shall price the Variation at the rates included in the Schedule of Rates for Variations and Dayworks (Tender Form Appendix 10/B sheet 1) to the extent that such rates are applicable. If no such rates are applicable, the Contractor shall set out the labour and plant components of each item of the Variation and extend the quantities at the unit labour and plant rates applicable to the class of labour or plant involved as set out in the Schedule of Rates for Variations and Dayworks (Tender Form Appendix 10/B sheets 2 and 3) and shall set out the material cost components of each item of the Variation plus any Additional, Reasonable and Valid Charge for Procurement and Delivery to the Site (refer to Clause 4.5.9.1) of such material. All items shall be totalled to arrive at the total fixed price lump sum quotation. | |
4.2.7.6 | The Contractor shall present the completed Quotation Price Request to the Engineering Manager within forty eight (48) hours of its issue and provide whatever explanations or details as may be required in order to satisfy the Engineering Manager that the quoted price is correct and reasonable. If any adjustments are agreed upon, such adjustments shall be noted on the Quotation Price Request. Once satisfied of the correctness and reasonableness of the Quotation Price, the Engineering Manager shall approve the Quotation Price Request for issue of a Contract Variation as per appendix 5/J and generally in accordance with the Contract Variation flow chart appendix 5/K). The approval of the Engineering Manager shall be in principle only and will be subject to checking the quantities and rates in detail. Acceptance of the quotation will only be |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 9 |
affected by the issue of a Contract Variation. The Contractor shall not proceed with the Variation until receipt by it of the Contract Variation. | ||
4.2.7.7 | If the Contractor and LGL do not agree upon the value of the Variation, LGL may have the Variation executed by others and if the Variation affects any of the Work not commenced or not completed, then that part of the Work or the remaining balance thereof, may also be deleted from the Contract at the full Contract value thereof and the Contractor shall not be entitled to claim any costs, loss or damage as a consequence of such deletion. | |
4.2.7.8 | LGL may issue to the Contractor from time to time during the progress of the Work revised drawings or new details which may or may not involve Variations to the Work. All drawings and details will be issued to the Contractor by way of a Site Instruction. Should the Contractor come into possession of any revised drawings or new details without a Site Instruction, it shall immediately refer to the Engineering Manager for a Site Instruction. | |
4.2.7.9 | Revised drawings or new details shall not form a part of the Contract nor shall they be used for execution of the Work unless accompanied by a Site Instruction authorising their use. If revised drawings or new details issued by LGL for the purpose of a Quotation Price Request affect any part of the Work in progress, the Contractor shall immediately refer to the Engineering Manager for directions. | |
4.2.7.10 | Variations to the Work shall only be executed by the Contractor’s existing resources if such resources have the capacity to carry out the Variation, without impact on the Contract Schedule. In all other cases, the Contractor shall provide additional resources (the costs of which are included, or shall be deemed included, in the rates tendered by the Contractor in the Schedule of Rates for Variations and Dayworks — Appendix 10/B). | |
4.2.8 | Dayworks | |
4.2.8.1 | If the Engineering Manager issues a Site Instruction on the condition that a Variation is to proceed on a Dayworks basis, the Contractor shall immediately proceed with the Variation so directed and shall record the resources utilised on the first day, on the Dayworks sheets (Appendix 5/L) which are issued with the Site Instruction. | |
4.2.8.2 | At the conclusion of the first days Work, the Contractor shall present to the Area Manager the completed Dayworks sheet for verification and approval, whereupon the Area Manager shall issue the Dayworks sheet for the following day’s Work. This procedure shall be repeated until completion of the Variation ordered. | |
4.2.8.3 | Under no circumstances will the Area Manager verify or approve a Dayworks sheet other than an original Dayworks sheet issued for Dayworks on that day. | |
4.2.8.4 | LGL shall not be liable to pay the cost of any Variation executed pursuant to a Site Instruction issued on the condition that the Variation is to proceed on a Dayworks basis, unless the Work is recorded, verified and approved as set out above. | |
4.2.8.5 | Dayworks shall be priced as follows: |
i) | LABOUR shall be priced at the unit labour rates for Variations and Dayworks (Tender Form Appendix 10/B sheet 2) applicable to the class of labour engaged on the Work (excluding superintendence and administration). | ||
ii) | PLANT AND EQUIPMENT shall be priced at the unit plant and equipment rates for Variations and Dayworks (Tender Form Appendix 10/B sheet 3). |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 10 |
iii) | MATERIAL shall be priced at the Contractor’s Actual Direct Cost plus any Additional Reasonable and Valid Charges for Procurement and Delivery (refer to Clause 4.5.9.1). |
4.2.8.6 | If the Schedule of Rates for Variations and Dayworks does not contain a rate necessary for pricing the Dayworks, a new rate shall be calculated based on the same method of calculation used to derive similar rates in the Schedule of Rates for Variations and Dayworks (Tender Form Appendix 10/B). | |
4.2.8.7 | Dayworks shall only be executed by the Contractor’s existing resources if such resources have the capacity to carry out the Work, without impact on the Contract Schedule. In all other cases, the Contractor shall provide additional resources (the cost of which are included, or shall be deemed included, in the rates tendered by the Contractor in the Schedule of Rates for Variations and Dayworks — Appendix 10/B) | |
4.2.8.8 | At the end of each Progress Claim period, when the extent of Dayworks for the period has been agreed upon, a Contract Variation shall be issued to adjust the Contract Sum by the value so agreed. This Contract Variation number shall be noted on subsequent Dayworks Progress Claims (Appendix 5/G, Sheet 4/4) but shall not be included in the Schedule of Variations (Appendix 5/G, Sheet 3/4). | |
4.2.9 | Adjustments to the Schedule of Rates | |
4.2.9.1 | If the Contract is a Schedule of Rates Contract, the quantities listed are provisional only and are estimates of the quantities of work required to execute the Work defined in the Original Scope of Work. Should the actual quantities required be different to the provisional quantities, the Contractor shall, as soon as the difference becomes apparent, but in any event, prior to including any additional quantities in a Progress Claim, submit a detailed quantity take off to the Engineering Manager who shall verify the quantities. | |
4.2.9.2 | The amount payable to the Contractor for each item in the Schedule of Rates shall be determined by application of the Tender Rates to the actual quantity unless the actual quantity varies from the provisional quantity by more than in which case the following procedure shall apply: |
i) | where the actual quantity is greater than of the provisional quantity, the rate applicable to the quantity in excess of the of the provisional quantity shall be adjusted to reflect any change in the Actual Direct Costs of carrying out that additional quantity; and | ||
ii) | where the actual quantity is less than of the provisional quantity, the rate shall be adjusted to reflect any change in Actual Direct Costs of carrying out that quantity. |
4.2.9.3 | This Clause shall be read subject to the provisions of Clause 4.5.3 and shall not operate to defeat the intent and purpose of that Clause. All costs associated with the Original Scope of Work shall be deemed included in the Tender Rates, even if these costs are not described in any item description in the Schedule of Rates. | |
4.2.10 | Goods or Services Provided by LGL | |
4.2.10.1 | During the execution of Work, in addition to items specifically referred to in the Contract, various goods and services may be provided to the Contractor by LGL. The Contractor will be charged for such additional goods and services at LGL’s cost plus which shall be deducted from payments due to the Contractor as back charges or may be otherwise recovered as a debt due. | |
4.2.10.2 | The provision of such goods and services shall be recorded on warehouse requisitions or agreed back charge forms. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 11 |
4.2.11 | Assignment and Subcontracting | |
4.2.11.1 | The Contractor shall not assign, mortgage, charge or encumber this Contract or any part hereof, or any benefit or monies or interest hereunder, without the written approval of LGL. | |
4.2.11.2 | The Contractor shall not Subcontract any section of the Work without the written consent of LGL. Any request by the Contractor to Subcontract any section of the Work shall nominate the proposed Subcontractor and shall include Key Personnel, Current Projects, Wages and Employment Conditions, Plant and Equipment details and safety and environmental information for the Subcontractor in the same form as those submitted by the Contractor at time of Tender and shall state whether any such items are in addition to, or replace, those items nominated by the Contractor in its Tender. | |
4.2.11.3 | Approval to Subcontract any section of the Work shall not alter, in any way, the Contractor’s obligations and/or liabilities under the Contract. | |
4.2.12 | Practical Completion | |
4.2.12.1 | The Contractor shall give the Engineering Manager fourteen (14) days notice in writing of the date upon which the Contractor anticipates that Practical Completion will be reached. At the commencement of the fourteen (14) day period, the Contractor shall arrange with the Area Manager and any technical advisers to the Area Manager (such as electrical and mechanical inspectors) a preliminary inspection of the Work. The purpose of this inspection will be to prepare a provisional list of items requiring attention prior to Practical Completion. The Area Manager may add to this list as any other items become apparent prior to the Contractor applying for Practical Completion. | |
4.2.12.2 | The purpose of these provisional lists is to assist the Contractor, but they shall not substitute for the Contractor’s own quality control, nor shall they replace the Practical Completion inspection by the Engineering Manager from which additional items may result. | |
4.2.12.3 | When the Contractor is of the opinion that Practical Completion has been reached, the Contractor shall request, in writing, the Engineering Manager to issue a Certificate of Practical Completion. Within fourteen (14) days of the receipt of the request, the Engineering Manager shall give to the Contractor a Certificate of Practical Completion as per Appendix 5/M, stating the date of Practical Completion, or shall give the Contractor, in writing, the reasons for not issuing the certificate and detailing any matter which the Contractor should attend to before re-applying to the Engineering Manager for the issue of a Certificate of Practical Completion in the same manner as the original application. | |
4.2.12.4 | The issue of a Certificate of Practical Completion issued pursuant to this Clause, shall not constitute approval of any Work or other matter in respect of which it is issued, nor shall it be taken as an admission by LGL of the due performance of the Contract, or any part thereof, or of the accuracy of any Claim or demand made by the Contractor, or of additional or varied Work having been ordered by LGL, nor shall any such Certificate negate or prejudice any of the rights or remedies of LGL. Following the issue of the Certificate of Practical Completion, the Contractor shall be entitled to claim a Progress Payment pursuant to Clause 4.2.6 for the full value of Work executed, which payment shall not be subject to the hold back. LGL however may, at its absolute discretion, hold back an amount sufficient to cover the full costs of any minor defects or omissions existing at the stage of Practical Completion, until all such items are rectified. LGL may also, at its absolute discretion, allow a reduction in the amount of security held pursuant to Clause 4.1.6. However, LGL shall not be under any obligation to allow such reduction, as the intent of such security is that it should be held, in full, until Contract Completion. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 12 |
4.2.12.5 | As the Work is part of the Total Project, it will be necessary for LGL to take over sections of the Work as they reach an appropriate stage of completion so that LGL and other contractors can execute other work in, upon, or associated with a section of the Work to achieve completion of the Total Project. Such takeover shall not constitute Practical Completion of any such section and shall not relieve the Contractor of any of its obligations under the Contract. | |
4.2.13 | Completion | |
4.2.13.1 | At the expiration of the Defects Liability Period, when all Work has been finally and satisfactorily executed, and the Contractor has fulfilled all its other obligations under the Contract, LGL shall issue to the Contractor a Final Certificate, as per Appendix 5/N. | |
4.2.13.2 | The issue of the Final Certificate shall constitute conclusive evidence that all Work has been finally and satisfactorily executed by the Contractor except in so far as it is proven in any proceedings in a court of competent jurisdiction that the Final Certificate is in any particular erroneous by reason of: |
i) | fraud, dishonesty or deliberate concealment, on the part of the Contractor or any of its Subcontractors, or of any of the employees or agents of the Contractor or its Subcontractors, relating to the Work or any part thereof, or to any matter dealt with in the Final Certificate; or | ||
ii) | any defect, including any omission, in the Work or any part thereof which reasonable inspection at the time of the issue of the Final Certificate would not have disclosed; or | ||
iii) | any accidental or erroneous inclusion or exclusion of any Work, materials, goods or figure in any computation, or an arithmetical error in any computation. |
4.2.13.3 | Following the issue of the Final Certificate, the Contractor shall be required to sign a Deed of Release as per appendix 5/0. Upon receipt of the Deed of Release, LGL shall return to the Contractor, the security or such part of it as LGL is then holding. | |
4.3 | WORK PROCEDURES | |
4.3.1 | Setting out of the Work | |
4.3.1.1 | LGL shall supply the information necessary to enable the Contractor to set out the Work and, if appropriate, shall supply reference level and location marks. The Contractor shall set out the Work in accordance with the Contract and shall provide all instruments necessary for that purpose. | |
4.3.1.2 | The Contractor shall keep in their true position all level and location marks supplied by LGL, and if disturbed, shall immediately reinstate same and notify LGL of the reinstatement prior to proceeding with any Work which could be affected by the reinstated level or location xxxx. | |
4.3.2 | Materials, Workmanship and Quality Control | |
4.3.2.1 | Materials used in the Work and the standards of workmanship shall be in conformity with the provisions of the Contract. In the absence of any such provision in the Contract in respect of any material or standard of workmanship, that material or standard of workmanship, as the case may be, shall be of a kind which is suitable for its purpose and is consistent with the nature and character of the Work. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 13 |
4.3.2.2 | Unless otherwise specified in the Contract, any materials to be incorporated into the Work shall be new. | |
4.3.2.3 | The Contractor shall, at its own cost, provide adequate storage and protection for all materials so as to preserve their quality and fitness for the Work. | |
4.3.2.4 | The Contractor shall maintain a system of quality control acceptable to LGL and consistent with the complexity of the work undertaken. The system shall be maintained solely by the Contractor and shall not be delegated as part of any Subcontract, purchase agreement or otherwise. | |
4.3.2.5 | LGL may, at any time before the issue of the Final Certificate, reject any part of the Work which is not in accordance with the Contract, and may direct its replacement, correction or removal (whether it has been the subject of a payment or not). Such rejection or direction shall be made or given as soon as practicable after the discovery by LGL of its non-compliance with the Contract. If LGL directs the Contractor to replace or correct any part of the Work, the Contractor shall commence the replacement or correction within five (5) Days after the receipt by it of the direction and shall complete the replacement or correction promptly and to the satisfaction of LGL without affecting the Contract Schedule. If LGL directs the Contractor to remove from the Site any material, which is not in accordance with the Contract, the Contractor shall do so promptly. All such replacements, corrections and removals shall be at the Contractor’s cost. If the Contractor fails to comply with any direction given by LGL pursuant to this Clause, LGL may carry out the replacement, correction or removal and the cost incurred shall be a debt due from the Contractor to LGL. | |
4.3.2.6 | All costs, expense, loss or damage borne or incurred by LGL as a result of, or consequential upon the Contractor failing to carry out the Work or any part of the Work in accordance with the Contract shall be reimbursed or made good to LGL by the Contractor upon request and in default thereof may be recovered by LGL as a debt due from the Contractor to LGL. | |
4.3.3 | Compliance with Applicable Laws and Standards | |
4.3.3.1 | The Contractor shall comply with all Applicable Laws and shall give all notices and pay and bear all fees in connection therewith. The Contractor shall ensure that the Work complies with all relevant Standards. | |
4.3.3.2 | If in the opinion of the Contractor, the provisions of any document forming part of the Contract are at variance with any Applicable Laws or Standards, the Contractor shall give written notice to LGL specifying the departure from such provisions which it considers necessary to comply with Applicable Laws and applying for instructions thereon. | |
4.3.3.3 | When requesting the Certificate of Practical Completion or upon demand in writing made by LGL, the Contractor shall surrender to LGL all documents in its possession evidencing any approval required under Applicable Laws. | |
4.3.3.4 | Where particular Standards are referred to in the Contract, the latest edition or supplement thereto in effect at the time of Invitation to Tender shall be the issue, unless a specific edition is referred to, which establishes the Contractor’s Original Scope of Work. The Contractor shall, however, be responsible for ensuring that all Work complies with any subsequent revised or replacement Standards. | |
4.3.4 | Control of Contractor’s Employees and the Employees of Subcontractors | |
4.3.4.1 | The Contractor shall employ and ensure that its Subcontractors employ, in connection with the Work, only such persons as are responsible, careful, skilled and experienced in their respective trades and jobs. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 14 |
4.3.4.2 | LGL may object to and direct the Contractor to immediately remove or have removed from the Site or from any activity connected with the Work within such time as LGL directs, any person employed by the Contractor or by any Subcontractor to it, who refuses to comply with any requirement of the Contract, engages in misconduct or is incompetent or negligent in the performance of duties. The Contractor shall comply with such direction and any such person shall not be employed on the Site or on activities connected with the Work. The Contractor shall pay the cost of removing and replacing any such person. A direction issued pursuant to this Clause shall not be the subject of dispute or otherwise contested by the Contractor. | |
4.3.4.3 | The Contractor shall, at all times, be responsible and liable for the actions of its employees and the employees of its Subcontractors and shall be responsible for the payment of any claims for damage or compensation as a consequence of the actions of such employees. In the event of the Contractors failure to pay such claims, LGL may, on behalf of the Contractor, pay such claims and recover the amount thereof as a debt due from the Contractor to LGL. | |
4.3.5 | Industrial Relations | |
4.3.5.1 | The Contractor shall be responsible for maintaining good industrial relations with its own employees while at the same time refraining from any action which could affect LGL and other contractors, subcontractors and tradespeople engaged on the Total Project. | |
4.3.5.2 | The Contractor shall pay such wage rates, and observe and meet such terms and conditions of employment as shall apply by virtue of any Award, Collective or Industrial Agreement or Applicable Laws. | |
4.3.5.3 | The Contractor shall immediately report to LGL any industrial dispute which has arisen or which may, in the opinion of the Contractor,.arise. If a dispute is developing with any of the Contractor’s employees or the employees of any of its Subcontractors or Suppliers, the Contractor shall consult with and pay regard to advice given by LGL, however, the Contractor shall have no claim against LGL as a consequence of any advice so given. | |
4.3.5.4 | The Contractor shall provide all facilities not provided by LGL which are necessary to comply with any Award, Collective or Industrial Agreement or Applicable Laws and shall keep these facilities serviced and in excellent condition. | |
4.3.5.5 | To the extent permitted by law, the following provisions shall apply. Neither the Contractor nor its Subcontractors or Suppliers shall enter into any agreement whatsoever with their employees to pay, provide or do anything not required by any Award, Collective or Industrial Agreement or Applicable Laws, without prior consultation and written approval of LGL. The Contractor shall not do anything to induce the employee of another contractor, subcontractor or LGL to leave his or her present employer. In the event that any such employee applies for an advertised position with the Contractor and is subsequently employed by the Contractor, such employee shall not be engaged upon the Work for a period of six (6) months from the date of their employment by the Contractor, unless otherwise approved in writing by LGL. | |
4.3.6 | Occupational Health and Safety | |
4.3.6.1 | LGL places and requires the Contractor to place the highest importance and priority on occupational health and safety during the performance of the Work. The Contractor shall be responsible for ensuring that all the Work is executed in a safe manner and that adequate safe working practices are at all times adopted to ensure that a safe and healthy work environment is maintained. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 15 |
4.3.6.2 | Notwithstanding that the Contractor is required to comply with all Applicable Laws, the Contractor shall, in addition, comply with any LGL occupational health and safety policy, Mine safety requirements or other document as set out in Section 6 (LGL Safety Requirements). Should there be any difference between the requirements of Applicable Laws and the LGL Safety Requirements, the highest requirement shall be adopted. | |
4.3.6.3 | LGL will conduct induction courses for all personnel commencing work on Site. The Contractor shall ensure that all its employees and those of its Subcontractors attend the induction course prior to commencing work on Site. The cost incurred by the Contractor due to the attendance of its employees shall be borne by the Contractor. LGL shall not charge for conducting the courses. | |
4.3.6.4 | Without limiting the extent of the Contractor’s responsibility and liability for occupational health and safety, the Contractor shall: |
a) | Before commencing any of the Work on the Site, publish at all work areas, rest areas and accommodation facilities all occupational health and safety regulations and LGL Safety Requirements; | ||
b) | Establish, publish and distribute to all its employees its own occupational health and safety manual incorporating Applicable Laws, LGL Safety Requirements, policies and procedures, construction methods and incentive programs to encourage occupational health and safety; | ||
c) | Ensure that its employees and the employees of its Subcontractors, before they begin and throughout their employment, are made aware of all occupational health and safety requirements and are notified that compliance therewith is a condition of their continued employment; | ||
d) | Give adequate instructions on a regular basis to all its employees and the employees of its Subcontractors, in accident prevention and safe working practices; | ||
e) | Provide all safety devices, equipment and apparel as are necessary to prevent accidents, injuries and fires, which devices and equipment shall include adequate life protection equipment, machinery guards, fire extinguishers, walkways, ladders, scaffolds and gang planks; | ||
f) | Provide adequate facilities for safe and protected means of entrance and exit to the Work and for the proper inspection and maintenance of all safety devices, equipment and apparel; and | ||
g) | Continuously inspect all Work, materials and Constructional Plant to discover and determine any conditions involving a risk of bodily harm to persons or a risk of damage to property and be solely responsible for discovery, determination and correction of any such conditions. |
4.3.6.5 | The Contractor shall, prior to commencing the Work, submit a written occupational health and safety program for the Work for LGL’s review and approval. Such review and approval shall not relieve the Contractor of its responsibility for occupational health and safety or its obligations to undertake any action that may be necessary or required to establish and maintain healthy and safe working conditions on the Site. | |
4.3.6.6 | The Contractor shall coordinate its occupational health and safety procedures with LGL and all other contractors and subcontractors on Site. In recognition of the Contractor’s and LGL’s commitment to improving occupational health and safety without financial restraints, the Contractor unconditionally agrees to work with LGL and accept and carry |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 16 |
out any direction of LGL relating to occupational health and safety without making any Claim. | ||
4.3.6.7 | The Contractor shall, at all times, have one of its employees on Site responsible for occupational health and safety who shall be nominated by the Contractor as its ‘Safety Officer’. The Contractor shall advise LGL in writing of the nominated Safety Officer and of any designate thereof during absence from the Site of the nominated Safety Officer. | |
4.3.6.8 | The Contractor shall immediately report any accident or other occupational health and safety incident to LGL’s senior safety officer on Site and shall, within forty-eight (48) hours thereof, submit an accident/incident report in the form of Appendix 5/P. | |
4.3.6.9 | In the event that any situation of whatsoever nature arises which could present a risk to the occupational health and safety of a worker, LGL shall have the absolute right to suspend the Work or any part thereof pursuant to Clause 4.2.5 at no cost to LGL, until the situation has been rectified. | |
4.3.6.10 | The Contractor covenants, represents and warrants to LGL that: |
i) | The Contractor is familiar with Applicable Laws relating to occupational health and safety, and that the Contractor’s activities will be conducted in compliance with all such Applicable Laws, so as not to give rise to any breach thereof or any non-compliance therewith by LGL or any of its directors, officers, employees, agents, consultants or related corporations; | ||
ii) | All employees of the Contractor have been properly trained with respect to occupational health and safety concerns associated with the Contractor’s activities, and methods and systems for ensuring worker safety; | ||
iii) | The Contractor will exercise due diligence in ensuring the protection and safety of workers and without limitation, the Contractor shall implement such systems and procedures, and provide all such equipment and facilities, necessary so as to ensure worker protection and safety; | ||
iv) | The Contractor shall be fully responsible for acts or omissions of any Subcontractors and shall ensure that any Subcontractor complies with the provisions of this Clause 4.3.6 and any other provision of the Contract which relates to occupational health and safety matters as if such Subcontractor was the Contractor hereunder; |
4.3.7 | Protection of Persons, Property and Existing Services | |
4.3.7.1 | The Contractor shall provide, erect and maintain all barricades, guards, fencing, temporary roadways, footpaths, bridges to excavations, signs and lighting and provide and maintain all watching and traffic flagging required by Applicable Laws or necessary for the protection of any person or property and shall remove the same when no longer required. | |
4.3.7.2 | The Contractor shall avoid obstruction or damage to roadways, footpaths, drains, watercourses, public utility and other services on or adjacent to the Site, which are visible or the location of which can be ascertained by the Contractor from the appropriate authority or from LGL. The Contractor shall have any obstruction or damage, which it causes, rectified immediately at its own cost. In the event that the Contractor fails to have such rectification carried out, LGL may arrange for such rectification on behalf of the Contractor and recover the costs as a debt due from the Contractor to LGL. | |
4.3.7.3 | The Contractor shall avoid interference with or damage to property on or adjacent to the Site and shall provide temporary protection for and shall pay the cost of any repair and |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 17 |
reinstatement of all damage caused by the Contractor, its employees, agents or Subcontractors or the employees of any such agents or Subcontractors, either directly or indirectly. In the event of the Contractor’s failure to pay such costs, LGL may make payment on behalf of the Contractor and recover the costs as a debt due from the Contractor to LGL. | ||
4.3.7.4 | The Contractor shall prevent nuisance to and minimise the impact of its activities on the owners, tenants or occupiers of properties adjacent to the Site and to the public. | |
4.3.7.5 | Should it be necessary for the execution of the Work or any Temporary Works, to alter, shutdown or otherwise affect any existing service, the Contractor shall advise the Engineering Manager of same forty-eight (48) hours prior to such alteration, shutdown or affect and shall co-ordinate same with the Engineering Manager to minimise the effect thereof. | |
4.3.8 | Care of the Work | |
4.3.8.1 | From the commencement of the Contract to the expiration of the Defects Liability Period the Contractor shall be solely liable for the care of the Work, the Temporary Works and all materials, Constructional Plant and other things that are brought on to the Site by or on behalf of the Contractor or any of its Subcontractors for the purpose of carrying out the Work or that are entrusted to it by LGL. | |
4.3.8.2 | The Contractor shall at its own cost make good to the satisfaction of LGL any loss of or damage to the Work, the Temporary Works, materials, Constructional Plant and other things resulting from any cause whatsoever (save and except the Excepted Risks as defined in Clause 4.3.8.3) when such making good is necessary for the satisfactory completion of the Work. When so ordered by LGL any such loss or damage caused by any of the Excepted Risks shall be made good by the Contractor as a Variation to the Contract. | |
4.3.8.3 | The Excepted Risks are: |
i) | Any negligent act or omission of LGL or the employees, consultants or agents of LGL; | ||
ii) | Any risk specifically excepted in the Contract; | ||
iii) | War, invasion, act of foreign enemies, hostilities (whether war be declared or not), civil war, rebellion, revolution, insurrection or military or usurped power, martial law or confiscation by order of any Government or public authority. |
4.3.9 | Cleaning Up | |
4.3.9.1 | The Contractor shall keep the Work clean and tidy as it proceeds and regularly remove from the Site rubbish and surplus material arising from the execution of the Work. | |
4.3.9.2 | Within fourteen (14) days of the issue of the Certificate of Practical Completion, the Contractor shall remove all buildings, workshops, Temporary Works and Construction Plant which it may have constructed or brought on the Site for carrying out the Work. | |
4.3.9.3 | If the Contractor fails to comply with any obligation imposed on it by this Clause, LGL may, without prejudice to any other rights or remedies, after giving notice in writing to the Contractor, carry out the work of cleaning and tidying up and remove all buildings, workshops, Temporary Works and Construction Plant to a point of storage and the costs |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 18 |
incurred by LGL in carrying out such work and providing such storage may be recovered by LGL as a debt due to LGL by the Contractor. | ||
4.3.10 | Environmental Responsibilities | |
4.3.10.1 | LGL places and requires the Contractor to place the highest importance and priority on environmental protection during the performance of the Work. The Contractor shall be responsible for ensuring that the Work is executed in an environmentally responsible manner and that adequate practices are at all times adopted to ensure that LGL’s environmental responsibilities are met with respect to carrying out the Work. | |
4.3.10.2 | The Contractor shall ensure that its employees on Site are familiar with Applicable Laws relating to protection of the environment and shall ensure that all its employees and the employees of its Subcontractors comply with all such Applicable Laws. | |
4.3.10.3 | The Contractor shall immediately report any environmental accident or incident to LGL’s senior safety officer on Site and shall, within forty-eight (48) hours thereof, submit an environmental accident/incident report in the form of Appendix 5/P. | |
4.3.10.4 | In the event that any situation of whatsoever nature arises which could present a risk to the environment, LGL shall have the absolute right to suspend Work pursuant to Clause 4.2.5 at no cost to LGL, until the situation has been rectified. | |
4.3.10.5 | The Contractor covenants, represents and warrants to LGL that: |
i) | The Contractor is familiar with Applicable Laws relating to environmental protection, and that the Contractor’s activities will be conducted in compliance with all such Applicable Laws, so as not to give rise to any breach thereof or any non-compliance therewith by LGL or any of its directors, officers, employees, agents, consultants or related corporations; | ||
ii) | All employees of the Contractor have been properly trained with respect to environmental concerns associated with the Contractor’s activities, and methods and systems for ensuring environmental protection; | ||
iii) | The Contractor will exercise due diligence in ensuring environmental protection and, without limitation, the Contractor shall implement such systems and procedures, and provide all such equipment and facilities, necessary so as to ensure environmental protection; and | ||
iv) | The Contractor shall be fully responsible for acts or omissions of any Subcontractors and shall ensure that each Subcontractor complies with the provisions of this Clause 4.3.10 and any other provision of the Contract which relates to environmental protection as if such Subcontractor was the Contractor hereunder. |
4.3.11 | General Contractor Warranties | |
4.3.11.1 | The Contractor covenants, represents and warrants to LGL that: |
i) | The Contractor has and will continue (for as long as it has any obligation or liability under this Contract) to have the requisite power and authority to enter into and perform its obligations and discharge its liabilities under this Contract; | ||
ii) | The Contractor has taken all necessary action to authorise the execution, delivery and performance by it of this Contract; |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 19 |
iii) | this Contract and the obligations created by it are binding obligations; | ||
iv) | all consents necessary to be obtained by it in relation to the execution, delivery, performance, validity and enforceability of this Contract have been obtained or effected and are in full force and effect; and | ||
v) | it will, and it will ensure that its employees, contractors and agents will, at all times: |
(A) | be suitably qualified and experienced; | ||
(B) | be appropriately licensed and authorised in accordance with Applicable Laws; and | ||
(C) | obtain all necessary approvals and required government consents; | ||
to perform the Work. |
4.4 | LIABILITIES | |
4.4.1 | Defects | |
4.4.1.1 | The Contractor shall, in addition to any liability which may exist under any Applicable Laws, be liable for the rectification of all omissions and defects in the Work listed on the Certificate of Practical Completion or becoming apparent during a Defects Liability Period of twelve (12) months which shall commence on the Date of Practical Completion. Such rectification shall include the making good, repair or replacement of any other works or property affected by the defect or rectification works. | |
4.4.1.2 | The Contractor shall rectify any minor omissions and minor defects listed on the Certificate of Practical Completion within fourteen (14) days of the issue of the Certificate of Practical Completion. | |
4.4.1.3 | Any omissions and defects which become apparent during the Defects Liability Period and which are due to any cause, including design, workmanship or materials for which the Contractor is responsible shall be rectified by the Contractor when directed to do so by LGL. At its discretion, LGL shall state the omissions or defects or in what respect the Work is otherwise defective, the making good, repair or replacement of any other works or property required and the date by which rectification shall be commenced and completed, but no such direction shall be given by LGL later than twenty-eight (28) days after the expiration of the Defects Liability Period. | |
4.4.1.4 | If any rectification referred to in Clauses 4.4.1.2 or 4.4.1.3 is not commenced or completed within the time stipulated, LGL may carry out the rectification at the Contractor’s expense but without prejudice to any other rights that LGL may have against the Contractor in respect of the rectification. The cost incurred by LGL in so carrying out the rectification shall be a debt due from the Contractor to LGL. Notwithstanding the provisions of this Clause, the Contractor shall not be responsible for the effects of fair wear and tear during the Defects Liability Period. | |
4.4.1.5 | If it becomes necessary for the Contractor to carry out any rectification, the provisions of this Contract relating to the Work shall apply to the rectification as if it were the Work and the Defects Liability Period for that part of the Work on which the rectification was executed shall commence on the day on which the rectification work is completed. LGL may approve a shorter Defects Liability Period in respect of any rectified work. | |
4.4.1.6 | For the purposes of carrying out any rectification or making tests or inspecting the working records of the Work and taking notes there from, and subject to the approval and requirements of LGL, the Contractor shall have the right of entry in so far as it may be |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 20 |
necessary for all or any of those purposes, at its own risk and cost and at all reasonable times, to the Site and the Work. | ||
4.4.1.7 | Any action taken by the Contractor for any of the purposes expressed in this Clause shall not disrupt or inconvenience the normal activities of the Mine. | |
4.4.2 | Royalties, Patents, Copyrights and Other Intellectual Property Rights | |
4.4.2.1 | Unless otherwise provided for in the Contract, all payments (whether or not accrued, due and payable at the date of the Contract) for royalties and patent rights, registered designs, trade marks or names, copyright and other protected rights and all fees then or thereafter to become payable for or in connection with any land (excluding mineral royalties), matter or thing used or required to be used in performance of the Contract or to be supplied under the Contract shall be included by the Contractor in the Contract sum and shall be paid by it to those to whom and at the time at which they become payable. | |
4.4.2.2 | The Contractor shall indemnify LGL and its directors, officers, employees, agents and consultants against any action, suit, proceeding, claim or demand, in respect of all costs or expenses arising from, or incurred by reason of, any infringement or alleged infringement of letters patent, registered design, trade xxxx or name, copyright or other protected rights, in respect of any machine, equipment, work, material or thing, system or method of using, fixing of or working, or any arrangement used or fixed or supplied by the Contractor for the purposes of the Contract. | |
4.4.2.3 | Title to, copyright in and other intellectual property rights in any documents, plans, specifications, designs, drawings, sketches, reports and materials produced for or in connection with the Works vests in LGL on creation and LGL grants to the Contractor an irrevocable royalty free, non-exclusive licence to use that material in connection with the supply of the Works. | |
4.4.3 | Accident or Injury to Employees | |
4.4.3.1 | The Contractor indemnifies LGL and its directors, officers, employees, agents and consultants, against liability for all loss or damage resulting from personal injury to or the death of (reduced to the extent of any contribution by LGL or its directors, officers, employees, agents and consultants) the Contractor or of any Subcontractor or any employee or agent of the Contractor or of any Subcontractor occurring during the currency of the Contract and arising out of or in connection with the execution of the Work under claims, demands, actions, suits or proceedings, including costs and expenses under Applicable Laws. | |
4.4.4 | Property Damage and Public Risk | |
4.4.4.1 | Subject to Clause 4.4.4.2, the Contractor indemnifies LGL and its directors, officers, employees, agents and consultants against all loss of or damage to property of LGL and its directors, officers, employees, agents and consultants, or any of them, and from and against any claim, demand, action, suit or proceeding that may be made or brought by any person against LGL and its directors, officers, employees, agents and consultants, or any of them, in respect of personal injury to or the death of any person or loss of or damage to any property arising out of or as a consequence of the construction or maintenance of the Work by the Contractor or its Subcontractors and also from any costs and expense that may be incurred in connection with any such claim, demand, action, suit or proceeding. | |
4.4.4.2 | The Contractor shall not, under Clause 4.4.4.1, be rendered liable for or in respect of loss of or damage to property or personal injury to or death of any person resulting from any breach by LGL of any provision of the Contract or any negligent act or omission of LGL |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 21 |
or for or in respect of any claims, demands, actions, suits or proceedings, costs and expenses whatsoever in respect thereof or in relation thereto. | ||
4.4.5 | Taxes and Contributions | |
4.4.5.1 | The Contractor shall be solely responsible for and indemnifies LGL against claims or liability for the payment of all corporate taxes, statutory levies, payroll taxes and fringe benefit taxes related to or arising from performance of the Work. Further, the Contractor shall make all contributions to pension funds that may be required to be made on behalf of its employees or agents under any Applicable Laws, or any Award, or Collective or Industrial Agreement to which they are subject, and indemnifies LGL and its directors, officers, employees, agents and consultants against liability for all loss including claims, demands, actions, suits and proceedings, and the costs and expenses relating thereto, arising as a result of its failure to do so. | |
4.4.5.2 | The Contractor indemnifies LGL and its directors, officers, employees, agents and consultants against liability for all loss including claims, demands, actions, suits and proceedings, and the costs and expenses relating thereto arising out of or caused by failure of the Subcontractor to fully and properly comply with these requirements. | |
4.4.5.3 | Liability for Tax | |
In this clause: | ||
“Tax” means any tax, levy, royalty, rate, duty, fee, impost, or other charge imposed by any governmental, semi-governmental, or other body authorised by law whether in PNG, Australia or elsewhere to impose such Tax. Without limiting the generality of the foregoing, Tax includes any withholding tax (including foreign Contractor withholding tax), goods and services tax, value added tax, petroleum resource rent tax, any tax respecting environmental effects including a carbon tax. | ||
“Income Tax” means any tax of general application imposed on net income. | ||
4.4.5.3 | (a) The Contractor shall reimburse LGL for the amount of LGL’s liability for any Tax (excluding Income Tax) in respect of any supply made by the Contractor under this Contract. | |
4.4.5.3 | (b) Any consideration to be paid or provided for a supply made under or in connection with this Contract is expressed inclusive of all Tax, other than GST, in force at the Commencement Date. | |
4.4.5.3 | (c) Should LGL be required to withhold any amounts on account of any Tax (excluding income Tax), the corresponding withheld amount will be taken as a reduction in the consideration to be paid or provided. | |
4.4.5.4 | GST | |
4.4.5.4 | In this clause: | |
“Australian GST Law” has the meaning given to the term “GST Law” by the A New Tax System (Goods and Services Tax) Xxx 0000 (Cth); | ||
“Consideration” has the meaning given by the Australian GST Law or the PNG GST Law; | ||
“Goods” has the meaning given to that term by the Australian GST Law or the PNG GST Law, as applicable; |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 22 |
“PNG GST Law” means the Goods and Services Tax Xxx 0000 (PNG); | ||
“Recipient” has the meaning given to that term by the Australian GST Law or the PNG GST Law, as applicable; | ||
“Tax Invoice” has the meaning given by the Australian GST Law or the PNG GST Law, as applicable; and | ||
“Taxable Supply” means a taxable supply as that term is defined in the Australian GST Law (excluding the reference to section 84-5 of the A New Tax System (Goods and Services Xxx 0000 (Cth)) or a supply upon which goods and services tax is imposed by the PNG GST Law, as applicable. | ||
4.4.5.4 | (a) Any consideration to be paid or provided for a supply made under or in connection with this Contract, unless specifically described in this Contract as “GST inclusive”, does not include an amount on account of GST. LGL is zero rated for GST for supplies made in PNG. | |
4.4.5.4 | (b) The Contractor will make all reasonable endeavours to ensure the supply of any Goods is GST-free under Australian GST Law. In this regard and where applicable to supply of equipment with the Works, the Contractor warrants that it will export any Goods within 60 days of the earlier of receiving any consideration for the supply or issuing an invoice for the supply and that it will hold sufficient documentary evidence to substantiate the export of the Goods within the 60 day timeframe. | |
4.4.5.4 | (c) Despite any other provision in this Contract, if a party (“Supplier”) makes a supply under or in connection with this Contract on which GST is imposed to any extent (not being a supply the consideration for which is specifically described in this Contract as “GST inclusive”): |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 23 |
4.4.5.5 | Reimbursements | |
4.4.5.5 | (a) If a payment to a party under this Contract is a reimbursement or indemnification, calculated by reference to a loss, cost or expense incurred by that party, then the payment must be reduced by the amount of any input tax credit to which that party is entitled for that loss, cost or expense. That party is assumed to be entitled to a full input tax credit unless it proves, before the date on which the payment must be made, that its entitlement is otherwise. | |
4.4.5.6 | Adjustment Events | |
4.4.5.6 | (b) If, at any time, an adjustment event arises in respect of any supply made by a party under this Contract, a corresponding adjustment must be made between the parties. Payments to give effect to the adjustment must be made between the parties and the Supplier must issue a valid adjustment note in relation to the adjustment event. | |
4.4.5.7 | No Merger | |
4.4.5.7 | (a) This clause does not merge on completion or termination of this Contract. | |
4.4.6 | Survival of Indemnities | |
4.4.6.1 | All indemnities provided for under the Contract shall survive termination of the Contract. | |
4.5 | LEGALITIES | |
4.5.1 | Construction of the Contract | |
4.5.1.1 | The Contract shall be governed by and construed with reference to the laws for the time being in force in the jurisdiction stated in Clause 1.8.(Total Project Data) | |
4.5.1.2 | All prices and sums of money and all payments made under the Contract shall be in the currency stated in Clause 1.8 (Total Project Data) and payments shall be made at the place named therein. | |
4.5.1.3 | All measurements of physical quantities shall be in the units stated in Clause 1.8 (Total Project Data). | |
4.5.1.4 | If any provision of the Contract shall be determined to be void, illegal or unenforceable by a court of competent jurisdiction, such provision shall be separable and struck from the Contract and the validity and enforceability of the remaining provisions of the Contract shall not be effected thereby. | |
4.5.1.5 | LGL may, at any time, deduct from any amount due or becoming due to the Contractor under this Contract all debts and amounts due from the Contractor to LGL whether under or in connection with this Contract or otherwise. | |
4.5.2 | Evidence of the Contract |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 24 |
4.5.2.1 | Until the Formal Instrument of Agreement referred to in Clause 4.5.2.2 is executed by the parties, the agreement in writing between the Contractor and LGL for the execution of the Work, including the documents or the parts of the documents to which reference may properly be made in order to ascertain the rights and obligations of the parties in relation to the Work, shall constitute the Contract between them. | |
4.5.2.2 | As soon as practicable after the Date of Acceptance of Tender, LGL shall prepare, in duplicate, a Formal Instrument of Agreement incorporating all Contract Documents. | |
4.5.2.3 | Within fourteen (14) days after being requested in writing by LGL so to do, the Contractor shall execute both copies of the Formal Instrument of Agreement at the place and in the manner directed in writing by LGL and shall return both copies to LGL duly executed. | |
4.5.2.4 | On receipt from the Contractor of the two copies of the Formal Instrument of Agreement duly executed by the Contractor, LGL shall, as soon as practicable, execute both copies of the Formal Instrument of Agreement and shall forward one of such copies to the Contractor. | |
4.5.2.5 | If the Contractor fails to duly execute the Formal Instrument of Agreement within the time and in the form prescribed herein, LGL shall be entitled to treat such failure as a default under Clause 4.5.4 (Default or Insolvency). | |
4.5.2.6 | The Formal Instrument of Agreement shall be in a form similar to that set out in Appendix 5/Q. | |
4.5.3 | Documents | |
4.5.3.1 | The documents, which constitute or evidence the Contract, shall be taken as mutually explanatory and, subject to any clauses providing for order of precedence in case of inconsistencies, anything contained in one but not in another shall be equally binding as if contained in all. The Engineering Manager shall explain any ambiguity, discrepancy or inconsistency, which is identified and is not covered by a clause providing for order of precedence in case of inconsistencies. If the Contractor finds any such ambiguity, discrepancy or inconsistency it shall immediately refer it in writing to the Engineering Manager. | |
4.5.3.2 | Minor items not expressly mentioned in the Contract but which are necessary for the satisfactory completion of the Work shall be supplied and executed by the Contractor without adjustment to the Contract Sum. | |
4.5.3.3 | The Contractor shall make allowance for slight variations in dimensions shown on drawings which may be caused by unavoidable inequalities in the sizes of materials. | |
4.5.3.4 | Drawings made to larger scales and those showing details of particular parts of the Work shall be taken as correct in preference to those made to smaller scales and for more general purposes. Where any discrepancy exists between figured and scaled dimensions, the figured dimensions shall prevail. | |
4.5.3.5 | LGL shall supply to the Contractor free-of-charge, all reasonable quantities of drawings or other written information as are necessary for the purposes of execution of the Work. If the Contractor shall require additional drawings or other written information, then the Contractor shall make such requests in writing. All such additional drawings or other written information supplied to the Contractor shall be deemed to be part of the Contract Documents. All documents supplied to the Contractor under this clause or otherwise shall be returned to LGL on demand in writing and shall not be used by the Contractor for any purpose other than execution of the Work. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 25 |
4.5.3.6 | The Contractor shall supply to LGL free-of-charge, at least three (3) copies of such drawings or other written information as it is required by this Contract to supply. If the Engineering Manager considers that such drawings or other written information are suitable for use, the Contractor shall be given permission to use them accordingly and one copy shall be returned to it. Notwithstanding the grant of permission to use any such drawings or other written information, the Contractor shall be bound to carry out and complete the Work strictly in accordance with the Contract. Permission for the use of any such drawings or other written information shall not relieve the Contractor from the full responsibility for the correctness of such drawings or other written information except in so far as any error in or omission from any such drawings or other written information has been caused by an error in or omission from any document which LGL has issued or caused to be issued. | |
4.5.3.7 | During the execution of the Work, the Contractor shall keep and maintain on Site, two (2) complete sets of drawings in print form progressively marked up to show all as constructed detail to the satisfaction of LGL. On completion of appropriate stages of the Work as determined from time to time by the Engineering Manager, one (1) set of drawings shall be handed to LGL. As a requirement of Practical Completion, the Contractor shall prepare and provide to LGL one (1) full set of as constructed drawings in electronic and hard copy format. | |
4.5.4 | Default or Insolvency | |
4.5.4.1 | If the Contractor defaults in the performance of its obligations under the Contract or refuses or neglects to comply with any direction given in writing in accordance with the Contract, LGL may issue to the Contractor a Show Cause Notice, in a similar form to Appendix 5/R, requiring the Contractor to show cause in writing why the powers hereinafter contained should not be exercised. Such notice shall specify the period (which shall not be less than three (3) days after service of notice) by which the Contractor is required to show cause as aforesaid. If the Contractor fails to show cause to the satisfaction of the Engineering Manager, why the powers hereinafter contained should not be exercised, LGL, without prejudice to any other rights or remedies that it may have against the Contractor, by notice in writing may: |
i) | Take any part of the Work remaining to be completed wholly or partly out of the hands of the Contractor or of any person in whose hands or possession the Work or any part of it may be; or | ||
ii) | terminate the Contract. |
4.5.4.2 | If LGL elects to exercise the power conferred on it by Clause 4.5.4.1, it may: |
i) | Suspend progress payments; | ||
ii) | Complete any part of the Work remaining to be completed and for that purpose may let a contract, or may employ persons to carry out the completion of the Work; | ||
iii) | Take possession of, use, and permit other persons to use any materials, Constructional Plant, and other things, which are owned by the Contractor and are requisite and necessary for the purpose of completing the Work. The Contractor shall have no right to any compensation or allowance in respect thereof, other than the right to require LGL to ensure the maintenance in good working order of the Contractor’s Constructional Plant during the use thereof; and/or |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 26 |
iv) | Require the Contractor to assign, within three (3) days, to LGL without payment, the benefit of any agreement for the supply of materials or for the execution of any part of the Work. |
4.5.4.3 | On completion of the Work, LGL shall determine the cost of the Work comprising payments to the Contractor and costs incurred by LGL in carrying out the completion of the Work. If the costs so determined are greater than the amount which would have been paid to the Contractor if the whole of the Work had been carried out by it, the Contractor shall pay LGL the difference between the two amounts and such sum shall be a debt due from the Contractor to LGL. Should the costs so determined be less than the amount which would have been paid to the Contractor, LGL shall pay to the Contractor whichever is the lesser amount of either the balance of the Contract value of that part of the Work actually executed by the Contractor but not paid or the amount by which the costs are determined to be less. | |
4.5.4.4 | No action taken by LGL under this clause shall vitiate the Contract or operate to the prejudice of any other rights or remedies of LGL at law or in equity. | |
4.5.4.5 | If the Contractor: |
i) | being a person, commits an act of bankruptcy or presents against himself or herself or has presented against him or her a petition in bankruptcy or a sequestration order is made against him or her or he or she enters into any scheme of arrangement or any composition with his or her creditors or executes as a debtor a deed of arrangement or a deed of assignment; or | ||
ii) | being a company, takes or has taken or instituted against it any action or proceeding whether voluntary or compulsory which has as an object or may result in the winding up of the company, other than a voluntary winding up by members for the purpose of reconstruction or amalgamation, or is placed under official management or enters into a compromise or other arrangement with its creditors or a controller is appointed or a receiver or receiver and manager is appointed to carry on its business for the benefit of its creditors or any of them | ||
iii) | breaches a safety requirement or direction from LGL in relation to safety which is of a nature significant enough to justify termination |
LGL may, by notice in writing, proceed as per Clause 4.5.4.1 (i) or (ii) above but without the requirement to issue a Show Cause Notice as detailed therein. | ||
4.5.4.6 | All remedies for any breach of, or default under, the Contract are cumulative and not exclusive, and a party may pursue and enforce any and all remedies available at law, in equity or under the Contract concurrently, consecutively or alternatively, unless the contrary is stated expressly in the Contract. | |
4.5.5 | LGL’s Right to Terminate the Contract | |
4.5.5.1 | LGL may, at its option, at any time and for any reason it may deem advisable, terminate the Contract, in which event the Contractor shall, having regard to any progress payments already made and any debts due from the Contractor to LGL, be entitled to receive payment and compensation as follows: |
i) | FOR LUMP SUM ITEMS: The Engineering Manager shall determine the percentage completion of such items up to the time of the termination of the |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 27 |
Contract and the Contractor shall be paid the percentage so determined of the value of the Lump Sum items. | |||
ii) | FOR UNIT PRICE ITEMS: The Engineering Manager shall determine the number of items completed up to the time of the termination of the Contract and the Contractor shall be paid for the number of items so determined at the unit prices listed in the Contract. | ||
iii) | DEMOBILIZATION: The Contractor shall be paid such an amount as in the opinion of the Engineering Manager will adequately compensate the Contractor for moving its employees, equipment, tools, supplies and materials off the Site. | ||
iv) | ADDITIONAL COMPENSATION: The Contractor shall be paid an additional amount to compensate the Contractor for any inconvenience, loss or damage incurred by it due to the termination of the Contract. Such compensation shall be determined by the Engineering Manager but shall amount to not more than of the Contract value of Work which the Contractor executed in the period of sixty (60) Days prior to the date of the notice of termination of the Contract. |
4.5.5.2 | It is specifically agreed that the amounts determined pursuant to Clause 4.5.5.1 shall be the Contractor’s total entitlement for the consequences of any such termination. | |
4.5.6 | Disputes | |
4.5.6.1 | In case any dispute or difference shall arise between LGL and the Contractor, either during the progress of the Work or after termination, repudiation or breach of the Contract, as to the construction of the Contract or as to any matter or thing whatsoever arising thereunder or in connection therewith, then the aggrieved party shall give to the other notice in writing setting out in full the detailed particulars of the dispute or difference. Upon receipt or issue of the notice, LGL shall give written notice to the Contractor appointing a date, time and venue for a conciliation meeting to be held to discuss in detail the dispute or difference and may appoint such further time as may be necessary for the continuation thereof. The parties shall not be legally represented at the conciliation meeting but shall present in their own manner, with the assistance of witnesses and documentary evidence, the details of their respective cases. | |
4.5.6.2 | If at the conclusion of the conciliation meeting the parties fail to resolve the dispute or difference, either party may give to the other within fourteen (14) days, a notice stating that at the expiration of thirty (30) days, it will proceed to have the dispute or difference referred to senior management representatives of both LGL and the Contractor who shall meet on a without prejudice basis to discuss the dispute and use their reasonable endeavours to resolve the dispute amicably and in the interests of both parties in reliance on this contract.. Each party is to meet its own costs of preparation and attendance at any dispute resolution process under clauses 4.5.6.1 or 4.5.6.2. | |
4.5.6.3 | If at the conclusion of the meeting between senior executives or the expiration of 60 days whichever is the earlier, the parties fail to resolve the dispute or difference, either party may give to the other within fourteen (14) days, a notice stating that at the expiration of thirty (30) days, it will proceed to have the dispute or difference referred to a court of competent jurisdiction in the jurisdiction stated in Clause 1.8 (Total Project Data) and at the expiration thereof, but not before, may so proceed. | |
4.5.7 | Service of Documents | |
4.5.7.1 | Any notice, communication or other document shall be deemed to have been given or served if delivered in person, in the case of LGL, to the Engineering Manager and in the case of the Contractor, to a person occupying one of the positions of authorization set out |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 28 |
in Tender Form Appendix 3/G, or if mailed by prepaid mail, in the case of LGL, to the address given for LGL in Clause 1.8 (Total Project Data) or in the case of the Contractor, to the address given for it in Tender Form Appendix 3/C (or at such substitute address as either party may, from time to time, direct in writing) or if sent by facsimile transmission, to the facsimile number at the party’s normal place of business. Any such notice shall be deemed to have been received, if delivered, or sent by facsimile, on the first business day following the date of delivery or transmission, and if mailed, on the tenth business day after the date of mailing. | ||
4.5.7.2 | Where any notice or other document requires an act or thing to be done or performed or allowed within the time or period specified in that notice or document, then the same shall be sent by certified or registered mail, served personally, or shall be sent by facsimile transmission. | |
4.5.8 | LGL Right to Audit | |
4.5.8.1 | LGL reserves at its discretion, the right to audit the Contractor’s books, records (including payroll and primary accounting records) and supporting documentation for any purpose, including the verification of any Claim made by the Contractor. | |
4.5.8.2 | In the event that LGL applies to the Contractor to exercise its right under Clause 4.5.8.1, the provision of access to such books, records and supporting documentation shall be a condition precedent to the Contractor’s right to receive any further payments, return or release of security or to commence or proceed in accordance with Clause 4.5.6 whether such proceedings have commenced or not. | |
4.5.9 | Definitions and Interpretations | |
4.5.9.1 | In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby assigned to them, except where the context otherwise requires: | |
“Actual Direct Costs” shall mean the actual monetary value paid by the Contractor as evidenced by both invoices and payment receipts or, with respect to depreciation, the actual percentage taken into account in the Contractor’s balance sheets. | ||
“Actual Onsite Overhead Costs” shall mean for any given period, the actual direct cost to the Contractor of its: |
• | Buildings on Site (based on cost of depreciation); | ||
• | Senior Site representative (providing such person is not directly engaged in physical construction of the Work); | ||
• | Clerical staff; | ||
• | Services costs (such as telephone, fax, power and water); | ||
• | Liability and Works Insurances, other than workers compensation; | ||
• | Office furnishings and equipment (based on cost of depreciation); and | ||
• | Office consumables at Site. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 29 |
i) | Where payment is to be made on a Lump Sum basis, the sum which is stated in the Contract to be payable to the Contractor for the execution of the Work by the Contractor and the performance of the obligations of the Contractor under the Contract. | ||
ii) | Where payment is to be made on a Schedule of Rates basis, the sum ascertained upon completion of the Work by calculating the products of the unit rates set out in the Schedule of Rates and the actual quantities of Work executed to complete the Original Scope of Work and adding to the sum thereof, the total of any amount properly payable for Work done in respect of Lump Sums, provisional sums, contingency sums, or other sums included in the Schedule of Rates for the Original Scope of Work. | ||
iii) | Where payment is to be made on a part Lump Sum and part Schedule of Rates basis, the aggregate of the sums referred to in paragraphs i) and ii). |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 30 |
i) | the Work is complete except for minor defects or omissions: |
• | which do not prevent the Work from being reasonably capable of being used for its intended purpose; | ||
• | in relation to which the Engineering Manager determines that the Contractor has reasonable grounds for not promptly rectifying them; and |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 31 |
• | rectification of which will not damage the convenient use of the Work, and |
ii) | those tests which are required by the Contract to be carried out and passed before the Work is handed over to LGL, have been carried out and passed; and | ||
iii) | such documents and other information required under the Contract which, in the opinion of the Engineering Manager, are essential for the use, operation and maintenance of the Work, have been supplied. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 32 |
“Tender Schedule” means the schedule submitted by the Contractor at time of Tender in accordance with the requirements of Clause 2.5.4 (j) | ||
“Total Project” means the project described in Clause 1.1.1. | ||
“Unit Rates” means rates of payment for identifiable units of Work | ||
“Variation” means a change in the Original Scope of Work and/or Contract Sum authorised by LGL by issue of a Contract Variation. | ||
“Work” or “Works” means all of the deliverable obligations of the Contractor pursuant to the Contract and includes all management, supervision, labour, and materials necessary to achieve those obligations. | ||
4.5.9.2 | The Clause headings and sub-clause headings in these General Conditions of Contract shall not be deemed to be part thereof and shall not be used in the interpretation or construction thereof or of the Contract. | |
4.5.9.3 | Words in the singular shall include the plural and words in the plural shall include the singular, according to the requirements of the context. | |
4.5.9.4 | Words importing the masculine gender shall include the feminine gender or the neuter gender, as the case may require. |
Volume 3A Issue 1 October 2006 version 3 | Section 4 Page No 33 |
5/A
|
Organization Chart Construction Management | |
5/B
|
Form of Unconditional Bank Guarantee | |
5/C
|
Site Instruction | |
5/D
|
Project Control System — Site Instruction Flow Chart | |
5/E
|
Draft Agenda for Weekly Coordination Meeting | |
5/F
|
Resources and Progress Report (3 Sheets) | |
5/G
|
Progress Claim (4 Sheets) | |
5/H
|
Quotation Price Request (2 Sheets) | |
5/1
|
Project Control System — Quotation Price Request Flow Chart | |
5/J
|
Contract Variation | |
5/K
|
Project Control System — Contract Variation Flow Chart | |
5/L
|
Dayworks Sheet (2 Sheets) | |
5/M
|
Certificate of Practical Completion | |
5/N
|
Final Certificate | |
5/O
|
Deed of Release | |
5/P
|
Accident/ Incident Report | |
5/Q
|
Formal Instrument of Agreement (2 Sheets) | |
5/R
|
Show Cause Notice |
(a) | notification has been received by the Surety from both the Obligee and Contractor that this | ||
(b) | until payment has been made to the Obligee by the Surety in accordance with the term hereof, of |
L — [Work Package No] — [Reference No
] |
Contractor:
Work Package:
|
Project:
Date:
|
Subject:
|
The Contractor is hereby advised: |
o | No cost Variation to the Contract | |
o | Issue with QPR No___ (work NOT to proceed until CV is issued) |
|
o | Issued with Dayworks Sheet No___ (work to proceed on Dayworks basis) |
|
Signed | Signed | |||||||
For & On Behalf Of LGL | For & On Behalf Of The Contractor | |||||||
Date:
|
Date: | |||||||
1.0 | Safety & Security |
1.1 | Review of safety reports and statistics. Review of ongoing safety action plans and incentive programs. |
2.0 | Progress Reports |
2.1 | Submission of Contractor’s Weekly Progress Report (Appendix 5/F Sheet 1 Of 3) | ||
2.2 | If status of Weekly Progress Report shows any item behind schedule, submission of alternative and revised schedules as per Clause 4.2.4 |
3.0 | Contract Schedule |
3.1 | Discussion and review of Contract Schedule |
4.1 | Submission and review of any outstanding QPR’s |
5.1 | Review of any technical problems |
6.1 | Review of any interface problems |
7.1 | Review of any problems with materials or logistics |
8.1 | Review of Quality Plans and Reports. Review action required on NCR’s |
9.1 | Review of existing and projected manpower. Review of accommodation requirements |
10.1 | |||
10.2 | |||
10.3 |
APPENDIX 5/F Sheet 1 Of 3 I Work Package: C — [Work Package No] — [Reference No] Date: I Contractor For Period Ending: MEASURED AGAINST EXISTING APPROVED CONSTRUCTION PROGRAMME No DATED Construction Programme Actual Progress Forecast Progress Ahead (+) MMy Description %Complete Start | Finish | ‘ Start | Finish ™ start Finish • Weighted % Complete = (% Value of Contract Sum) x (% Complete) Signed Signed Date (Contractor’s Site Representative) (Area Manager) |
APPENDIX 5/F Sheet 2 Of 3 Work Package: C — [Work Package No] - [Reference No] Contractor: Report For: Hours Worked & Classification Of Work name ID Total No Ori 9 inal Contract Davworks Hours Contract Variations c V No Payworks shee nq Totals 0 0 0 0 Signed Signed Contractor’s Site Representative) (Area Manager) Date: Date: |
APPENDIX 5/F Sheet 3 Of 3 Work Package: C — [Work Package No] - [Reference No] Contractor: Report For: Hours Worked & Classification Of Work Description Of ID Total Plant/Equipment No I Origi nal Contract Dayworks Dayworks Hours ___Contract Variations C V N0 Dayworks sheet No Signed Signed Contractor’s Site Representative) (Area Manager) Date: Date: |
APPENDIX 5/G SHEET 1 Of 4 C — [Work Package No] — [Progress Claim No] Work Package: Date: Contractor: For Period Endingj CUMULATIVE TOTAL OF CONTRACT WORK (As per attached details sheet 2 of 4) CUMULATIVE TOTAL OF CONTRACT VARIATIONS (As per attached details sheet 3 of 4) CUMULATIVE TOTAL OF DAYWORKS (As per attached details sheet 4 of 4) TOTAL VALUE OF PROGRESS CLAIM $0.00 THE CONTRACTOR HEREBY CERTIFIES THAT: 1 All employees, agents, consultants, Subcontractors and Suppliers have been paid all amounts properly due to them in 2 That it has notified LGL of all Claims and particulars thereof which it may have against LGL arising out of circumstances Signed Date: (For and on behalf of the Contractor) SCHEDULE OF ADJUSTMENTS TO CONTRACTORS PROGRESS CLAIM REASON FOR ADJUSTMENT I VALUE OF ADJUSTMENT Addition Deduction TOTAL ADJUSTMENTS NET ADJUSTMENT ACCEPTANCE OF ADJUSTMENTS BY THE CONTRACTOR: Signed Date: For and on behalf of the Contractor) APPROVAL BY ENGINEERING MANAGER TOTAL PROGRESS CLAIM VALUE APPROVED TOTAL PAYMENT VALUE CERTIFED LESS TOTAL PAYMENT VALUE PREVIOUSLY CERTIFIED LESS HOLD BACK OF 10% PAYMENT VALUE CERTIFIED FOR THIS PERIOD Signed Date: Engineering Manager) SCHEDULE OF DEBTS DUE FROM THE CONTRACTOR TO LGL Item Advice Reference Details Amount TOTAL DEBTS DUE TO BE DEDUCTED NET AMOUNT APPROVED GST 10% TOTAL VALUE THIS PAYMENT! |
APPENDIX 5/G Sheet 2 Of 4 Work Package: C — [Work Package No] - [Reference No] Page No Date: Contractor: For Period Ending: AIM AREA MANAGER’S AREA MANAGER & ENGINEERING MANAGER’S UUINIKAUUK5U-AIM ASSESSMENT CONTRACTORS REVIEW DETERMINATION Contract I %or Qty 10/A Unit Value %or Qty Adjustment Accept Or Reject c|aim Item Code Work Description Vag|ue Rate Cl a|med complete To Claim Value Comments No Addition Deduction A/R Commenls TOTAL VALUE CLAIMED OR CONTRACT WORKS $ 0 $0 Total Assessment £0 Total Determination Signed Signed Sjgned Signed Contractor’s Representative Area Manager Contractor’s Representative Engineering Manager |
APPENDIX 5/G Sheet 3 Of 4 Xxxx Package: C — [Work Package No] - [Reference No] Page No Date: Sontractor: For Period Ending: CONTRACTOT’S CLAIM AREA MANAGER’S ~~| AREA MANAGERS ENGINEERING MANAGERS CONTRACTORS CLAIM ASSESSMENT CONTRACTORS REVIEW DETERMINATION cv|totI Contract I %or Qty I 10/A I Unit Value %orQty I A d]ustment ~ Accept Or Reject No Code Work Description ^ ^ ^ C|ajmed J e ToC^ By Contractor value Comments ___^_^___^ Additon _Deduction A/R Comments _^^^___^_^^^^^^___TOT AL VALUE CLAIMbUhUU CON IRAQ I wUKK,y~ SO ‘ JO SO Total Assessment SO Total Determination Signed Signed Signed Signed Contractor’s Representative Area Manager Contractor’s Representative Engineering Manager |
APPENDIX 5/G Sheet 4 Of 4 Work Package: C — [Work Package No] - [Reference No] Page No Date: Contractor: For Period Ending: nAuar/iB^,.. .».™ nor^.,.. a rr,i^l • : -’” Onginals of Dayworks Sheets for period from last dam to b 9 attached hereto j™, ~’™~ ‘.—.-.—. | AREA MANAGER’S ] ENGINEERING MANAGER’S DAYWORKS CLAIMEO PREVIOUS PERIODS ^ DAYWORKS CLAIMED FOR THIS PERIOD™” ASSESSMENT DETERMINATION Date ., Amount Date Work Description Cost Code Amounl Amount Comments Amount Comments No No Sheet No •otai Previous periods $0 TOTAL AMOUNT CLAIMED FOR DAYWORKS THIS PERIOD $0,00 $Q.QQ Total Assessment $ 0.00 Total Determination TOTAL PERVIOUS PERIODS $ 0 $ Q (Area Manager) $q (Engineering Manager) TOTAL VALUE TO DATE: $Q,OQ $Q,og $0.0(1 Signed Signed Signed Signed Contractor’s Representative Area Manager Area Manager Engineering Manager |
APPENDIX 5/H Sheet 1 Of 2 L — [Work Package No] — Work Package: QPR No: Contractor: Date: You are hereby requested to provide a quotation for the following PRICE BREAKDOWN Item ___Description Unit Quantity Rate Amount TOTAL FIXED PRICE LUMP SUM QUOTATION — ~ If additional space is required, please use copies of sheet 2, and attach them to sheet 1 and bring forward the totals of each sheet 2 Signed ___Date (Contractor’s Representative) AGREED ADJUSTMENTS I Unit I Quantity I Rate I Amount TOTAL ADJUSTMENTS -REVISED QUOTATION -[ Signed Date i Contractor’s Representative) in acknowledgement of adjustment Signed Signed 3y Contractor upon receipt By LGL upon issue Date Date This Quotation shall provide for execution of the Work without impact on the Contract Schedule USE ONLY Approved for issue of Contract Variation Signed Date (Engineering Manager) |
APPENDIX 5/H Sheet 2 Of 2 L — [Work Package No] — Work Package: QPR No: Contractor Date: PRICE BREAKDOWN Item Description Unit Quantity Rate Amount BALANCE CARRIED FORWARD TO SHEET 1 — |
APPENDIX 5/1 ENGINEERING MANAGER (ORIGINATE) (File) N (EVALUATE) Copies ~S.CONT~S.CONT ~S.CONTAREA MANAGER Issue Contract Variation as Required (See Appendix 5/K) (File) Copies CONTRACTOR (Fiie) NOTE — THE QUOTATION PRICE REQUEST MUST BE ISSUED IN CONJUNCTION WITH A SITE INSTRUCTION |
APPENDIX 5/X X — [Work Package No] - Work Package: CV No: Contractor: Date: The Contract Sum is hereby varied as follows: S.I. No Q.P.R. No Cost Code Additions Deductions HI P + + 1 1 + 41 1 1 p- 1 1 M 1 1 + + I l + »m — — -..-.. TOTALS - NET ADJUSTMENT — YOU ARE HEREBY AUTHORIZED TO PROCEED WITH THE WORK INSTRUCTED BY THE ABOVE LISTED SITE INSTRUCTIONS Signed Date Engineering Manager) CONTRACT RECONCILIATION (LGL use only) DETAILS AMOUNT Original Contract Sum — Total Adjustments for C.V.’s to Previous C.V. No Net Adjustment this C.V. — Total Adjustments for C.V.’s to date — REVISED CONTRACT SUM - |
APPENDIX 5/K ENGINEERING MANAGER (ORIGINATOR OF CONTRACT VARIATIONS) ~S.CONT Copies ~S.CONTQUOTATION PRICE REQUEST RETURNED BY CONTRACTOR AREA MANAGER (See Appendix 5/1) (File) Copy CONTRACTOR (File) ACTION SITE INSTRUCTIONS NOTE • THE QUOTATION PRICE REQUEST MUST BE ISSUED IN CONJUNCTION WITH A SITE INSTRUCTION |
APPENDIX 5/L Sheet 1 Site Instruction No o CD |f Dayworks Sheet No Previous Dayworks Sheet No Month Day Shift 3 O Please list alt Labour as per Tender Form Appendix 10/B used to perform the Work, If material has been supplied, attach a list of the material supplied and copies of the invoices for that material. Work Package Contractor CD «-•• Total Chargable Hours Badge No Name Classification Allocated Hours Rate Total Hours Total Costs Distribute Total Costs For This Sheet (Including Materials) Into The Respective Cost Codes. Total Labour Total Material ARVC (Clause 4.2.8.5) Total Costs Signed Signed Date Note: Dayworks Sheets will only be approved on the day after the Work s performed. (Contractors Site Representative) (Engineering Manager) |
APPENDIX 5/L Sheet 2 Site Instruction No o CD «___% f •§• Dayworks Sheet No Previous Dayworks Sheet No Month Day Shift ^r o 3 2 Please list all Plant as per Tender Form Appendix 10/B used Work Package Contractor to perform the Work. 0 o 1° CD •-•• Total Chargable Hours Item No Plant Description Allocated Hours Unit Rate Quantity Total Costs — — ~~- — — - — — — — Distribute Total Costs For This Sheet Into The Respective Cost Codes. Total Costs $0.00 Signed Signed Date Note: Dayworks Sheets will only be approved on the day after the Work is performed. (Contractors Site Representative) (Engineering Manager) |
APPENDIX 5/M L — [Work Package No] — Certificate No Work Package: Contractor: Pursuant to Clause 4.2.12 of the General Conditions Of Contract, the Work is certified as having The following minor omissions and / or minor defects currently exist in the Work and you are i Minor Omissions And / Or Defects No Description (ATTACH ADDITIONAL LIST AS REQUIRED) Your attention is also drawn to the following: a) Pursuant to Clause 4.3.3 of the General Conditions Of Contract you are required to b) Pursuant to Clause 4.3.9 of the General Conditions Of Contract you are required to c) Pursuant to Clause 4.5.3 of the General Conditions Of Contract you are instructed to NOTE — THIS CERTIFICATE MUST BE ISSUED IN CONJUNCTION WITH A SITE INSTRUCTION Issued this Day of 200 Signed Engineering Manager) |
APPENDIX 5/N L — [Work Package No] — Certificate No Work Package: Contractor: Pursuant to Clause 4.2.13 of the General Conditions Of Contract it is hereby certified that the above Pursuant to Clause 4.1.6 of the General Conditions Of Contract the security presently held by LGL Details Of Security Is hereby returned and notice is hereby given to the surety’s that this or these Guarantees NOTE — THIS CERTIFICATE MUST BE ISSUED IN CONJUNCTION WITH A SITE INSTRUCTION ssued this Day of 200 Signed Name For and on behalf of LGL) n the presence of Mame of Witness Address of Witness |
APPENDIX 5/O Contractor Work Package: To: LGL WITH RESPECT TO THE ABOVE REFERENCED CONTRACT (hereinafter called the and after deduction of backcharges and other adjustments, the net payment to us of: (Agreed Net Payment] hereby remises, releases and forever discharges LGL and the Owner as defined in the It is further agreed that for the consideration and Agreed Net Payment aforesaid, the i The Contractor shall indemnify and save harmless the Releases against and from any and all IN WITNESS WHEREOF we the said Contractor have executed these presents according to Dated this Day of 200 SIGNED for and on behalf of the Contractor by its duly constituted attorneys: n the presence of: ^Xxxx of Witness: Address of Witness: |
APPENDIX 5/P Contractor: Work Package: Project; f^ J^*- Date: TO BE SUBMITTED WITHIN FOL^^^J-iGHT (48) HOURS e£ Date of Accident ^^f; Time Exact location <• -^ PERSONS INVOLVED ^^"^ Name Involvement * t- i <^J> | ~OjT — WITNESSES -^^l"^ Slame Address l ^^^ Tel No Details of injury to personnel and / or damage tp^cjPTprrifcnt and / or property: CL^ Sequence of events leading up to accident: £^^ ^s Detailed description of the accident: * K^ Conclusions: ^ ml <3 Recommendations: ^. N&^’ /Vhen and by whom will the recommendatrf^T t^ carried out: j^ 3 0*3 Signed (Contractor’s Safety Officer) |
APPENDIX 5/Q THIS AGREEMENT made the day of 200 between of (‘LGL’) of the one part and of (‘Contractor’) of the other part WHEREAS LGL requires the following work should be undertaken: AND has accepted a tender by the Contractor to undertake and completion such work for the total contract price of: The parties agree as follows: 1 In this agreement words and expressions shall, unless the context otherwise require, have the same meaning 2 The following documents shall be deemed to form and be read and construed as part of this agreement: a) Addenda and Notices Of Explanation (list) b) Tender documents as issued by LGL including Volume 3A, 3B & 3C c) Minutes of Post-Tender/ Pre-Award Meeting and post-tender correspondence (list) d) Contract Schedule (attach) e) Contractor’s Tender 3 In consideration of the agreements on the part of LGL in this agreement the Contractor will undertake and 4 In consideration of the agreements on the part of the Contractor in this agreement LGL will make payments to 5 If any party to this agreement consists of one or more persons or one or more corporations or two or more 6 This agreement shall take effect according to its tenor notwithstanding any prior agreement in conflict or at 7 The undersigned authorised representatives of each party have initialled each page of this document and each Initialled by (For and on behalf of the Contractor) and by (For and on behalf of LGL) IN WITNESS WHEREOF the parties have executed this agreement the day and year first above written ixecuted by the Contractor by its authorised representative: n the presence of: Name of Witness: Address of Witness: ixecuted by LGL by its authorised representative: the presence of: Name of Witness: Address of Witness: |
APPENDIX 5/X X — [Work Package No] — Work Package: Contractor: Address (From Contract for ‘Service of Notices”) NOTICE is hereby given pursuant to Clause 4.5.4 of the General Conditions Of Contract that you Defaults, Refusals, Neglects or Acts (Specify in details the defaults, refusals, neglects or acts.) (ATTACH ADDITIONAL LIST AS REQUIRED) •vJOTE — To be served personally on one of the person occupying the positions of authorisation on j site nominated in Tender Form 3/G to accept Service of Notices or sent by certified or registered mail or facsimile to the normal place of business of the Contractor or otherwise served in accordance with Clause 4.5.7 of the General Conditions Of Contract. Dated this Dayjrf 200 Signed Engineering Manager) |
6.1
|
Introduction | |
6.2
|
Country Specific Amendments and Additions to Section 4 | |
6.3
|
Training and Localisation Policy | |
6.4
|
Freight, Duty and Taxes | |
6.5
|
Travel to Site | |
6.6
|
Accommodation and Messing | |
6.7
|
Power | |
6.8
|
Communications | |
6.9
|
Potable Water | |
6.10
|
Construction Water | |
6.11
|
On Site Facilities | |
6.12
|
Site Security | |
6.13
|
Hours of Work | |
6.14
|
LGL Safety Requirements | |
6.15
|
Vehicles | |
6.16
|
Insurance to be Arranged by LGL | |
6.17
|
Insurance to be Arranged by the Contractor |
6.1 | INTRODUCTION | |
6.1.1 | This Section sets out the Special Terms and Conditions of Contract, which are to regulate the performance of the Work, and the obligations and requirements of the various parties involved in the execution of the Work. These terms and conditions are of special application to the Contract and to the extent if any, that they may be inconsistent with the General Conditions of Contract, these terms and conditions shall take precedence over the General Conditions. | |
6.2 | COUNTRY SPECIFIC AMENDMENTS AND ADDITIONS TO SECTION 4 | |
6.2.1 | In addition to the requirements of Clause 4.1.3.3, the Contractors workforce shall be sufficiently conversant in the English Language to understand the induction courses (Clause 4.3.6.3), the LGL Safety Requirements (Clause 4.3.6.2) and any instructions regarding industrial safety and health. | |
6.3 | TRAINING AND LOCALISATION POLICY | |
6.3.1 | LGL has a specific policy for the training and use of local persons, suppliers and organizations (the LGL Training and Localisation Policy). It is a requirement of this contract that the Contractor strictly complies with this policy (the costs of which are deemed included generally in the Contract Price or Contract Rates). A copy of the policy is included as Appendix 7/A. | |
6.3.2 | Lihirian residents shall be given employment preference where they are suitably qualified. | |
6.4 | FREIGHT, DUTY AND TAXES | |
6.4.1 | As set out in General Condition 4.4.5.4(a), LGL is zero rated for GST in PNG and all Contractor invoices to LGL should reflect this. For the removal of doubt, LGL will not be responsible for the payment of GST on sub-contractor’s invoices as it is the responsibility of the Contractor to be registered for GST in PNG. | |
6.5 | TRAVEL TO SITE | |
6.5.1 | Travel to site shall only be permitted if LGL approve the Contractor’s Accommodation Request Form (see appendix 7/A). | |
6.5.2 | The Contractor is responsible for all costs associated with transport of its personnel to Lihir. | |
6.6 | ACCOMMODATION AND MESSING | |
6.6.1 | LGL will provide accommodation and messing together with laundering facilities at Site (Site Accommodation). | |
6.6.2 | Site Accommodation will be provided at no charge to the Contractor for the Contractor’s Projected Manpower as set out in Tender Form Appendix 10/D, and for any additional mandays required for Variations. The Contractor must provide the Site Accommodation to its employees and Subcontractors at no cost. Any additional accommodation that the Contractor requires shall be deducted from payments due to the Contractor as back charges or may be otherwise recovered as a debt due. | |
6.6.3 | Accommodation will be available on both a single and share basis with detached ablution blocks. The single accommodation shall be limited to key personnel however, no guarantee on availability of single accommodation is given. |
Volume 3A Issue 1 October 2006 version 3 | Section 6 Page No 1 |
6.6.4 | All occupants of the Site Accommodation must strictly comply with the LGL Camp Rules & Procedures. The Contractor shall ensure that all its employees including the employees of any of its Subcontractors are given a copy thereof and acknowledge receipt by signature, and that they are fully familiar with the provisions of these Rules & Procedures. | |
6.6.5 | Any person who wilfully causes damage to any part of the Site Accommodation premises or its facilities or acts in a manner which interferes with the use or enjoyment of same by other residents, will have their Site Accommodation withdrawn without notice. | |
6.6.6 | Advance booking must be made as part of travel arrangements. No one shall be provided camp accommodation without prior approval by LGL. | |
6.6.7 | All persons shall be required to book into the accommodation through the camp manager in the camp office. The camp manager shall only allocate accommodation to those persons who have been approved by LGL. | |
6.6.8 | All departing residents must book out through the camp office and obtain a departing resident’s clearance. | |
6.6.9 | The Contractor hereby indemnifies and holds harmless LGL and its directors, officers, employees, agents and consultants from and against any and all claims, demands, debts, accounts, expenses, costs, liens, actions and proceedings of any and every kind whatsoever by any person arising from the accommodation of any person who whilst booked into LGL’s camp was an employee of the Contractor or an employee of any Subcontractor to the Contractor | |
6.7 | POWER | |
6.7.1 | The Contractor shall be provide all necessary construction power. | |
6.7.2 | All temporary construction power distribution shall be in full compliance with all Applicable Laws | |
6.8 | COMMUNICATIONS | |
6.8.1 | Telephone and facsimile services are available in limited supply at the Mine for use by the Contractor. Contractors who use LGL facsimiles and telephones shall have all costs accrued, deducted from payments due or otherwise recovered as a debt due. | |
6.8.2 | The Contractor shall provide, at its expense, any onsite H.F. / VHF / UHF. radio communications system it may require. Any such systems shall be properly licenced and operated in accordance with all Applicable laws. | |
6.9 | POTABLE WATER | |
6.9.1 | Limited potable water shall be available at the Site. Any other requirements and distribution of potable water shall be arranged and paid for by the Contractor. | |
6.10 | CONSTRUCTION WATER | |
6.10.1 | Limited construction water will be available to the Contractor from the Londolovit xxxx. The Contractor shall provide all equipment necessary to load and haul the water to its Work site. | |
6.11 | ON SITE FACILITIES | |
6.11.1 | The Contractor shall supply all necessary on site facilities, such as crib huts and construction offices. Such facilities shall be located as required by LGL. |
Volume 3A Issue 1 October 2006 version 3 | Section 6 Page No 2 |
6.11.2 | LGL will establish and maintain ablution blocks on Site at various locations for the general use by any person. | |
6.12 | SITE SECURITY | |
6.12.1 | The Contractor shall be responsible for the security of the Work, including but not limited to materials, plant and tools whilst performing the Work. | |
6.12.2 | No employee will be permitted to remove any materials (including scraps or waste), tools or other equipment from the Site, without the written authority of the Contractor’s Site representative. | |
6.12.3 | The Contractor shall be bound to follow the directions of the general security regulations issued by LGL and any amendments to such security regulations as may be issued by LGL from time to time. | |
6.12.4 | For the purpose of safeguarding property, LGL reserves the right to examine any package or container entering or leaving the Site. | |
6.12.5 | The Contractor must provide LGL with a list of all proposed personnel prior to starting work for LGL’s review. LGL reserves the right to deny access to the Mine to any individual. This right is arbitrary and absolute. | |
6.12.6 | LGL reserves the right to have any Contractor’s personnel excluded from the Site and the Work for any deemed or apparent breach of safety or security. LGLs’ interpretation of safety or security breeches will be arbitrary and absolute. | |
6.13 | HOURS OF WORK | |
6.13.1 | The Site will be available for the Work to be undertaken seven days per week, twenty-four hours per day. LGL will provide supervision seven days per week ten hours per day. | |
6.13.2 | The Contractor shall work a roster schedule acceptable to LGL and indicate its preferred work schedule in its Tender submission — Appendix 10/D, Projected Construction Weekly Manpower. | |
6.13.3 | The Contractor shall maintain work continuity during the period its employees are rostered off. This shall be shown on the Contractor’s work schedule. | |
6.13.4 | The Contractor’s employees shall vacate the Site when not actively engaged in the Work. | |
6.13.5 | The hours worked by all employees, other than staff and superintendents, shall be recorded on the daily manpower records (Appendix 5/F, Sheet 2 of 3). | |
6.14 | LGL SAFETY REQUIREMENTS | |
6.14.1 | The Contractor shall, at all times, have a first aid attendant on site who is properly trained in all matters of general first aid. | |
6.14.2 | Should a medical situation require an evacuation from site, LGL will assist in making the appropriate arrangements, at the cost of the Contractor, for the evacuation of the employee. | |
6.14.3 | If medical and first-aid facilities are made available to the Contractor’s employees, then, in consideration of the use of such facilities and the receipt of such services, the Contractor hereby agrees that it will release, defend, indemnify and hold harmless; LGL and its directors, officers, employees, agents and consultants from and against any and all claims, suits, demands and liabilities arising from the receipt of such |
Volume 3A Issue 1 October 2006 version 3 | Section 6 Page No 3 |
services by the Contractor’s employees or the use of such facilities by the Contractor’s employees. | ||
6.14.4 | In the event that Contractor’s personnel require the use of LGL’s on-site first aid facilities then the Contractor will be charged per person for each treatment received. | |
6.14.5 | LGL will provide a safety indoctrination for all Contractor’s personnel. The safety indoctrination is mandatory and must be taken prior to the personnel starting work at site. The Contractor must provide a request for the course 48 hours in advance, detailing the number of persons attending. | |
6.14.6 | The following Occupational Health and Safety manuals and/or documents shall be complied with: |
• | LGL’s LihirSafe Policy | ||
• | MOPU Specific Safety Management System (SMS) | ||
• | LGL’s Environmental Management System | ||
• | MOPU Specific Environmental Management System (copies available upon request). |
6.15 | VEHICLES | |
6.15.1 | The restricted use of vehicles on the site will be enforced. | |
6.15.2 | Only vehicles absolutely required will be allowed on the Mine. | |
6.15.3 | The maximum speed of vehicles on site is 25 km per hour. | |
6.15.4 | All equipment on the site shall be equipped with devices to produce an auditory signal when the vehicle is moving in reverse. | |
6.16 | INSURANCE TO BE ARRANGED BY LGL | |
6.16.1 | LGL shall maintain comprehensive general liability insurance on its own behalf and on behalf of the Contractor. LGL’s insurance in respect of the Contractor shall be secondary to the Contractor’s primary coverage for comprehensive general liability in an amount of not less than. | |
6.16.2 | LGL will provide upon request, a summary of the coverage in place and a copy of the insurance certificate. | |
6.16.3 | LGL shall be entitled at any time, and from time to time during the currency of the comprehensive general liability insurance policy, to arrange or agree to such alterations to the amount therein or any of the terms and conditions thereof, as LGL in its absolute discretion thinks fit. | |
6.16.4 | The Contractor shall at all times observe and perform the appropriate procedures and requirements, specified or implied in relation to any claims made by the Contractor under the comprehensive general liability insurance policy. | |
6.16.5 | The Contractor shall be responsible for the amount of the deductibles specified in the comprehensive general liability insurance policy and shall indemnify LGL and its directors, officers, employees, agents and consultants against all losses, claims and demands up to the amount of such deductibles. | |
6.16.6 | The effecting and keeping in force of insurance by LGL in favour of the Contractor and Subcontractors shall not in any way limit the responsibilities, obligations and liabilities of the Contractor under the provisions of the Contract. | |
6.17 | INSURANCE TO BE ARRANGED BY THE CONTRACTOR |
Volume 3A Issue 1 October 2006 version 3 | Section 6 Page No 4 |
6.17.1 | The Contractor shall, at its own expense, obtain and maintain in effect and cause its Subcontractors (including those at sub-tier levels) to take out and maintain in effect, for the duration of the Work, the following insurances: | |
6.17.1.1 | Motor Vehicle Related Insurances | |
Motor Vehicle Third Party Insurance covering third party personal injuries liability for all motor vehicles, as required by the PNG Motor Vehicles (Third Party Insurance) Act; | ||
Comprehensive Motor Vehicle Liability Insurance covering use of all motor vehicles used by the Contractor or its Subcontractors (whether or not owned by them) in connection with the execution of the Contract, with not less than the following limits: |
a. | Death and Bodily Injury — the Kina equivalent of each person/occurrence; | ||
b. | Property Damage. |
6.17.1.2 | Third Party Liability Insurance | |
Third Party Liability Insurance covering all operations of the Contractor in the performance of work on or off the Site, including contractual liability insurance covering the liability assumed in this Contract. This policy or policies shall provide combined single limits for all injuries or death to persons and damages per occurrence. | ||
6.17.1.3 | Workers’ Compensation and Occupational Health Insurances | |
Insurances covering any damage, expense, loss or liability suffered or incurred by any person employed by it or its Subcontractors during the performance of the Work, whether arising; |
(a) | by virtue of the any Applicable Laws relating to workers’ or accident compensation or employers’ liability in any relevant jurisdiction where the Work is to be performed; | ||
(b) | by virtue of the PNG Workers Compensation Act; or | ||
(c) | at common law at least 0. | ||
(d) | WETHA clause |
Such insurance shall include the following special coverage extensions: |
(a) | Employer’s Liability Insurance coverage with limits of not less than for any one occurrence attributable to a single source/each employee; | ||
(b) | Such insurance shall indemnify and keep indemnified LGL as principal in respect of any claim made under any relevant workers or accident compensation legislation or at common law in Papua New Guinea and will include where non Papua New Guinea domiciled employees, contractors and agents are engaged in the provision of the Works in Papua New Guinea an additional WETHA Policy Extension. | ||
(c) | LGL to be noted as Owner on the Workers’ Compensation Policy. |
6.17.1.4 | Contractor’s Plant and Equipment Insurance | |
Insurances covering all of the Contractor’s and/or its Subcontractor’s major plant and equipment which the Contractor or its Subcontractors intend to bring or bring onto the Site for the execution of the Work. |
Volume 3A Issue 1 October 2006 version 3 | Section 6 Page No 5 |
6.17.1.5 | Professional Liability | |
If the Contractor is providing any professional services, professional liability insurance with a limit of not less than inclusive for any one claim [and in the aggregate?] or such greater amount may be required by any applicable professional organization or licensing authority. Such insurance shall be continued in place for at least six years following completion of the Work | ||
6.17.2 | It is the Contractor’s responsibility and liability to ensure that any subcontractor they engage is fully insured in accordance with the conditions of this Contract. | |
6.17.3 | The Contractor shall, and ensure that each of its Subcontractors shall comply with the requirements of the PNG Insurance Act which requires all insurance covering risks situated in Papua New Guinea to be arranged with PNG licenced insurers, unless an exemption is obtained. | |
6.17.4 | Where, in accordance with the provisions of the Contact, insurances effected by the Contractor and its Subcontractors are effected in joint names, the Contractor must ensure that the insurance policies provide that all insurance agreements and endorsements (with the exception of limits of liability) operate as if there was a separate policy of insurance covering each party comprising the insured under each policy. | |
6.17.5 | The Contractor must ensure that each insurance policy effected by it and its Subcontractors provides or contains an endorsement that: |
(i) | the insurer waives all rights, remedies or relief to which it might become entitled by way of subrogation against any of the parties comprising the insured under each policy; | ||
(ii) | failure by any insured under each policy to observe and fulfil the terms of the policy does not prejudice the insurance in regard to any other insured under that policy; | ||
(iii) | the giving of notice of an occurrence by one insured shall constitute notice by each insured; | ||
(iv) | it may not be cancelled or the protection afforded thereby substantially changed without 30 days prior written notice to LGL; | ||
(v) | LGL and its subsidiaries, associated and affiliated companies and their respective officers, directors and employees are noted as named insureds; and | ||
(vi) | the Contractor’s coverage is primary to any coverage LGL may elect to carry for its own account, or for the Contractor and its Subcontractors. |
6.17.6 | The Contractor shall be liable for all deductibles specified in insurances. |
Volume 3A Issue 1 October 2006 version 3 | Section 6 Page No 6 |
LIHIR GOLD LIMITED Towns & Camps Administration |
• | Please complete all details and forward to LGL Cam Operations Department. Allow 5 and days for processing. | ||
• | Accommodation is requested for the following person (one per person). Authorization of relevant Department Head must be obtained. |
Date:
|
/ / | Gender Male/Female | ||||
Given Name(s)
|
Last Name: | |||||
Company:
|
Point of Hire: | |||||
Position Title:
|
(If Lihirian, please state village) | |||||
Reason for Accommodation; |
||||||
SINGLE:
|
SHARED: | HOTEL: | ||||||||
1st Field | Room Allocation | |||||||||
Permanent or Short | Roster Cycle eg. | Break Travel | (Camp Admin | |||||||
Site Based: | Term | 21/9, 21/12 | Out Date | Only) | ||||||
From: |
||||||||||
To: |
Print Name:
|
Department: | |||||
Section: | ||||||
Site Phone:
|
Trunk Radio: | |||||
Signature:
|
Contract/Cost Code: | |||||
LGL Camp Operations Authorisation | ||||||
Print Name:
|
Date: | / / | ||||
Signature: |
||||||
• | This request does not guarantee accommodation until approved by Camp Operations. Do not proceed with travel arrangements until confirmation has been received as to availability. | |
• | Failure to compete R&R or final departure form will result in continued charging. | |
• | All new bookings (in and out) of camp will be carried out at
both NCS Camp Offices. Accommodation will not be processed until all details are filled in. |
PROJECT
INTERNAL EQUIPMENT
SCOPE OF WORK
Revision | Date | Author | Approved By | Comments | ||||
OB
|
11/06/09 | AD | IMcN | Removed Pyroflex installation from SoW | ||||
OA
|
14/10/08 | IMcN | Initial Draft |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 2/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
8.1
Introduction |
3 | |||
8.2
Work Included |
3 | |||
8.2.1 Work Summary |
3 | |||
8.2.2 Battery Limits |
3 | |||
8.2.3 General Requirements |
3 | |||
8.2.4 Methodology |
4 | |||
8.2.5 Temporary Works |
4 | |||
8.2.6 Survey and Set Out |
4 | |||
8.2.7 Quality Control & Testing |
5 | |||
8.2.8
Refractory Lining |
6 | |||
8.3
Work Not Included |
9 | |||
8.4
Attachments |
10 | |||
8.4.1 LGL Technical Specifications |
10 | |||
8.4.2 Contract Drawings |
10 | |||
8.4.3 Volume 3C |
11 |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 3/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
8.1 | INTRODUCTION | |
The Work under this Contract consists of the supply of labour, supervision, transportation, materials, equipment, tools and supplies (except those items described in clause 8.3 “Work Not Included”) necessary for the complete installation of the Autoclave internal equipment for the MOPU project at LGL’s operation on Lihir island. | ||
The internal equipment to be installed includes: |
• | Refractory Lining | ||
• | Cluster Blinds and Dip Pieces | ||
• | Titanium Internals |
8.2 | WORK INCLUDED | |
8.2.1 | Work Summary | |
The Contractor shall supply all labour, supervision, transportation, materials, plant, equipment, consumables and supplies necessary to perform the Works as set out in the Drawings, Specifications and this scope. | ||
A summary description of the works by project facility is outlined below, with detailed requirements covered in Section 8.2.8 and 8.2.9: |
Facility | Facility Name | Requirements | ||
1343
|
Pressure Oxidation | Installation of the corrosion resistant membrane lining, refractory lining, cluster blinds, dip pieces, and titanium internal baffles and walls. |
The Work includes, but is not limited to, installation, monitoring and testing of installation, and site clean-up. | ||
8.2.2 | Battery Limits | |
The physical limits of work for this package shall be defined by the following: |
• | The internals of the new 44.8 m x 5.6 m autoclave shell. |
8.2.3 | General Requirements | |
All material, equipment and services to be furnished by the Contractor shall conform with the requirements of all statutory authorities having jurisdiction over the work, to the Specifications and Drawings, to the current local and international standards relevant to the work, and to all other relevant publications, which by this reference, shall form part of the contract. | ||
At all times during The Works, the Contractor shall observe and adhere to the statutory limitations / restrictions under which the Mine licence operates. | ||
At all times, the Contractor shall observe and respect LGL’s OH&S standards, and maintain and promote a high regard for safety. The Contractor shall prepare and implement Project specific safety and environmental management plans that covers all aspects of the Works. | ||
All requirements of this Scope of Work shall be minimum requirements unless otherwise specifically stated. | ||
Hazardous materials shall be stored, handled and used in such a manner that workers and the environment are protected. All hazardous waste resulting from the work shall be properly disposed of |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 4/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
8.2.4 | Methodology | |
Prior to commencement of the Works on Site, the Contractor shall prepare, for LGL review, construction methodologies for the various components of the Works. The works methodologies shall address the following as a minimum: |
• | Undertaking of the Works within the constraints imposed by the available land footprint, available height clearances and the location of other existing infrastructure; | ||
• | Management of access to Works area given identified accessibility constraints; | ||
• | Specific job safety assessment (JSA) requirements; | ||
• | Planned working hours / shifts; | ||
• | Power and water requirements; |
The Contractor shall not commence work on Site until the works methodologies have been approved by LGL. | ||
8.2.5 | Temporary Works | |
The Contractor shall establish any temporary offices, sheds, stores and working areas as may be required for the execution of the Works under the Contract within the area occupied by the Works or such other areas as may be shown on the Drawings or designated by LGL. | ||
Any temporary construction which the Contractor requires for the performance of the Works, such as construction of haul roads, bridging of toe drains, additional access ramps to the Site of Works, equipment yards, etc, shall be to the approval of LGL and shall be performed at the Contractor’s expense. Prior to practical completion of the Contract, the Contractor shall remove all Temporary Works and reinstate affected areas to their original condition at its own expense, and to the complete satisfaction of LGL, unless otherwise directed by LGL. | ||
8.2.6 | Survey and Set Out | |
The Contractor shall be responsible for all survey and set out required for the Works and, unless otherwise approved by LGL, shall provide a licensed surveyor to perform all such work. | ||
Unless otherwise advised, all coordinate and level information shall be related to the “Lihir Grid” which is a plane coordinate system in metres aligned on AMG North. The site position datum is PSM 12340 “UNIFORM 8” with the following characteristics: |
Coordinates and | ||||||||
Parameter | RL to “Lihir Grid” | AMG Coordinates and RL | ||||||
Easting
|
11 843.12 | 461 842.3 | ||||||
Northing
|
5 030.31 | 9 655 030.1 | ||||||
RL |
18.50 | 18.60 |
The “Lihir Grid” bearing is AMG plane bearing at PSM12340. | ||
LGL will provide details of any existing local benchmarks in the vicinity of the Site of Works. Where no such benchmarks are available the Contractor shall be responsible for transferring control to the Site from the nearest available benchmark or site position datum PSM 12340 as appropriate. | ||
The site also uses a second level datum for the mine pit and general topographical survey. This mine datum is based on a level at PSM 12340 of RL1018.50 and conversion to the project level datum entails subtraction of 1000.000m. Certain survey / reference information may reflect the mine datum and should be converted to the project datum as required to support design and construction. |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 5/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
8.2.7 | Quality Control & Testing | |
8.2.7.1 | Quality Plan | |
The Contractor shall prepare a Quality Plan for all Works to be carried out under the Contract, whether on Site or off Site. A controlled copy of the Quality Plan shall be provided to LGL prior to commencement of any Works. | ||
The Contractor’s Quality Plan shall describe the application of the Contractor’s Quality System to the Contract and shall identify the Contractor’s proposed methods of assuring that the requirements of the Contract are met. In particular, the Quality Plan shall address the following: |
• | Survey control; | ||
• | Daily record keeping during the course of the Works; | ||
• | Inspection and testing plans; | ||
• | The requirements of each Hold Point for the Works, including information to be supplied at the Hold Point and the party responsible for approval to proceed; | ||
• | Collection of information to facilitate preparation of as-constructed documentation. |
No provision of the Quality Plan shall over-rule any requirement of the Contract. | ||
8.2.7.2 | Inspection, Testing and Daily Work Records | |
The Contractor shall maintain daily records during the execution of the works. As a minimum, the record shall include the following information: |
• | Description / sketch of the work completed; | ||
• | Details of any inspections or testing carried out; | ||
• | Other pertinent observations such as weather constraints or other unusual outcomes. |
All inspection reports, test records and daily work sheets shall be available for inspection by LGL within twenty-four (24) hours of completion of the inspection, test or days work. Copies of relevant information shall be supplied to LGL upon request. | ||
8.2.7.3 | Hold Points | |
For the purposes of this Contract, “Hold Points” shall mean those points beyond which the Work shall not proceed without review and release by LGL. | ||
The Contractor shall agree the “Hold Points” with LGL prior to the work commencing and in accordance with the Manufacturer’s recommendations and procedures. The “Hold Points” shall form part of the Contractor’s schedule. | ||
Unless otherwise directed by LGL, the Contractor shall give at least two (2) working days prior notice of each Hold Point and shall ensure that all relevant test and verification results are available for inspection by LGL at the time of the Hold Point. | ||
The Contractor shall allow for one (1) working day at the Hold Point for LGL to attend the Site and inspect the work and documentation. | ||
8.2.7.4 | Non-Conformance | |
The Contractor shall promptly notify LGL of any product or service non-conformances. Such notification shall require submission of a non-conformance report which shall clearly identify the issue and indicate the proposed method of rectification for approval by LGL. | ||
The Contractor shall use standard forms approved by LGL for all non-conformance reports. | ||
8.2.7.5 | Audits | |
LGL may carry out a Quality Audit of the Contractor’s Quality System at any time. Such audits |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 6/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
may include system or compliance audits and require access by LGL to the Contractor’s offices, factories or Site of Works. | ||
Where LGL’s audit indicates non-conformance in a process or procedure, the Contractor shall submit a proposal for remedial action, for the approval of LGL. | ||
Where LGL’s audit indicates a non-conformance in a test or measurement which would lead to a failure of a lot or batch to satisfy specified requirements for acceptance, then the Contractor shall either: |
(i) | Accept LGL’s test or measurement, and submit a proposal for remedial action for the approval of LGL, or | ||
(ii) | Carry out a repeat test or measurement which shall be used for determining acceptance or otherwise of the lot or batch. Any repeat test or measurement shall be at the Contractor’s cost, and shall be subject to a process audit by LGL. |
8.2.7.6 | As-Built Documentation | |
The Contractor shall provide LGL with a collated copy of all documentation developed during the course of the Works including as-built drawings / drawing xxxx-ups, daily work sheets, inspection reports, test records, photographs, information registers, calculations, hand sketches, software input files, computer models, documentation and compliance certificates from suppliers, MSDSs, etc. | ||
As an absolute minimum, as-built drawings shall comprise a full set of the design drawings marked up in red with the following information: |
• | Any changes to the designed general arrangement; | ||
• | Any new information developed during the course of the Works including set out of works designed by the Contractor, survey levels and locations of underground construction, etc. |
Where electronic information exists in a recognised standard format, the information shall be handed over electronically. All other information shall be handed over as suitably collated and bound hardcopies. | ||
Practical Completion will not be awarded until a suitable as-built documentation package has been handed over to LGL. |
8.2.8 | Refractory Lining | |
8.2.8.1 | General | |
The acid resistant refractory lining system is to be installed by this Contractor after completion of the corrosion resistant membrane lining. | ||
The acid resistant refractory lining system shall be installed at the plant site. | ||
8.2.8.2 | Documents, Drawings, and Data | |
The following documents will be available from LGL: |
• | an overall assembly drawing | ||
• | detailed drawings | ||
• | certificates of manufacturing materials (ISO or other), including all production tests conducted during manufacture and qualification of the products | ||
• | other material records specified by applicable codes and/or standards |
The Contractor shall provide the following documents and data to LGL: |
• | As-Built drawings |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 7/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
• | Contractor’s quality control program | ||
• | installation records as required by the applicable codes and/or standards and the liner manufacturer/supplier |
All Contractor supplied documentation shall be identified with LGL’s name, LGL’s contract number, item number, and job location. | ||
8.2.8.3 | Materials and Installation | |
The Autoclave will be supplied and erected at the Site by others. The Contractor shall install the brick lining comprising ceramic paper, and acid resistant bricks, compartment divider walls and the titanium nozzle liners. The Contractor’s scope of supply shall include, but is not limited to the following: |
• | install the brick lining as detailed on the manufacturer/supplier’s design drawings which will consist of a ceramic paper layer (if detailed as the Supplier as part of the lining system), backing mortar joint, backing course of brick, face course mortar joint, and face course of brick. | ||
• | install the brick lining to the nozzles which nominally consists of a ceramic paper layer (if deemed required by the Supplier), mortars as detailed, polymer blocks or sleeve as detailed, and the titanium sleeve. | ||
• | installation of titanium compartment divider walls and titanium nozzle liners as detailed on the drawings | ||
• | all materials (not detailed in clause 8.3 as being supplied by others), equipment, manpower, supervision, transportation as required to complete the installation of the brick lining | ||
• | post installation treatment and/or curing in accordance with the manufacturer/supplier’s recommendations and procedures | ||
• | inspection, examinations, and testing |
8.2.8.4 | Brick Lining | |
The supplied bricks will be the supplier’s brick shapes required to suit the internal layout of the Autoclave. Straight through mortar joints from the face course brick through to the corrosion resistant membrane shall be minimised. | ||
The bricks forming the chases for the compartment wall corbels and head baffles shall be saw cut and shall form an even surface within the chase. The Contractor shall install the chases and corbels in accordance with the supplier’s design drawings. | ||
Special bricks shall be sued to line the Autoclave dished heads. The supplier will supply bricks such that the size and tapers provide a close fit lining minimising the mortar filled gap (ged gap) between brick and ceramic paper. | ||
Specially shaped bricks shall be used for the nozzle openings so that the bricks form a compression ring around the nozzle opening for the nozzle necks. This is applicable to all courses. | ||
Each baffle shall be built though the face course brick, which shall serve as a chase. The head baffles shall be constructed of brick using alternate header and stretcher courses keying the bricks in both horizontal directions. | ||
8.2.8.5 | Installation | |
8.2.8.5.1 | General | |
All exposed membrane lined surfaces on which workers have to stand shall be protected from damage (gouges, punctures, scratches or nicks) and from contamination by particulates and impurities. |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 8/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
Any protective covering installed by the Contractor to prevent damage to the membrane lined surfaces shall remain intact until that area is ready for brick lining. | ||
The Contractor shall repair the membrane lining at its cost where the repairs are required due to damage made by the Contractor during the installation of the brick lining. | ||
8.2.8.5.2 | Mortar | |
The mortar joints shall be in accordance with the Supplier’s design which will include the average design mortar joint thickness and maximum and minimum mortar joint thicknesses. | ||
All mortar joints shall be full and tight with no air inclusions or voids. The bricks shall be buttered on three sides and pressed into place. Excess mortar shall be cleaned off with a trowel and mortar surface finished. During the work, LGL or its inspector will have the right to request the Contractor to remove random bricks to ensure that mortar coverage is complete on the brick backside. | ||
The mortar mix, its application, and curing shall be made in strict accordance with the mortar manufacturer’s instructions. Mixed mortar life, as specified by the manufacturer, shall be strictly adhered to and not exceeded. Nothing shall be added to prepared mortar to extend its life beyond that specified by the manufacturer. Leftover mortar, not used within the prescribed hardening time, shall be discarded. | ||
8.2.8.5.3 | Bricks | |
Damaged, broken or chipped bricks shall not be installed. LGL and the Contractor shall establish guidelines regarding the acceptance of marginally damaged bricks. | ||
Cutting of the bricks shall be done outside the Autoclave. The cuts shall be smooth and straight to provide a good bonding surface. The cuts shall be made with a brick cutting saw only. All residual water on the cut piece shall be wiped off with a clean dry rag. | ||
To prevent air moisture condensation, which would impair mortar quality, no bricks shall be laid when the temperature is less than 3°C above the ambient air dew point at the location where the refractory lining is being installed. | ||
The temperature of the brickwork must be maintained within the range of 10°C and 32°C until the mortar is set. | ||
6.2.8.5.4 | Nozzles | |
The nozzle necks shall be lined with special shaped polymer brick to suit the nozzle internal diameter. | ||
The Contractor shall install the metallic nozzle sleeves. The sleeves shall be installed so that no voids exist between the sleeve and nozzle brick lining. | ||
8.2.8.5.5 | Compartment Walls | |
The Contractor shall install the compartment walls after the barrel, head, and nozzle bricks have been installed. | ||
The Contractor shall install the compartment walls as detailed on the drawings. | ||
8.2.8.5.6 | Autoclave Internals | |
The Contractor shall install the Autoclave internals as detailed on the drawings. | ||
8.2.8.6 | Inspection and Testing | |
8.2.8.6.1 | General | |
LGL’s Area Manager and inspector shall have access to the work during its preparation or progress. The Contractor shall provide facilities and access for this inspection. | ||
Deficiencies found by LGL during lining installation shall be promptly reported to the Contractor |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 9/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
before the end on the day the deficiency is identified. Failure of LGL to identify deficiencies shall not relieve the Contractor from its responsibility to repair or replace any areas found to be deficient. | ||
The Contractor shall satisfy LGL that the tests described have been performed according to the test method requirements, and that the test results meet or exceed the specification. | ||
The Contractor shall notify LGL at least 3 days in advance of readiness of each agreed upon witness point. | ||
Defective materials disclosed by testing shall be rejected and not used. | ||
8.2.8.6.2 | Mortar |
Samples of mixed mortar shall be randomly taken once per day during installation of the brick lining. Sufficient material shall be taken to make three 2.54 cm right cylinders from each mix. Consistency in taking the samples is important. The samples shall be uniformly cured at 20°C for seven days or 20 °C for 24 hours and 60°C for 16 hours. | ||
Following curing, the Contractor shall perform compressive strength in accordance with ASTM C579, method A and water adsorption tests in accordance with ASTM C413 on one of the cylinders from each batch. The compressive strength of the mortar samples shall be greater than 90% of the value specified by the supplier for that mortar type. If the sample fails the test, then the Contractor shall test a second sample. If the 2nd sample also fails, then LGL and the Contractor shall evaluate the impact of the failed sample and, at its discretion, LGL may require the affected brick lining affected by the sub-standard mortar, reinstalled at no cost to LGL. | ||
Untested samples will be delivered by the Contractor to LGL clearly identifying the lot number, date manufactured, batch number, batch time/cure time, compressive strength, and water absorption as documented in the Contractor’s QA/QC documentation. LGL at its discretion and cost, may test additional cylinders to verify the Contractor’s QA/QC documentation. | ||
8.2.8.6.3 | Rejection | |
If the workmanship is not in accordance with the supplier’s design and specification, this scoe of work, or the Contractor’s QCP, then LGL will require repairs or alterations to rectify the defect. | ||
If defects in the materials or workmanship are discovered after Practical Completion, they will be handled in accordance with the Defects Liability. | ||
Any omission or failure on the part of LGL to disapprove or reject any work or materials shall not be construed as an acceptance of any defective work or materials. | ||
8.3 | WORK NOT INCLUDED | |
The following items are specifically excluded from the Contractor’s scope: |
• | Supply and installation of the Autoclave shell | ||
• | Supply of the corrosion resistant membrane lining materials | ||
• | Installation of the corrosion resistant membrane lining | ||
• | Supply of the refractory brick lining components including bricks, mortar, and ceramic paper if required | ||
• | Supply of oxygen xxxxxxx blinds A & B; vent blind, and feed dip pipes as detailed on the drawings | ||
• | Supply of the titanium internals as detailed on the drawings | ||
• | Supply of power and water for construction purposes; | ||
• | Supply of diesel fuel; | ||
• | Provision of on-site accommodation and messing arrangements; |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 10/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
• | Provision of bus transport from the accommodation village to the Work site at the start of the shift and return at the end of the shift. |
8.4 | ATTACHMENTS | |
All material, equipment, and services to be furnished by the Contractor shall conform with the requirements of all Applicable Laws, to the specification and relevant drawings, and to the latest edition of the relevant LGL Technical specifications, technical Association Standards, and all other relevant publications and regulations and they shall form part of this Contract. | ||
The following information is attached as Volume 3C to the Contract Documentation and shall be read as part of this scope of work: | ||
8.4.1 | LGL Technical Specifications | |
The following LGL Technical Specifications shall be applicable to the Work: |
• | General reference documentation: |
Specification Number | Rev | Title | ||
None Included |
In the case of a conflict between the requirements of the Technical Specifications and those of the listed referenced Standards, the requirements of the most stringent specification shall prevail. | ||
If there is a question as to whether any material, product, or system is in conformance with applicable Standards, then the Contractor shall pay the costs associated with any testing or certification to demonstrate conformance. | ||
Any reference to “Engineer” or “Consultant” contained within the LGL Technical Specifications shall have the meaning of LGL. | ||
The Technical Specifications are contained in Section 13. | ||
8.4.2 | Contract Drawings | |
The materials, equipment, and services furnished shall be in accordance with the drawings nominated as Contract Drawings, listed below. By this reference they shall form part of the Specification. |
SCOPE OF WORK | Section 8 | |
WORK PACKAGE MOPU-0035 | Page 11/11 | |
INSTALLATION OF AUTOCLAVE INTERNAL EQUIPMENT |
8.4.3 | Volume 3C | |
The drawings referred to in clause 8.4.2 form an attachment to this documentation and shall be referred to as Volume 3C. |
TENDER CONDITIONS OF PARTICULAR APPLICATION
WORK PACKAGE
MOPU-0035 AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
Section 9 |
9.1 | Introduction |
|||
9.2 | Contract Key Dates |
|||
9.3 | Contract Currency |
|||
9.4 | Components of Tender Price — Tender Form 10/A |
|||
9.5 | Site Travel |
|||
9.6 | Post Tender / Pre-Award Meeting |
|||
9.7 | Enquiries During Tender Period |
TENDER CONDITIONS OF PARTICULAR APPLICATION | Section 9 | |
WORK PACKAGE MOPU-0035 | Page 1 / 4 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
9.1 | INTRODUCTION | |
This section sets out the Special Conditions of Particular application to the Tender that are of special application to the Work Package and to the extent, if any, that these Conditions may be inconsistent with the conditions of Tendering set out in Sections 2 and 3 of Volume IB, these conditions shall take precedence over those conditions. | ||
9.2 | CONTRACT KEY DATES | |
9.2.1 | The following Contract Key Dates shall apply to this Contract: |
Activity | Week | Contract Key Date | ||||||
Contract Award |
0 | 5 Dec 2008 | ||||||
Autoclave installed on-Site ready for installation of internal equipment |
75 | 14 May 2009 | ||||||
Personnel mobilised to Site |
75 | 14 May 2009 | ||||||
Corrosion Resistant Membrane Lining & Refractory Lining and all built-in
equipment installation complete |
85 | 22 July 2009 | ||||||
Curing & installation of miscellaneous equipment |
88 | 12 August 2009 | ||||||
Demobilisation |
88 | 12 August 2009 |
9.3 | CONTRACT CURRENCY | |
The Tenderer shall price its Tender in its native currency, then in United States Dollars (USD) detailing the exchange rate it has assumed. The last line item on Tender form 10/A requests the Tenderer to nominate the cost of fixing the Tendered lump sums and rates into USD. | ||
9.4 | COMPONENTS OF TENDER PRICE TENDER FORM 10/A | |
9.4.1 | This Contract shall be Lump Sum Contract in accordance with Clause 2.4, not subject to escalation during the Contract Period as extended by LGL. The Contractor shall submit lump sums for the units of Work set out in Appendix 10/A hereto and include any additional Lump Sum items for which it will require payment. | |
9.4.2 | Mobilisation — Lump Sum | |
All costs associated with the following shall be included in the item in Tender Form 10/A referred to as “Mobilisation”: |
a) | all transport of Contractor’s construction plant, small tools, consumable products and other temporary materials necessary to carry out the Work from the point of origin to the Site; | ||
b) | all crating, packaging, and loading of materials, plant, etc., at their point of origin; | ||
c) | all uncrating and unpacking, set-up and commissioning of all materials and plant, etc., on Site; | ||
d) | all transport costs, wages, and salaries of personnel being mobilised to Site; | ||
e) | all Contractor overheads applicable to items a to d shall be included in this item. |
Demobilisation — Lump Sum |
TENDER CONDITIONS OF PARTICULAR APPLICATION | Section 9 | |
WORK PACKAGE MOPU-0035 | Page 2 / 4 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
All costs associated with the following shall be included in the item in Tender Form 10/A referred to as “Demobilisation: |
a) | all dismantling, crating, packing on Site, and transport of Contractor’s construction plant, small tools, consumable products, and other temporary materials from the Site to the point of origin. | ||
b) | All transport costs, wages, and salaries of personnel being demobilised from Site; | ||
c) | All Contractor overheads applicable to items a and b shall be included in this item. |
9.4.4 | Insurance | |
The cost of the Contractor providing the insurance detailed in Volume
3A clause 6.17 shall be detailed on Tender form 10/A. |
||
9.4.5 | All Other Items — Lump Sums | |
All other items are self explanatory. The Contractor shall include all costs in each Lump Sum associated with the identifiable item of Work including transportation of permanent materials for inclusion into the Work from the point of origin to the Site, overheads, and profits. | ||
9.5 | SITE TRAVEL | |
Tenderers shall include an allowance for travel on Site, particularly from the nominated campsite to the Site of Work which could be a distance of up to 15 kilometres and could take up to one half hour travel time one way. LGL will provide bussing for Contractors’ personnel. Tenderer shall nominate the number of personnel to be transported at the beginning and end of each shift. | ||
9.6 | POST TENDER / PRE AWARD MEETING | |
Should LGL require the Tenderer to attend a Post Tender / Pre Award Meeting pursuant to Clause 2.10, the Tenderer shall make all adequate arrangements at its own cost, to attend the meeting. This meeting will be held in LGL’s Lihir Site Office or LGL’s Brisbane Office at the date and time nominated by LGL. | ||
9.7 | ENQUIRIES DURING TENDER PERIOD | |
All enquiries during the Tender Period should be made in writing to: | ||
Contracts Engineer- Lihir MOPU Project |
APPENDICES TO TENDER CONDITIONS OF PARTICULAR APPLICATION | Section 10 | |
WORK PACKAGE MOPU-0035 | ||
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
Appendix 10/A | Components of Tender Price |
|
Appendix 10/B | Schedule of Rates (3 pages) |
|
Appendix 10/C | Tender Schedule |
|
Appendix 10/D | Projected Weekly Manpower |
COMPONENTS OF TENDER PRICE — APPENDIX 10/A Work Package MOPU-0035 Submitted 16 June 2009 Tender For Autoclave Internal Equipment Installation, Lihir Island Tenderer Xxxx Australia Pty Ltd, Xxxx Knight Division Proposal Number: ###-##-#### A4 Rev 4.1 The total Tender Price as shown on the Tender Form (Appendix 3/C) shall be broken out into its constituent parts on this form Cost Provisional Unit Currency Total Total Item No Code Description Unit Quantity Rate Total Conversion (USD) (AUD) 1 Mobilisation LS Included Included 2 Demobilisation LS Included Included 3 Site Superintendence LS Included Included 4 Accommodation No 5,040 Man-Days Quantity Only Quantity Only 5 6 Project Insurance LS Included Included Surface Preparation of 7 Steel Substrate LS NOT INCLUDED Install Corrosion 8 Resistant Membrane LS NOT INCLUDED Install Refractory Lining including built-in items of 9 equity LS Install all other 10 items of equipment LS 11 Fee for fixing currency LS split currencies, none applicable NA NA The progress claim procedures must follow the above breakdown for consideration of payment by LGL. Progress Payment Schedule to be agreed, Xxxx Australia4 March offer proposes: Tenderer’s Proposed Terms of Payment now: with order; when brick installation begins when lining installation completes; via monthly xxxxxxxx as installation work proceeds. Progress Claims to follow LGL Procedures Signature of Tenderer: MANAGING DIRECTOR, XXXX AUSTRALIA Dated this 16TH DAY OF JUNE 2009 Signature of Witness: Name of Witness: BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA Address of Witness: Components of Tender Price — Appendix 10/A Page 1/6 | |
Page 1/6
LGL MOPU PROJECT TENDER FOR: AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION SCHEDULE OF RATES WORK PACKAGE No: MOPU-0035 TENDER FORM 10/B TENDERER: Xxxx Australia Pty Ltd. Xxxx Xxxxxx Division SHEET 1 OF 3 ###-##-#### A4 Rev 4.1 16 June 2009 Tenderers shall submit all inclusive Unit Rates for units of Work listed hereunder. The value of any Variations and Dayworks ordered shall be determined by applying these rates to the units of Work executed. For further requirements, refer Vol I, Clauses 4.2.7 “Variations” and 4.2.8 “Dayworks”. The unit rates applicable thereto shall be inclusive of all labour bases on 84 hrs/week, materials, plant and equipment, transport and freight, accommodation, industrial overheads, small tools, and all “on-costs” (including site superintendents, site administration, head office administration, drafting costs and profit. Page 1 of 1 MATERIAL ERECT/LABOUR TOTAL TENDERED ITEM DESCRIPTION UNIT COST PER UNIT COST PER UNIT LUMP SUM USD, AUD 1 Site Holiday Shutdown LS 2 Demobilization in LS case of cancellation 3 Mobile Dust Each Prices good for order placed Collector — Negative before 1 Sept 2010 Air Unit (See Note A Below) 4 Environmental Each Prices good for order placed Control AC Unit (See before 1 Sept 2010 Note B Below) 5 6 7 NOTE A: Mobile Dust Collector: 1 Unit Required 8 NOTE B: Environmental Control AC Unit: 3 Units Required 9 10 11 12 13 14 15 16 17 18 19 20 TOTAL MOPU-0035 These rates shall provide for the execution of additional Works without impact on the Contract Construction Schedule. Signature of Witness Signature of Tenderer MANAGING DIRECTOR, Name of Witness BUSINESS DIRECTOR, XX XXXX KNIGHT DIVISION XXXX AUSTRALIA Dated this 16TH DAY OF JUNE 2009 Address of Witness |
LGL MOPU PROJECT TENDER FOR: AUTOCLAVE INTERNAL EQUIPMENT INSTALATION SCHEDULE OF RATES WORK PACKAGE No: MOPU-0035 TENDER FORM 10/B SHEET 2 OF 3 TENDERER: Xxxx Australia Ptv Ltd. Xxxx Xxxxxx Division Submitted 16 June 2009 692-Ofl-5893 A4 Rev 4-1 Tenderers shall list hereunder all classes of Labour (including Leading Hands and Foremen) to be engaged on the Works (but excluding superintendents and administrative personnel). The hourly rates applicable thereto shall be based on 84 hrs/week and be inclusive of all costs including transport, accommodation, industrial overheads, small tools and all “on-costs” (including site superintendents, site administration, head office administration, overheads at Page 1 of 1 ITEM LABOUR DESCRIPTION TENDERED DAILY RATES 1 Average Daily Rates, 12 Hours Days — Day Work Only $2 Including Standard Safty Gear (PPE) and Small Tools $3 York Supervisor $4 York Lead Hand $5 York Bricklaver $6 York L/H Ref Asst $7 York Fork Driver $8 York Ref Asst $9 $10 Xxxx Knight Supervisortlnspector These rates shall provide for the execution of additional Works without impact on the Contract Construction Schedule. Signature of Tenderer Signature of Witness MANAGING DIRECTOR, XXXX AUSTRALIA Name of Witness BUSINESS DIRECTOR, XXXX KNIGHT DIVISION XXXX AUSTRALIA Dated this 16TH DAY OF JUNE 2009 Address of Witness |
LGL MOPU PROJECT TEMDER FOR: AUTOCLAVE INTERNAL EQUIPMEDNT INSTALLATION SCHEDULE OF RATES WORK PACKAGE No: MOPU-0035 •“TENDER FORM 10/B SHEET 3.OF 3 TENDERER Xxxx-Austratla Pty Ltd. Xxxx Xxxxxx Division Submitted 16 June 2009 ###-##-#### A4 Rev 4-1 Tenderers shall list hereunder all items of Plant and Equipment to be utilised on the Works and the hourly rates applicable thereto inclusive of all costs including operators (if applicable), accomodation, transport, fuel, maintenance, consumables and all “on-costs” (including Company overheads, administration and profit). The rates shall be based upon operating hours worked only and exclude time for maintenance, standby (unless directed by LGL) and fuelling. Page 1 of 1 ITEM ITEM OF PLANT OR:EQUIPMENT YEAR MAKE MODEL. CAPACITY HOURLY RATE DAILY (10 HRS) WEEKLY (70 HRS) MONTHLY (250 HRS) HOURLY (OVER 250) EST FUEL CONSUMPTION (LITRES/HR) • Coast 1 Bricksaw 2008 Clipper 18"/14” 415V N/A 2 Bricksaw Blades 3 Festo Mixer 2008 Protool MXP 1602 N/A 4 HobartMixer 2006 Hobart D 300 T N/A 5 Brout Pump N/A 6 Distribution Board N/A 7 Air Blowers & Ducting Bluw Wizard N/A 8 Gravity Rollers N/A 9 Grinder 5” Air Power N/A 10 Grinding Cups 11 Site Container N/A 12 Materials Hoist N/A 13 Lights (each) N/A 14 Globes 15 Standard Safety Gear (PPE) each man Included in Daily Rates shown on Form 10BSH2 N/A 16 Small Tools N/A 17 Power Leads N/A 19 20 21 These rates shall provide for the execution of additional Works without impact on the Contract Construction Schedule. Signature of Tenderer: Signature of Witness managing director, xxxx australia Name of WItness BUSINESS DIRECTOR, XXXX XXXXXX DIVISION XXXX AUSTRALIA Dated this 16tHlSA* Of JUNE 2009 Address of Witness |
UPROJECTPERSCHEDULE-TENDERFORM10/Cofthis16THDAYOFJUNE2009TENDERFOR:WORKPACKAGENo:TENDERERAUTOCLAVEIN TERNALEQUIPMENTINSTALLATIONMOPU-0035KochAustraliaPtyLtd.KochKnightDivision ###-##-####A4Rev41Page1of1loirACTIVITYWeekNo.12345GTftDtDJlIS13Id15IS1718192dWeekBeginingGENERAL’_[_ \"\ff|ITI”|]J’|"\\\JJ\j1~Y34Properte-QuartyyControlPlanandSubit|uLGLFora *Uflbtli^flEqui(mn]/LU^pjjih SL-pniiiD^;f^t-itm"*\MruhirONsiteWOrK67Seti-upstateIVfUtri-triH*,t’lX-L-,.i,nrl.flJ^n-J-prii-,irgr-r tnu^’iablurfKoPnpnttonofStMlSub«n uDetailedKochKnightscheduleisattachedtothe12Juneoffer,andabarchartsent—.—.-separately.Thisformleft inplacefordirectiontotheKnightbarchart’anHattatiofir rCnrtoiH)r.R«nt«nlMamtrt-wt0Cureln(CniffJtJqtrRtaiv’jilMflTTbrgng11Prgic^iHBCurrutitnfttntlftrtiVnmh farie2nitiBSlpCnrM11MHttacfcryLtrunrjITn«*fliT*l%DfllMCflmnnlilVftfi?W;tlh-T;;f;:::nnriltuwnflJiK r Ai|’g-^nvtl^cmahT!:CU^rhoflfl!ractoryu i:ng_..tt;;^nn^p•P?aa.cnlCompktwnT3ewhi[jiAl£nrtTTKo r orOrk-SifaPGiMnnnl-STAFFMa.0rCivSi10FijAftrsnc|.31RiECT\.ASQU*.ThtTenderershalfincorporateanCortfmdK ftyDateslisledinClause9.2“ContractKeyDates“intheTenderSchedule.IftheTendererconsidersthatInsufficien tactivitiesarelistedthenitshouldinsertadditionalitemsasitrequires.ShowKeyDates|SignatureofTendererSi gnatureofVUilnessNameoFWrtness;AddressofWitness |
PROJECTED WEEKLY MANPOWER TENDER FOR: AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION APPENDIX 10D Submitted 16 June 2009 WORK PACKAGE # MOPU-0035 The Total Manpower levels for both STAFF and DIRECT LABOUR shown below must be the same as those listed on Tender Form 10/C (Tender Schedule) TENDERER: Xxxx Australia Ptv Ltd, Xxxx Knight Division ###-##-#### A4 Rev 4.1 ON A WEEKLY BASIS Total MANPOWER 1 2 3 4 5 6 7 8 9 10 11 1.2. 13 14 15 16 17 18 19 20 Manpower Staff 36 Max. 36 Max. 36 Max, 36 Max. 36 Max. 36 Max. 36 Max 33 Max 36 Max 36 Max 36 Max 36 Max 36 Max 36 Max 36 Max 36 Max 36 Max 36 Max 36 Max 36 Max. 36 Maximum Xxxxxxx Tradesmen Labourers Other (Tenderer to Nominate) Detailed Xxxx Knight schedule is attached to the 12 June 2009 offer, to be revised per LGL schedule to be updated. Site manpower and accommodation will be at maximum 36 people in the last 20 weeks of the contract, during brick lining installation. TOTAL MANPOWER 36 36 i 36 36 36 36 36 36. 36 36 36 36 : 36 36 36 36 36 36 36 36 MAXIMUM ACCOMMODATION Total Free Issue Accommodation Person-Days Number of Rooms Required at LGL Camp 36 36 36 36 36 36 36 36 36 36 36 36 36 36 36 36 36 36 36 36 5,040 Man-Days The work roster the Tenderer proposes to use as per Clause 9.4.4 is 12 hr days, 13 days per fortnight Signature of Witness: Signature of Tenderer Name of Witness BUSINESS DIRECTOR, XXXX MANAGING DIRECTOR, XXXX AUSTRALIA KNIGHT DIVISION XXXX AUSTRALIA Dated this 16TH DAY OF JUNE 2009 Address of Witness Page 6 of 6 |
Page 6 of 6
11.1 | Introduction |
|||
11.2 | Advertising |
|||
11.3 | Site Facilities |
|||
11.4 | Personnel Instruction and Training |
|||
11.5 | Handling of LGL Supplied Materials or Equipment |
|||
11.6 | Project Reporting Requirements |
|||
11.7 | Special Conditions |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 1 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
11.1 | INTRODUCTION | |
11.1.1 | This Section sets out the special terms and conditions of Contract which have particular application to this Contract and to the extent, if any, that they may be inconsistent with the General or Special Conditions of Contract, these terms and conditions shall take precedence. | |
11.2 | ADVERTISING | |
11.2.1 | The Contractor shall not in any manner advertise, publish or release for general information, any statement mentioning LGL or the MOPU Project, without first obtaining the written consent of LGL, including LGL’s approval of the material requested to be advertised, published, or released for general information. The Contractor shall use its best efforts to ensure that its employees, offices, agents, representatives, Subcontractors, vendors, and suppliers abide by this restriction. | |
11.3 | SITE FACILITIES | |
11.3.1 | The Contractor’s site facilities shall be kept clean and tidy and maintained in good conditions at all times during the Works. | |
11.3.2 | The Contractor shall adhere to LGL’s environmental policy by ensuring that all hydrocarbon product storage areas within its site facilities are bunded and lined with HDPE liner. | |
11.4 | PERSONNEL INSTRUCTION AND TRAINING | |
11.4.1 | The Contractor’s employees and Subcontractors shall be adequately trained, instructed, tested, and certified in the operation of plant and equipment, or carrying out tasks, required by their class of work. | |
11.4.2 | The Contractor shall issue to each operator a LGL site Operator’s Permit to operate specific mobile equipment upon satisfactory completion of an on-site test of competency. A copy of all permits shall be forwarded to LGL. | |
11.4.3 | The Contractor shall implement an instruction and training program for all operators of plant and equipment on site. These programs shall be submitted to LGL for approval. | |
11.4.4 | LGL may direct the Contractor to modify aspects of its instruction and training programs at any time during the Contract if, in its opinion, it does not adequately meet the requirements of safe operation of plant and equipment, or safe operating practices on the site. | |
11.4.5 | The Contractor shall maintain a register on site of the induction, training, authorization, and licences that each employee and Subcontractor has received. The register shall be made available to LGL upon request. | |
11.4.6 | The Contractor’s employees and Subcontractors shall adopt and actively participate in LGL’s Safety Management System. |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 2 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
11.5 | HANDLING OF LGL SUPPLIED MATERIALS OR EQUIPMENT | |
11.5.1 | The Contractor shall be fully responsible for any damage to LGL supplied materials or equipment caused by mishandling, improper storage, or failure to follow the manufacturer’s recommendations and/or accepted practices. | |
11.5.2 | Any damage or loss to LGL supplied materials or equipment, resulting from the Contractor’s actions shall be the sole liability of the Contractor. | |
11.6 | PROJECT REPORTING REQUIREMENTS | |
11.6.1 | General | |
11.6.1.1 | The Contractor shall prepare and submit to LGL daily, weekly, and monthly reports. All reports shall be in a format acceptable to LGL. | |
11.6.1.2 | LGL may direct that additional information, forms, or reports be completed as deemed necessary and appropriate for the performance and control of the Works, and such information shall be provided by the Contractor at no additional cost to LGL. | |
11.6.1.3 | All reports shall be signed by the Contractor upon submission, and by LGL as evidence of receipt only of the report, not necessarily acceptance of the details and accuracy of the report. | |
11.6.1.4 | The Contractor shall provide3, on the request of LGL, monthly consumables usage figures for, but not limited to lubricants and chemicals used during the Works. | |
11.6.2 | Daily Reports | |
11.6.2.1 | The daily production report must be submitted to LGL at the time designated by the Area Manager. The report shall be an Excel spreadsheet and submitted to the Area Manager electronically. | |
11.6.2.2 | The Contractor shall keep records of all reports both electronically and hard-copy. | |
11.6.2.3 | The daily reports shall address, as a minimum, the following listed topics with regards to the previous twenty-four (24) hour period: |
• | Any safety or industrial relations incidents involving the Contractor’s or Subcontractor’s employees. | ||
• | All Works undertaken during the preceding twenty-four (24) hour period | ||
• | Progress of the Works compared to the Schedule | ||
• | Manpower on-site and hours worked | ||
• | Details of any damage to the Contractor’s or LGL’s materials, plant, equipment or facilities | ||
• | Mechanical availability of each item of the Contractor’s plant and equipment | ||
• | Hours of work performed by each item of equipment and type of work it performed | ||
• | Downtime hours of each item of plant and the cause of the downtime Status of any Variation aughorised by LGL |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 3 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
• | Any problem or potential problem area(a) | ||
• | Any other activity or event that has or may impact on the timely and satisfactory performance and completion of the Contract |
11.6.3 | Weekly and Monthly Reports | |
11.6.3.1 | Weekly and monthly reports shall include a summary of information supplied in daily reports and detailed status reports on the overall performance of the Works. | |
11.6.3.2 | The reports shall be submitted within a time period following the end of the week or month as directed by the Area Manager. | |
11.7 | SPECIAL CONDITIONS | |
11.7.1 | Inspection and Provision of Insurance Policies | |
11.7.1.1 | Amend clause 4.1.7.5 by adding the following words after the first paragraph. “For the avoidance of doubt, the parties agree that the Contractor’s liability is limited as provided in clause 11.7.24, and as otherwise provided in the Contract”. | |
11.7.2 | Security | |
11.7.2.1 | Delete existing Clause 4.1.6.1, and replace with “The Contractor shall provide two forms of security, each equal to of the Contract Sum for the purpose of ensuring the due and proper performance of the Contract and of satisfying the obligations of the Contractor under the Contract. LGL may recover all debts due and owing from the Contractor to LGL from the security if not otherwise paid by or recovered from the Contractor. The security shall be in the form of an Unconditional Bank Guarantee in the form as agreed between the Contractor and LGL, as detailed in Section 12.” | |
11.7.2.2 | Amend Clause 4.1.6.2 by replacing the words “14 days” with “30 days”. | |
11.7.3 | Progress Claims and Payments | |
11.7.3.1 | Amend Clause 4.2.6.7, by deleting subclause ii), and subclause iii). | |
11.7.3.2 | Amend clause 4.2.6.1, by adding the words “in accordance with the milestone payments detailed in clause 11.7.31”, to the end of clause 4.2.6.1. | |
11.7.3.3 | Amend clause 4.2.6.10 by adding the following paragraph to the existing clause: “Contractor shall have the right to suspend performance of the Contract from seven (7) days of the date of such notice until payment is made. The Proposed Project Schedule shall be extended by the period of the suspension for non-payment.” | |
11.7.4 | Variations | |
11.7.4.1 | Amend clause 4.2.7.7 by replacing the existing words with the following wording: | |
“If the Contractor and LGL do not agree upon the value of the Variation, LGL may have the Variation executed by others. The work of the Contractor in this area will resume on completion of the Variation work. The Contractor provides no warranty for the Variation Work provided by others. The Contractor shall not be entitled to claim from LGL any cost or Contract Value for this Variation Work supplied by others.” |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 4 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
11.7.5 | Goods or Services Provided by LGL | |
11.7.5.1 | Delete clause 4.2.10 in its entirety. | |
11.7.6 | Completion | |
11.7.6.1 | New Special Conditions: Deed of Release Appendix 5/0 modified as agreed between parties on 10lh June, 2009 and as referenced in Section 12. | |
11.7.7 | Materials, Workmanship, and Quality Control | |
11.7.7.1 | Amend Clause 4.3.2.5 by adding after the words “5 days”, “(prior to issue of certificate of practical completion), or within 30 days (within DLP)”. | |
11.7.7.2 | Amend clause 4.3.2.5 be deleting the last sentence, “If the Contractor fails to comply with any direction given by LGL pursuant to this Clause, LGL may carry out the replacement, correction or removal and the cost incurred shall be a debt due from the Contractor to LGL.” | |
11.7.7.3 | Delete clause 4.3.2.6 in its entirety. | |
11.7.8 | Occupational Health and Safety | |
11.7.8.1 | Amend clause 4.3.6.4 by deleting the word “solely” from sub clause g). | |
11.7.8.2 | Amend clause 4.3.6.6 by adding the word “reasonable” before the word “direction” in the last sentence. | |
11.7.9 | Protection of Persons, Property and Existing Services | |
11.7.9.1 | Delete clause 4.3.7.1 in its entirety, and replace with the following: | |
“Light sets will be provided by the contractor for use inside of the Autoclave. Power and associated cabling to the Contractors distribution box for such lighting equipment will be provided by LGL.” | ||
11.7.10 | Care of the Work | |
11.7.10.1 | Amend clause 4.3.8.1 by deleting the words “expiration of the Defects Liability Period” and replacing with “issue of the Certificate of Practical Completion”. | |
11.7.10.2 | Clause 4.3.8.2 is deleted and replaced with “The Contractor shall at its own cost make good to the satisfaction of LGL any loss of or damage to the Work, the temporary Works, materials and Constructional Plant resulting from the negligence of the Contractor, its employees, agents or Subcontractors (save and except the Excepted Risks as defined in clause 4.3.8.3) when such making good is necessary for the satisfactory completion of the Work. When so ordered by LGL any such loss or damage caused by any of the Excepted Risks shall be made good by the Contract as a Variation to the Contract”. | |
11.7.10.3 | Amend clause 4.3.8.3 by adding new subclause iv) as follows: | |
“iv) Contractor and/or LGL will be excused from their respective obligations in the event and to the extent that their respective performance is delayed or prevented (a) by any circumstance (except financial) reasonably beyond their control or (b) by fire, explosion, breakdown of machinery or equipment, plant shutdown, strikes or other labour disputes, riots or other civil disturbances, or voluntary or involuntary compliance with any law, order, regulation, recommendation or request of any governmental authority.” |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 5 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
11.7.11 | Environmental Responsibilities | |
11.7.11.1 | Amend clause 4.3.10.5, subclause iv), by inserting the words “of its” before the words “Subcontractors and shall ensure...” and before the words “Subcontractors complies with the provisions...”. | |
11.7.12 | General Contractor Warranties | |
11.7.12.1 | Amend clause 4.3.11.1, subclause v)(C), by replacing clause with the following: | |
“(C) obtain all necessary government authorisations required for the Contractor and its subcontractors to carry on a business within PNG and all required PNG work permits and visas for its expatriate employees;” | ||
11.7.13 | Defects | |
11.7.13.1 | Amend clause 4.4.1.3 by deleting the words, “But no such direction shall be given by LGL later than twenty-eight (28) days after the expiration of the Defects Liability Period.” | |
11.7.13.2 | Amend clause 4.4.1.4 be replacing the clause with the following words: | |
“If any rectification referred to in Clauses 4.4.1.2 or 4.4.1.3 is not commenced or completed within 5days (prior to issue of certificate of practical completion), or within 30 days (within DLP), LGL may carry out the rectification at the Contractor’s expense but without prejudice to any other rights that LGL may have against the Contractor in respect of the rectification. The cost incurred by LGL in so carrying out the rectification shall be a debt due from the Contractor to LGL. Notwithstanding the provisions of this Clause, the Contractor shall not be responsible for the effects of fair wear and tear during the Defects Liability Period, nor will it be responsible for warranty on work carried out by others.” | ||
11.7.13.3 | Delete clause 4.4.1.5 in its entirety. | |
11.7.13.4 | Amend clause 4.4.1.6 by deleting the words “or making tests”. | |
11.7.14 | Royalties, Patents, Copyrights and Other Intellectual Property Rights | |
11.7.14.1 | Delete clause 4.4.2.1 in its entirety. | |
11.7.14.2 | Amend clause 4.4.2.2 by deleting the words “and its directors, officers, employees, agents and consultants”. Insert the following new paragraph: | |
“Additionally, this indemnification does not apply to any liability for infringement (i) of any method patent where the equipment is used with other apparatus for carrying out a process resulting in a combination of elements which is deemed to infringe a method patent or patent directed to a combination of elements, (ii) the equipment is modified by LGL without the prior written approval of the Contractor, or (iii) the equipment is used by LGL in a manner different than the use communicated to and understood by the Contractor at the time the equipment was sold to LGL (under a separate equipment supply purchase order) and such use constitutes infringement.” | ||
11.7.14.3 | Amend clause 4.4.2.3 to read: | |
“Title to, copyright in and other intellectual property rights in any documents, plans, specifications, designs, drawings, sketches, reports and materials produced for or in connection with the Works vests in the Contractor and the Contractor grants to LGL an irrevocable royalty free, non-exclusive licence to use that material in connection with the Works for the life of the LGL Mine.” |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 6 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
11.7.15 | Accident or Injury to Employees and Property Damage and Public Risk | |
11.7.15.1 | Delete clauses 4.4.3 and 4.4.4 in their entirety. | |
11.7.16 | Construction of the Contract | |
11.7.16.1 | Amend clause 4.5.1.5 by deleting the words “whether” and “or otherwise, then adding the following words at the end of the clause: “The parties agree that the U.N. Convention on Contracts for the International Sale of Goods (CISG) will not apply to this agreement.” | |
11.7.17 | Documents | |
11.7.17.1 | Amend clause 4.5.3.5 by adding the words “provided, however, that Contractor may retain one complete copy thereof in its legal archives in order to determine its rights and obligations hereunder.” to the last sentence. | |
11.7.18 | LGL’s Right to Terminate the Contract | |
11.7.18.1 | Replace Clause 4.5.5.1, sub clause i) with: | |
“i) FOR LUMP SUM ITEMS: The Engineering Manager and Contractor shall determine and agree the percentage completion of such items up to the time of the termination of the Contract and the Contractor shall be paid the percentage so determined of the value of the Lump Sum items.” | ||
11.7.18.2 | Replace Clause 4.5.5.1, sub clause ii) with: | |
“ii) FOR UNIT PRICE ITEMS: The Engineering Manager and Contractor shall determine and agree the number of items completed up to the time of the termination of the Contract and they Contractor shall be paid for the number of items so determined at the unit prices listed in the Contract.” | ||
11.7.18.3 | Replace clause 4.5.5.1, sub clause iii) with: | |
“iii) DEMOBILIZATION: The Contractor shall be paid to fully compensate the Contractor for moving its, employees, equipment, tools, supplies and materials off the Site.” | ||
11.7.19 | Disputes | |
11.7.19.1 | Amend clause 4.5.6.3 by deleting the words “the jurisdiction stated in Clause 1.8 (total Project Data)” and replacing with the words “Brisbane, Queensland” | |
11.7.20 | Definitions and Interpretations | |
11.7.20.1 | Amend the definition of “Contractor” in clause 4.5.9.1 by deleting the words “that person’s heirs, executors, administrators and permitted assigns, and in the case of a corporate body, its successors and permitted assigns” and replacing with “its successors and permitted assigns.” | |
11.7.20.2 | Amend the definition of “Practical Completion” in clause 4.5.9.1 by deleting the words “in the opinion of the Engineering Manager”. | |
11.7.20.3 | Amend the definition of “Standards” in clause 4.5.9.1 by deleting the words “or if no relevant standard is specified, the standard published by the International Standards Organization (ISO) or if no relevant ISO standard exists, the standard published by |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 7 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
the standards organization for the country in which the Work is performed.” and replacing with the words “including the Contractor’s and Sub-contractors Quality plans.”. | ||
11.7.21 | Export Compliance | |
11.7.21.1 | “LGL shall, to the extent that it is legally required to do so, comply with all applicable export and re-export control laws and regulations, including without limitation the Export Administration Regulations (15 C.F.R. Parts 730 et se.) maintained by the United States Department of Commerce and the Office of Foreign Assets Control Regulations (31 C.F.R. Chapter V) of the U.S. Treasury Department. Specifically, LGL shall not — directly or indirectly — sell, export, re-export, transfer, provide, divert, loan, lease, consign, or otherwise dispose of any goods, services, software, source code, or technology received in connection with this transaction and covered by this Agreement to any person, entity, or destination prohibited by the laws or regulations of the United States, without obtaining prior authorisation from the competent government authorities as required by those laws and regulations.” | |
11.7.22 | Contractors Limited Warranty — Workmanship Guarantee |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 8 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
11.7.23 | Contractors Indemnification |
11.7.24 | Limitation of Liability | |
11.7.24.1 | Limitation on LGL’s Liability |
(a) The total liability of LGL arising out of or in connection with the Contract including a claim in tort, under statute, for rectification or frustration or like claim available under the law governing the Contract is limited to the Contract Sum as adjusted pursuant to the Contract. | |||
(b) | The limitation of liability under clause 11.7.24.1 (a) shall not apply to: |
(i) | loss arising through fraud or Wilful Misconduct by LGL; | ||
(ii) | liability for infringement of any third party intellectual property rights; | ||
(iii) | the extent that liability is otherwise limited by another provision of the Contract; and | ||
(iv) | liability out of which by law LGL cannot contract. |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 9 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
11.7.24.2 | Limitation on the Contractor’s Liability |
(i) | in the case of the Works, at the Contractor’s option: |
(A) | the replacement of the Works or the supply of equivalent Works; | ||
(B) | the repair of the Works; | ||
(C) | the payment of the cost of replacing the Works or of acquiring equivalent Works; or | ||
(D) | payment for having the Works repaired, and |
(ii) | in the case of services, at the Contractor’s option: |
(A) | the supply of the Works again; or |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 10 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
(B) | the payment of the cost of having the Works supplied again. |
(d) | The limitation of liability under clause 11.7.24.2(a) shall not apply to: |
(i) | loss arising through fraud or Wilful Misconduct by the Contractor; | ||
(ii) | liability for infringement of any third party intellectual property rights; | ||
(iii) | the extent that liability is otherwise limited by another provision of the Contract; and | ||
(iv) | liability out of which by law the Contractor cannot contract. |
11.7.24.3 | General provisions |
11.7.25 | Travel to Site | |
11.7.25.1 | Amend clause 6.5.2 by deleting the word “Lihir” and replacing with Cairns. LGL will arrange and pay for transportation from Cairns to Lihir Island and return to Cairns. | |
11.7.25.2 | For MOPU-0063, this clause needs to be modified: Change title to “Contractor Travel”, delete 1st paragraph, 2nd paragraph — replace “Lihir” with the Work site, which is located at Melaka, Malaysia. | |
11.7.26 | Power | |
11.7.26.1 | Amend clause 6.7.1 by deleting the words “The Contractor shall be provide all necessary construction power.” and replace with the words “LGL will provide 3Phase 440-480V 100A power supply, wired directly to the Contractors panel box. Three connection points will be allowed. Local distribution from the panel boxes by the Contractor.” | |
11.7.27 | Communications | |
11.7.27.1 | Amend clause 6.8.1 by deleting the words “Telephone and facsimile services are available in limited supply at the Mine for use by the Contractor. Contractors who use LGL facsimiles and telephones shall have all costs accrued, deducted from |
SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 11 | |
WORK PACKAGE MOPU-0035 | Page 11 / 11 | |
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
payments due or otherwise recovered as a debt due,” And replacing with the words “LGL to provide the Contractor with one(1) telephone line and one (1) facsimile line for the duration of the Works.” | ||
11.7.28 | Potable Water | |
11.7.28.1 | Amend clause 6.9.1 by deleting the words “Limited potable water shall be available at the Site. Any other requirements and distribution of potable water shall be arranged and paid for by the Contractor.” and replacing with the words “LGL will supply the contractor with a minimum of 500 litres of Potable water per day. LGL will also provide Potable ice to fill the Contractors supplied containers. These containers to be filled with ice and potable water prior to leaving the camp each day.” | |
11.7.29 | Construction Water | |
11.7.29.1 | Amend clause 6.10.1 by deleting the words “Limited construction water will be available to the Contractor from the Londolovit xxxx. The Contractor shall provide all equipment necessary to load and haul the water to its Work site.” and replace with the words “LGL will provide a minimum of 500 litres of construction water per day. This water will be provided to 8 delivery points in the Work area.” | |
11.7.30 | Insurance arranged by the Contractor | |
11.7.30.1 | Delete clause 6.17.1.1 in its entirety. | |
11.7.30.2 | ||
11.7.30.3 | Delete clause 6.17.1.5 in its entirety. | |
11.7.30.4 | Delete clause 6.17.5, subclause (v). | |
11.7.31 | Milestone Payments | |
11.7.31.1 | Contract milestone payments to occur as follows: |
APPENDICES TO SPECIAL CONDITIONS OF PARTICULAR APPLICATION | Section 12 | |
WORK PACKAGE MOPU-0035 | ||
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
Contractor:
|
Work Package: |
Dated this
|
Day of | 200 |
1. | Statement by Lihir Gold Limited on their letterhead manually signed by a purported office of Lihir Gold Limited stating that “Xxxx Australia has failed to substantially meet it’s obligations under the terms of Lihir Gold Limited purchase order __________ dated , and this demand under Bank Guarantee No._________ is made in accordance with the terms of said purchase order. | ||
2. | A copy of your dated prior written notice to Xxxx Australia stating that “Xxxx Australia is in material breach of it’s obligations under purchase order __________ dated __________, by failing to meet the obligations of the Contract described in said purchase order and Xxxx Australia has thirty (30) days to remedy the breach.” | ||
3. | A copy of your letter to Xxxx Australia dated no less than thirty (30) days after the date of the notice in paragraph 2 above stating “under purchase order ________ dated ________, Xxxx Australia has failed to respond within the thirty (30) day period and Lihir Gold Limited plans to call the demand payment under this bank guarantee as Xxxx Australia has refused or failed to take the necessary steps to remedy the breach.” |
TECHNICAL SPECIFICATIONS | Section 13 | |
WORK PACKAGE MOPU-0035 | ||
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
GENERAL SPECIFICATIONS | Section 14 | |
WORK PACKAGE MOPU-0035 | ||
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
TOTAL PROJECT PROGRAM | Section 15 | |
WORK PACKAGE MOPU-0035 | ||
AUTOCLAVE INTERNAL EQUIPMENT INSTALLATION |
1. | Xxxx’x Quality plans | |
2. | Xxxx’x Proposal | |
3. | Minutes of Meetings | |
4. | Contract Schedule | |
5. | Xxxx Drawing “Q-1270-C Rev 1 Revised” |
REVISION:
A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 1 of 10 |
Xxxxx Xxxxxx
|
2/24/2009 | |||
NAME
|
DATE | |||
VP Engineering and Construction
|
President | Date: 3/5/09 | |||
Engineering Manager | Date: MAR-5-09 | |||
Project Manager | Date: MAR-5-09 | |||
XXXX KNIGHT LLC
REVISION: A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 2 of 10 |
1.0 | General - |
1.1 | These quality plans were prepared specifically for the project named in the title block. Customer requirements as defined in documents submitted and Xxxx Xxxxxx general practice and procedures form the core of the plan. |
2.0 | Responsibility and Authority |
2.1 | Xxxx Knight management believes that quality is a leading method of differentiating competitors in the marketplace. That’s why the management team at Xxxx Xxxxxx is actively involved in evaluating and defining the quality plans and practices employed to meet customer needs. | ||
2.2 | This “Quality Plan” is authored by the Process Improvement Manager and approved by the President and other key operations managers as defined on the cover page of this document. The president and other top management participate in a review of this and other components of the quality system at the bi-annual management review. This participation includes a review and analysis of results related to the goals and objectives contained in the plans. | ||
2.3 | Xxxx Knight designates personnel responsible for: |
2.3.1 | Management, including management of the Quality System. | ||
2.3.2 | Operations that effect product and service quality | ||
2.3.3 | Inspection, testing and verification activities that prove processes are in control and meet specified requirements. |
2.4 | All assigned personnel are properly trained to carry out required tasks properly. | ||
2.5 | Bach department that is responsible for work that effects product or service quality is responsible and authorized to control actions that directly or indirectly determine customer satisfaction. | ||
2.6 | All employees have the authority and the responsibility to stop work processes when the employee identifies a problem that could affect product or service quality. |
3.0 | Responsibilities for the Quality System: |
3.1 | President — Xxxx Xxxxxx LLC |
||
The President of Xxxx Knight is responsible for setting policy, goals and objectives for the |
XXXX KNIGHT LLC
Revision:
A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 3 of 10 |
quality system at Xxxx Xxxxxx. The President will schedule and attend the Management Review where these goals are established and reviewed on a bi-annual basis. | |||
3.2 | Business Director | ||
Business Directors are responsible for ensuring products and services provided meet the contractual needs and requirements of the customer. This includes a review of all contracts prior to acceptance. In addition the manager is required to prepare and document the service and support requirements for products as necessary, provide input design requirements, and prepare product literature. | |||
3.3 | Engineering Manager | ||
The manager in charge of Design and Development is responsible to ensure that all appropriate steps required to design a quality product which meets customer specifications are performed as necessary. This includes design reviews, verification tests, design-input analysis to customer requirements, regulatory requirement analysis, design change review and documentation, and qualification tests, all where applicable. This manager is responsible for generating, issuing and maintaining all appropriate documentation regarding the coordination and operation of the design and development function. This manager ensures that design activities are properly staffed with appropriately trained personnel. The design system is maintained to ensure that all requirements are understood, those that can be implemented are, and that the design output is measured to ensure that this in fact occurs. | |||
3.4 | Plant Manager | ||
The plant manger is in charge of manufacturing operations and is responsible for performing all necessary tasks and preparations to commence production of released products. The manager is responsible for ensuring that all required equipment is available and properly maintained, that personnel are trained as required prior to performing tasks which affect quality and that all required documents used in production are current and understood by all related personnel. Since the Plant Manager is responsible for producing products that meet customer requirements, he has full authority and responsibility to stop production of unacceptable materials. In conjunction with requirements for continual improvement, he is responsible for gathering quality data, analyzing, and taking corrective action as required. | |||
3.5 | Contract Administrator | ||
The Contract Administrator is responsible for contract and purchase order review and |
XXXX XXXXXX LLC
Recision:
A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 4 of 10 |
acceptance.The administrator ensures that contract requirements are adequately defined and documented and that we can meet the contractual requirements of the order. This will include working with the Manufacturing Scheduler/Planning personnel to define the commitment for delivery. | |||
3.6 | Construction Manager | ||
The Construction Manager is responsible for documenting and implementing a system to ensure proper installation and support of all products. These installations may be conducted in-house or at a job site, by Xxxx Knight employees or by sub-contracted installers anywhere in the world. The Construction Manager will implement control procedures for the receipt, storage, and return of materials. The Construction Manager is responsible to ensure Xxxx Xxxxxx and customer safety procedures and practices are observed at all times during an install, in-house or at a job site. The manager will insure that all required documents and reports are completed to demonstrate the safe, efficient completion of a quality installation project. The manager is responsible for reviewing the training needs of personnel, and providing training required to ensure personnel performing all tasks are appropriately trained. | |||
3.7 | Senior Project Manager | ||
The Senior Project Manager is responsible for monitoring the process during each step of the design, manufacturing, inspection, delivery and installation of the product. The Senior Project Manager is responsible for understanding all aspects of the supply requirement and coordinating all aspects to the efficient processing of products and services to the customer. This thorough understanding of the project, and real time understanding of each facet within the scope of supply, should make the Project Manager the primary customer contact during the performance of a contract. | |||
3.8 | Logistics Manager | ||
The Procurement/Logistics Manager is responsible for the shipment of materials per documented procedures and customer contract. The Procurement/Logistics Manager will have primary responsibility of the shipment from the production site to the customers designated delivery point or point of entry. The Procurement/Logistics Manager is responsible for selecting carriers and methods of packaging when not otherwise specified by the customer. | |||
3.9 | Procurement Manager and Buyer | ||
Purchasing personnel are responsible for documenting and implementing a system to ensure the |
XXXX XXXXXX LLC
REVISION:
A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 5 of 10 |
purchasing of quality materials from quality suppliers. This system includes supplier selection, purchase order generation and placement, change control, specification agreement with the supplier, data acquisition and reporting, and delivery coordination. | |||
3.10 | Process Improvement Manager | ||
The Process Improvement Manager is the site representative and is responsible for the overall quality system. This includes controlling, documenting and implementing systems affecting quality of products, services and philosophies of customer satisfaction and continual improvement. The manager is responsible for resolving differences between customer requirements and products intended for delivery. The manager is also responsible for ensuring that customer required documents such as certificates are processed per request. Additional Quality System responsibilities of the manager include establishing, implementing, and maintaining quality procedures relevant to the quality functions. Manager internal quality audit functions. Investigate, resolve and implement preventive actions in answer to quality problems within manufacturing. Report quality indicators to upper management through management review and other appropriate means. Support and promote the supplier quality process in conjunction with purchasing goals and objectives. The Process Improvement Manager and all quality managers and technicians have the authority and responsibility to stop shipment of products that have a probability of being defective or not meeting specified requirements. | |||
3.11 | Shipping and Receiving Supervisor | ||
The manager in charge of receiving is responsible for receipt inspection, handling, and control of all products and materials supplied to the company. This responsibility includes the proper identification and storage of materials used in production of manufactured products. The manager is responsible to select and maintain storage, handling and packaging controls to prevent damage and deterioration of all materials and products. As manager of shipping this supervisor is responsible for appropriate handling, packaging and shipment of products to meet customer requirements and preclude damage or deterioration in transit. | |||
3.12 | Manufacturing Scheduling/Planning Manager | ||
The Manufacturing Scheduling/Planing Manager is responsible for order scheduling and material and control functions to ensure materials and products are available to meet forecasted product demands and customer delivery requirements. |
XXXX KNIGHT LLC
REVISION:
A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 6 of 10 |
4.0 | Procedures |
4.1 | The following procedures are relevant to the work required and are attached to the Quality Plan |
4.1.1 Purchasing
|
P0740-10 | |
4.1.2 Control of Nonconforming Product
|
P0830-10 | |
4.1.3 Corrective Action Process
|
P0850-10 | |
4.1.4 Construction & Preparation of Steel Shell for Sheet Linings
|
TL-111D | |
4.1.5 Application of PYROFLEX® Sheet Lining
|
TL-117B | |
4.1.6 Acid Proof Brick Laying Procedure
|
B-100A |
5.0 | Test Methods |
5.1 | The customer has specified ASTM test methods to be used for testing of product. Xxxx Knight’s own Inspection and Test Plans also use ASTM methods as a basis and most methods specified are utilized by Xxxx Knight. Below are the methods specified and the Xxxx Xxxxxx methods that are derivatives from the specified ASTM methods specified. Where Xxxx Knight methods are called out, the method is also attached as requested. |
5.1.1 | Brick Testing |
5.1.1.1 Acid Solubility
|
WI-950 (Based ASTM C-279) | |
5.1.1.2 Brick Drawing and Physical Inspection
|
WI-234 | |
5.1.1.3 Moisture Determination of Clay Mixtures
|
WI-980 | |
5.1.1.4 Bend Test
|
WI-211 | |
5.1.1.5 Chemical Analysis of Soda Lime
|
ASTM C-169 | |
5.1.1.6 Sulfur in Ash from Coal
|
ASTM D-5016 | |
5.1.1.7 Apparent Porosity
|
ASTM C-20 | |
5.1.1.8 Liquid Absorption
|
ASTM C-20 | |
5.1.1.9 Bulk Density
|
ASTM C-20 | |
5.1.1.10 Modulus of Rupture
|
ASTM C-133 | |
5.1.1.11 Dimensions, Squareness and Warp
|
ASTM C-134 |
The following brick testing will be conducted outside Xxxx Xxxxxx laboratories at a third party testing facility. |
5.1.1.12 Modulus of Elasticity
|
ASTM C-885 |
XXXX XXXXXX LLC
REVISION: A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 7 of 10 |
5.1.1.13 Thermal Conductivity
|
ASTM C-1113 | |
5.1.1.14 Thermal Expansion Coefficient
|
ASTM E-228 | |
5.1.1.15 Crushing Strength
|
ASTM C-133 |
5.1.2 | Silicate and Litharge Mortars |
5.1.2.1 Bond Strength
|
ASTM C-321 | |
5.1.2.2 Absorption
|
ASTM C-20* | |
5.1.2.3 Working Life
|
ASTM C-414 | |
5.1.2.4 Shrinkage
|
ASTM C-531 | |
5.1.2.5 Compressive Strength
|
ASTM C-579 | |
5.1.2.6 Flexural Strength
|
ASTM C-580 |
The following mortar testing will be conducted outside Xxxx Knight laboratories at a third party testing facility |
5.1.2.7 Coefficient of Thermal Expansion
|
ASTM E-228 | |
5.1.2.8 Modulus of Elasticity
|
ASTM C-580 |
5.1.3 | Pyroflex® 500 Membrane |
5.1.3.1 Softening Point
|
WI-960 (Based on ASTM D-36) | |
5.1.3.2 Slump Test
|
WI-960 | |
5.1.3.3 Sheet Weights and Measurements
|
WI-960 | |
5.1.3.4 Bulk Density
|
WI-960 | |
5.1.3.5 Weight loss during xxxx off (Proprietary)
|
WI-700 |
6.0 | Inspection and Test Plans |
6.1 | Inspection and Test Plans (ITP’s) shall be prepared and submitted for all products manufactured at Xxxx Knight, as well as Sub-contract Suppliers. |
7.0 | Field Installation Audits |
This Specification shall pertain to the Operation and Manufacturing process of at Xxxx Xxxxxx LLC East Canton, Oh. Under no circumstances is any person allowed to alter this specification in any way unless it has been approved in writing by the Quality Assurance Supervisor and or the Technical Manager. |
XXXX KNIGHT LLC
REVISION: A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 8 of 10 |
All lining installation shall be performed by experienced and competent personnel in a safe, quality oriented and productive manner. Xxxx Xxxxxx trained personnel will perform all PYROFLEX DUPLY Lining installations per Xxxx Knight Bulletin TL- 117B APPLICATION OF PYROFLEX SHEET LINING. Xxxx Xxxxxx has sub-contracted the brick installation to York Linings Inc. under the direct supervision of a Xxxx Knight site superintendent. Site installation is part of the subject order scope of supply and Field Inspection Checklists (FIC’s) are part of the requirements of the project. In addition to the required FIC’s, daily and periodic audits and checklists will be utilized to ensure a quality installation. |
7.1 | Field Inspection Checklists |
7.1.1 | Electrostatic test of PYROFLEX membrane | ||
7.1.2 | Daily Quality Control Checklist for PYROFLEX and DUPLY membranes | ||
7.1.3 | Daily Quality Control Inspection Report for Acid-Proof Brick Installation | ||
7.1.4 | Site curing process |
7.2 | Additional daily or periodic audits |
7.2.1 | Project Daily Production Report | ||
7.2.2 | Vessel Lining Quality Assurance Inspection Report | ||
7.2.3 | Visual inspection of PYROFLEX for uniform thickness, smoothness and no air pockets | ||
7.2.4 | Visual inspection of DUPLY for uniform coverage and tap test for bonding | ||
7.2.5 | Mortar samples taken per batch to ensure adequate set-up and workability | ||
7.2.6 | Visual and/or dimensional inspection of brick installation to ensure the lining is pockets drawings and specifications, including checking for: |
7.2.6.1 | Adequate stagger of mortar joints | ||
7.2.6.2 | High-low between consecutive brick faces | ||
7.2.6.3 | Levelness of brick courses | ||
7.2.6.4 | Mortar joint thickness | ||
7.2.6.5 | Proper cut brick sizes | ||
7.2.6.6 | Properly culled brick with excessive chips or nicks |
2.0 | Supplier Audits |
XXXX KNIGHT LLC
REVISION: A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 9 of 10 |
8.1 | Within one month from the date of award of contract, internal audits will be performed on all procedures noted in paragraph 4.0 of this document. An exception to this commitment will be made for those procedures that had already been audited within one month prior to that date. In all cases these procedures will be audited every six months until the contract is complete. | ||
8.2 | Sub-contract suppliers used in the performance of this contract will all have quality system that conform to the requirements of AS/NZS ISO 9000 or the equivalent. All sub-contract suppliers will be subject to audits per the existing audit plan. Each primary sub-contractor (steel vessel fabricators, installation services for example) will be audited one month prior to beginning fabrication or providing service. |
9.0 | Sub-contract Suppliers |
9.1 | It is the intention of Xxxx Xxxxxx LLC to obtain the services of a few key sub-contract suppliers. Xxxx Knight will approve the quality and inspection and testing plans of all sub-contract suppliers. The following products have been identified as those to be supplied by sub-contractors. |
9.1.1 Titanium fabrication | |||
9.1.2 Installation services |
9.2 | Xxxx Xxxxxx will perform periodic in-process site inspections for all sub-contract supplied items to verify all supplied items and services are in accordance with the project drawings and specifications. These inspections will include site visits to the sub-contractor fabrication facilities as deemed necessary. In-process inspection checks shall include the following. |
9.2.1 | Visual inspection | ||
9.2.2 | Dimensional checks | ||
9.2.3 | Progress monitoring | ||
9.2.4 | Sub-contractor quality control records including dimensional, material certification and NDE | ||
9.2.5 |
9.3 | If the Xxxx Knight inspector or designate identifies a fabricated item or installation service that does not meet specification, he will describe the nonconformance in “Section 1 — Originator” of the “Nonconforming Material Report” and turn it into the Project Manager for review and |
XXXX KNIGHT LLC
REVISION: A
|
East Canton, Ohio | |||
DATE: 24 February 2009
|
General Procedures | Page 10 of 10 |
disposition. If necessary, photographs will be attached for clarity. In his absence the Engineering Manager or Construction Manager may decide the disposition of item. | |||
The Project Manager or his designate will determine product disposition based on the total effects of the nonconformity and document the decision on the “Nonconforming Material Report” in “Section 2- Disposition”. If it is determined that the product will meet customer requirements and application the customer will be contacted and told of the nonconformance and provided a copy of the report. The customer will have final say if the nonconforming item is acceptable. This acceptance must be in writing and the release included with nonconformance disposition paperwork. The item can then be acceptance stamped and fabrication or installation may proceed. |
York Forter Australasia Pty Ltd | Projecrt Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
TABLE OF | ||||
CONTENTS | PAGE NUMBER | |||
Project Quality Plan Summary |
3 | |||
SECTION 1 |
||||
Acceptance of Project Quality Plan |
4 | |||
Scope |
5 | |||
SECTION 2 |
||||
Project Management Structure and Quality Assurance Responsibilities |
6 | |||
2.1 Brief description of project |
6 | |||
2.2 Quality Management |
6 | |||
Company Quality Policy Statement |
7 | |||
Site Organisational Chart |
8 | |||
3.0 Responsibilities |
9 | |||
3.1 Managing Director |
9 | |||
3.2 Site Administration Officer |
9 | |||
3.3 Site Manger |
9 | |||
3.4 Site Supervisor |
9 | |||
3.5 Direct Labour |
10 | |||
3.6 Quality Inspectors |
10 | |||
3.7 Suppliers and Subcontractors |
10 | |||
SECTION 3 |
||||
Quality Assurance Procedures |
11 | |||
1. Project Document Control |
12 | |||
2. Purchased Materials |
12 | |||
3. Commencement of Work |
13 | |||
4. Controlling Construction Processes |
13 | |||
5. Identification and Traceability |
14 | |||
6. Monitoring Subcontractors |
14 | |||
7. Control of Nonconforming Product |
14 | |||
8. Corrective and Preventitve Action |
16 | |||
9. Quality Records |
16 | |||
10. Variations |
17 | |||
11. Project Quality Audits |
17 | |||
12. Induction and Training |
17 | |||
13. Health and Safety Management |
17 | |||
14. Enviromental Management |
17 | |||
SECTION 4 |
||||
Examples of Standard Forms |
19 |
York Xxxxxx Australasia Pty Ltd | Project Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
PROJECT: |
JOB No: |
LOCATION: DRAWING No: |
||
CLIENT: |
||
CLIENT CONTACT: |
PHONE: | |
VFA SITE CONTACT: |
PHONE: | |
BRIEF DESCRIPTION OF PROJECT |
SUPPLIER | PRODUCT | CERTIFICATE REQUIRED |
SUBCONTRACTOR | WORK SUBCONTRACTED | Q.A BY | Q.A BY YFA | |||
SUBCONT |
CHECKLISTS |
QUALIFICATIONS | |
1. I.T.P |
||
2. SITE ESTABLISHMENT |
TRADES CERTIFICATE | |
3. MATERIALS RECIEPT |
CONFINED SPACE | |
4. DEMOLITION |
FORK LIFT LICENCE | |
5. PROTECTIVE LINING |
MATERIAL HOIST | |
6. INSTALL INSULATION |
TRUCK / BUS LICENCE | |
7. INSTALL BRICKWORK |
OTHER | |
8. INSTALL CASTABLE |
SITE SPECIFIC INDUCTION | |
9. INSTALL GUNNING MATERIAL 10. DAILY INSPECTIONS |
ACCREDITATION OF NOZZLEMAN | |
11. FINAL INSPECTION |
||
12. TIME SHEETS |
TESTING | ||||
SITE SAFETY PLAN |
YES/NO | MORTAR SAMPLES | ||
ENVIROMENTAL CHECKLIST |
YES/NO | BRICK TESTING | ||
PROJECT QUALITY AUDIT |
YES/NO | |||
APPROVED BY: |
||||
DATE: |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
COMPANY: |
||||
ACCEPTED BY: |
||||
PRINT NAME: |
||||
POSITION: |
||||
DATE: |
||||
COMPANY: |
POSITION: | |||||
NAME: |
DATE: | |||||
SIGNATURE: |
YFA REP: | |||||
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
SCOPE OF PROJECT QUALITY PLAN |
SECTION 1.
|
TITLE, ACCEPTANCE, CONTENTS | |
SECTION 2.
|
PROJECT MANAGEMENT STRUCTURE AND QUALITY ASSURANCE RESPONSIBILITIES | |
SECTION 3.
|
PROJECT QUALITY ASSURANCE PROCEDURES | |
SECTION 4.
|
PROJECT QUALITY ASSURANCE DOCUMENTATION |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
YORK FORTER AUSTRALASIA Pty Limited
May 2008
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 16/06/08 X.Xxxxxx |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
* | compiling the Project Quality Plan, with assistance from the Site Manager: |
* | Project Review |
* | Determining and implementing corrective actions and preventive actions. |
* | implementing the Project Quality Plan; |
* | construction programming and precommencement activities; |
* | selecting plant and equipment with suitable capability for the job; |
* | preparation of subcontract documentation; |
* | all testing, inspection and review necessary to demonstrate of the work with contract requirements; |
* | maintaining a non conformance reporting system, including authority to restrict further work pending disposition of nonconformance; |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
* | Rubber linings; |
* | Epoxies; |
* | Brickwork; |
* | Insulation materials; |
* | Mortar mixing; |
* | Castables and gunning materials. |
Project Manager
Site Supervisor
Safety Officer
QA Officer
All other relevant emergency contact numbers will be posted in crib sheds and YORK FORTER AUSTRALASIA site office.
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
York Forter Australasia Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
Arrange with Site Manager for access permits, as required
After signing off all items on the Construction Checklist for each construction process, the Site Supervisor makes a final check that all work required have been satisfactorily completed and all testing has passed. Record that this check has been done and is OK by initialing the item in the YORK FORTER AUSTRALASIA column on the ITP.
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
a) | Immediately arrange for the nonconforming work to be suitably identified by labels, flags, markers or other appropriate means to distinguish it from conforming work or materials. Wherever possible, physically isolate the nonconforming work. | |
b) | Immediately record the nature of the nonconformance on a Nonconformance Report NCR 001. | |
c) | Assess whether the construction process is likely to produce more nonconforming work and whether further output should be restricted. Consider the significance of the nonconformance and the progress of the project. Where appropriate, restrict production until a rectification for the nonconformance has been resolved and note this on the Nonconformance Report. | |
d) | Immediately examine the nature of the nonconformance and determine the appropriate method for rectifying the problem. This may be by rework, repair, replacement or use-as-is. Record the rectification method and when you intend to undertake it, on the Nonconformance Report. | |
e) | Where the proposed rectification involves a change from the design plans or YORK FORTER AUSTRALASIA Standards, submit a copy of the Nonconformance Report to the Site Manager for concurrence to the rectification. Do not commence rectifying the nonconformance without the concurrence of the Site Manager (and from YORK FORTER AUSTRALASIA; if applicable). | |
f) | Where the Site Supervisor has determined the rectification in the absence of the Site Manager, the Site Manager shall review the Nonconformance Report to determine if any further action is needed. | |
g) | The rework, repair or replacement shall be inspected or tested in accordance with the Inspection and Test Plan or as otherwise agreed with the Site Manager to ensure that the required qualify has been achieved. This shall be confirmed on the Nonconformance Report. |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd |
Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
h) | If required by YORK FORTER AUSTRALASIA, a HOLD POINT shall apply prior to covering up rectification work. In such cases notify the Site Manager when the rectification work has achieved conformance. |
The site Supervisor shall promptly file quality records at the site in lever-arch folders, grouped as follows: |
• | Construction Processes — For each process, include ITP Checklists, test results and daily inspections separately for each lot or work area. | |
• | Supplied goods and Materials-For each supplier, include delivery dockets, receiving inspection records, certificates etc. | |
• | Nonconformance Records | |
• | Site Safety Records |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd |
Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
York Forter Australasia Pty Ltd |
Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X.Xxxxxx |
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Project Quality Plan YFA-039 Rev. 1 | 16/06/08 X. Xxxxxx |
* CONSTRUCTION SCHEDULE (TO BE ISSUED ON A WEEKLY BASIS)
|
þ | |
* VESSEL TAKE OVER CERTIFICATE
|
þ | |
* VESSEL RELEASE CERTIFICATE
|
þ | |
* SITE XXXXXXX SHEET
|
þ | |
* EMPLOYEE TIME SHEET
|
þ | |
* CHANGE IN SPECIFICATION
|
þ | |
* CONTACT RECORD SHEET
|
þ | |
* INSPECTION and TEST PLANS
|
þ | |
* EQUIPMENT HIRE REGISTER
|
þ | |
* ENTRY PERMIT CONFINED SPACE
|
þ | |
* CONFINED SPACE RECORD SHEET
|
þ | |
* CHECKLIST PRIOR TO STARTING WORK
|
þ | |
* DAILY INSPECTION SHEET — REFRACTORIES
|
þ | |
* DOCUMENT REGISTER
|
þ | |
* CASTING SHEET
|
þ | |
* NON — CONFORMANCE REPORT
|
þ | |
* INCOMING INSPECTION REPORT
|
þ | |
* SITE PROGRESS REPORT — DAILY
|
þ | |
* YFA DRUG AND ALCOHOL POLICY
|
þ | |
* YFA ENVIRONMENTAL POLICY
|
þ | |
* ACCIDENT LOG
|
þ | |
* RISK ASSESSMENT
|
þ | |
* ENVIRONMENTAL PLAN
|
þ | |
* SITE SAFETY PLAN
|
þ | |
* EMPLOYEE INDUCTION HANDBOOK
|
þ | |
ATTACHMENTS |
Page 19 of 00
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd |
LEGEND: | ||||||||||||||||||||||||||||||||||||||||||||||||
W=Witness R=Review H=Hold | ||||||||||||||||||||||||||||||||||||||||||||||||
STP No. | CONTRACT | CONTRACT | SU=Survellance I=In House | |||||||||||||||||||||||||||||||||||||||||||||
CONTRACTOR CONTACT | CONTRACTOR | REV No. | No. | ITEM No. | S=Subcontractor | |||||||||||||||||||||||||||||||||||||||||||
LOCATION | QUALITY | CONTROLLING | APPROVAL | DESCRIPTION OF ITEM OR SERVICE | VESSEL. No. | |||||||||||||||||||||||||||||||||||||||||||
TASK | task | CODE | CONTROL | PROCEDURE OR | ACCEPTANCE | VERIFYING | INSP. REQ. - W/H/R/SU/S | SIGNATURES | ||||||||||||||||||||||||||||||||||||||||
No. | DESCRIPTION | (1 or 5) | ACTIVITY | INSTRUCTION | CRITERIA | DOCUMENTS | CONTR (YFA) | INSPECT. | SUPT. | CONTRACTOR | ||||||||||||||||||||||||||||||||||||||
(YFA) | ||||||||||||||||||||||||||||||||||||||||||||||||
1 |
||||||||||||||||||||||||||||||||||||||||||||||||
2 |
||||||||||||||||||||||||||||||||||||||||||||||||
3 |
||||||||||||||||||||||||||||||||||||||||||||||||
4 |
Page 1 of 1
York Forter Australasia Pty Ltd | Casting Record Sheet YFA-020 Rev. 1 | 12/06/08 X. Xxxxxxxx |
CLIENT: |
||
CONTRACT DESCRIPTION: |
||
YFA JOB REF No:
|
CLIENT JOB REF No: |
DATE:
|
/ | / | AREA: | |||||||||||||||
POSITION: | ||||||
MIXING | MATERIAL | WATER | ||||||||||
START | FINISH | DURATION | WEIGHT | VOL | TEMP | BATCH No. | ||||||
Material Type:
|
Weather Conditions: | |||||||||
Material Manufacturer:
|
Total Material Placed: | |||||||||
Material Date of Manufacture:
|
Sample Required? | YES / NO | ||||||
Material Temperature:
|
Sample Number: | |||||||||
Ambient Temperature: | (If yes, record batch number on sample) | |||||||
Completed By: |
||||
Supervisors Signature: |
||||
York Forter Australasia Pty Ltd | Daily Inspection – All Types YFA-021 Rev. 1 | 12/06/08 X. Xxxxxxxx |
CLIENT: |
||
CONTRACT DESCRIPTION: |
||
YFA JOB REF No:
|
CLIENT JOB REF No: | |
SECTION OF PLANT BEING WORKED ON: |
INSPECTED BY:
|
SIGNATURE: | |||||||||
INSPECTION DATE:
|
/ | / | ||||||||||
CERAMIC | ||||||||||||||||||||
CHECK LIST | BRICKWORK | CASTING | GUNNING | RAMMING | FIBRE | |||||||||||||||
Manufacturer: |
||||||||||||||||||||
Material Type: |
||||||||||||||||||||
Batch Number: |
||||||||||||||||||||
Identification Xxxx: |
||||||||||||||||||||
Installation Surface Clean: |
||||||||||||||||||||
Anchor Condition: |
||||||||||||||||||||
Joint Condition: |
||||||||||||||||||||
Expansion Joint Condition: |
||||||||||||||||||||
Type of Mortar being Used: |
N/A | N/A | N/A | N/A | ||||||||||||||||
Mortar Batch
No: |
N/A | N/A | N/A | N/A | ||||||||||||||||
Formwork Condition: |
N/A | N/A | ||||||||||||||||||
Ambient Temperature: |
N/A | |||||||||||||||||||
Water Temperature: |
N/A | |||||||||||||||||||
Water Quality: |
N/A | |||||||||||||||||||
Final Inspection: (Initials). |
York Forter Australasia Pty Ltd | Document Register Form YFA-022 Rev. 1 | 12/06/08 X. Xxxxxxxx |
Job Description
|
YLI No. |
DOCUMENT | ||||||
DOCUMENT NAME | REF No. | STATUS | ||||
C | U | |||||
C = Controlled | ||
U = Uncontrolled |
York Forter Australasia Pty Ltd | Incoming Inspection Report YFA-027 Rev. 1 | 12/06/08 X. Xxxxxxxx |
CLIENT: |
||
CONTRACT DESCRIPTION: |
||
YFA JOB REF No:
|
CLIENT JOB REF No: |
DATE:
|
TIME: | |||||||||
PURCHASE ORDER NUMBER: |
||||
DESCRIPTION: |
||||
PROJECT: |
VISUAL INSPECTION: |
||||
DIMENSIONAL CONFORMANCE: |
||||
YES: |
||||
INSPECTED BY:
|
DATE: | |||||||||
York Forter Australasia Pty Ltd | Non Conforrmance Report YFA-034 Rev.1 | 12/06/08 X. Xxxxxxxx |
a. Product / Work Identification |
Job No. : | |
Client : |
||
Project : | ||
Supplier:
|
Serial/Part No. : | |
Purchase Order No. :
|
Product Description : | |
Drawing No. : |
||
Quantity: |
||
Date: |
||
Originator : |
||
b. Cause and Description of
|
c. Corrective Action to Resolve | |
Non-Conformance
|
Root Cause |
The above requires your prompt attention for correction or
resolution |
DISPOSITION:
|
REJECT: | |||||
Please Initial required disposition. |
REPLACE: | |||||
REPAIR : | ||||||
ACCEPT AS IS: | ||||||
CLIENT INSP REQ’D : | ||||||
RE-INSPECT AFTER REPAIR: |
||||||
d. Corrective Action Detail | e . Corrective Action Acceptance | |||
Action Required To Prevent Recurrence
|
Completion Date : | |||
Client rep : | ||||
Date : | ||||
YFA rep : | ||||
Date : | ||||
Corrective Action Implemented :
|
YES / NO | |||
Q.A Final Review NCR Closed :
|
YES / NO | Date : |
York Forter Australasia Pty Ltd | Site Shift Report (Internal) YFA-044 Rev. 1 | 12/06/08 X. Xxxxxxxx |
CLIENT: |
||
CONTRACT DESCRIPTION: |
||
YFA JOB REF No:
|
CLIENT JOB REF No: |
ORIGINATOR:
|
SIGNATURE: | |||||||||
SHIFT:
|
DATE:___/ ___/ ___ | |||||
Qty Removed or Installed | ||||
Item | Description | (or % Done) for Shift | ||
1
|
||||
2 |
||||
3 |
||||
4 |
||||
5 |
||||
6 |
||||
7 |
||||
8 |
||||
9 |
||||
10 |
||||
11 |
||||
12 |
SIGNATURE (YFA):
|
DATE:___/ ___/ ___ | |||||
York Forter Australasia Pty Ltd | Vessel Release Certificate YFA-047 Rev. 1 | 12/06/08 X. Xxxxxxxx |
VESSEL RELEASE CERTIFICATE
CLIENT:
|
CLIENT KEF No: | |||||||||||
CONTRACT: |
||||||||||||
YFA REF No: |
||||||||||||
SECTION OF PLANT WORKED ON: |
||||
CLIENT: |
||||||||
APPROVED BY:
|
Name: | |||||||
Position: | ||||||||
Signature: | ||||||||
Date: | ||||||||
___/ ___/ ___ | ||||||||
INSTALLED BY:
|
YORK FORTER AUSTRALASIA. | |||||||
WITNESSED BY:
|
Name: | |||||||
Position: | ||||||||
Signature: | ||||||||
Date: | ||||||||
___/ ___/ ___ | ||||||||
COMMENTS: |
||||||||
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Vessel Take Over Certificate YFA-048 Rev. 1 | 12/06/08 X. Xxxxxxxx |
VESSEL TAKE OVER CERTIFICATE
CLIENT:
|
CLIENT KEF No: | |||||||||||
CONTRACT: |
||||||||||||
YLI
REF No: |
||||||||||||
SECTION
OF PLANT TO BE WORKED ON: |
||||
CLIENT: |
||||||||
APPROVED BY:
|
Name: | |||||||
Position: | ||||||||
Signature: | ||||||||
Date: | ||||||||
___/ ___/ ___ | ||||||||
INSTALLED BY:
|
YORK FORTER AUSTRALASIA. | |||||||
WITNESSED BY:
|
Name: | |||||||
Position: | ||||||||
Signature: | ||||||||
Date: | ||||||||
___/ ___/ ___ | ||||||||
COMMENTS: |
||||||||
Xxxx Xxxxxx Xxxxxxxxxxx Pty Ltd | Work Method Statement YFA-1124 Rev.1 | 23/02/09 X. Xxxxxx |
Item | Work Procedure | Major Hazards | ||
1
|
||||
2 |
||||
3 |
||||
4 |
||||
5 |
||||
6 |
ABN 11 280 836 918
Quality management systems — Requirements
(“XXx Global”) and subject to the SAI Global Terms and Conditions for Certification. While all due care and skill was exercised In carrying out
the assessment XXx Global accepts responsibility only for proven negligence. This certificate remains the property of SAI Global and must be
Certificate No.: | QEC21609 | Certified Date: | 14 March 2005 | |||||
Issue Date: | 16 May 2008 | Expiry Date: | 13 March 2011 |
Alex Ezrakhovich General Manager Certification for and on behalf of SAI Global Limited |
Authorised Local Signatory, SAI Global |
MOPU-0035, MOPU-0063, AND MOPU-1010
AUTOCLAVE #4
Supply Autoclave Lining System & Installation Services
Revision 4.1
Proposal 000 00 0000 A4
16 June 2009
Perth, Western Australia Office
A Division of Xxxx Australia Pty Ltd. |
Lihir Services Australia Pty Ltd
Xxx 0, 000 Xxxxx Xxxxxx, Xxxxxxxx, XXX, 0000
XXX Xxx 000, Xxxxxxxx, XXX, 0000. Australia
Phone
x00 0 0000 0000 (Switch)
Fax: x00 0 0000 0000
Email:
Web: xxx.xxxxxxx.xxx
• | Under MOPU 1010, all lining materials including titanium compartment walls and nozzle liners will be provided. | ||
• | Under MOPU0063, the PYROFLEX® RESIBOND® DuPly Membrane System will be installed at the fabricator shop in Malaysia before the autoclave shell ships. | ||
• | Under MOPU0035, the brick lining will be installed after the shell is in place at the Lihir PNG site. |
Perth Office, Phone ; Fax 00-0-0000-0000, ; xxx.xxxxxxxxxx.xxx
LGL MOPU-0035, MOPU0063, MOPU-1010 Knight ###-##-#### A4 Rev 4.1 |
16 June 2009 Page 3 of 7 |
PRICES | USD, AUD As Noted | |||
MOPU-1010: MATERIALS SUPPLY |
||||
• Autoclave Lining Materials, Firm Price FOB Rail Point Cleveland Ohio |
$ | |||
• Titanium Baffles, Compartment Walls, and Nozzle Parts, Price Firm, Validity date
for ordering metal 30 June 2009, FOB Brisbane |
$ | |||
MPOU-1010: Materials Supply Total |
$ | |||
• Additional Item: Estimated Freight CIF Brisbane and Kuala Lumpur (for Membrane
only) |
$ | |||
MOPU-0035: Labour & Services for Brick Lining Installation at Lihir Island |
||||
• Xxxx Xxxxxx Services, Firm Price to 30 September 2011 |
$ | |||
• York-Forter Subcontract, Firm price to 30 September 2011, in Australian Dollars |
$ | |||
• Registration, visas, work permits for YFA and Xxxx, locally sourced insurance
coverage in PNG |
$ | |||
• Travel for Crew to Cairns instead of Brisbane to Meet LGL Transport |
$ | |||
• One Lot Lead Abatement PPE |
$ | |||
• One Internal Scaffolding |
$ | |||
Prices good for orders placed before September 2010 |
||||
MOPU-0035: Lining Installation in PNG, AUD Currency Total |
$ | |||
USD Currency Total |
$ |
XXX XXXX-0000, MOPU0063, MOPU-1010 Knight ###-##-#### A4 Rev 4.1 |
16 June 2009 Page 4 of 7 |
PRICES | USD, AUD As Noted | |||
• Optional Item: Site Holiday Shutdown ( Secure Tools and
Materials, Travel in/out of Cairns, Reset Tools and Materials) |
$ | |||
• Optional Major Tools, Shipment Before 1 September 2010: |
||||
o One Mobile Dust Collector (Negative Air Unit), Each |
$ | |||
o Three Environmental Control-AC Units, Each |
$ | |||
MOPU-0063: Services, Labour, Expenses, Equipment for
PYROFLEX Membrane Installation in Malaysia |
||||
• Xxxx Xxxxxx Installation Services |
$ | |||
• Visas, work permits, registration in Malaysia |
$ | |||
• Lodging, Food, In Country Travel by Xxxx Knight Personnel |
$ | |||
MOPU-0063: Membrane Installation in Malaysia Total |
$ |
Activity | Approximate Duration | |||
Lining Drawings and Calculations |
||||
Approval by client |
||||
Titanium component submittal drawings |
||||
Autoclave brick, membrane manufacture |
||||
Titanium component fabrication |
||||
Shipping Time to Brisbane or Malaysia, All Materials |
||||
Autoclave Membrane Installation at the Fabricator |
||||
Shipping Time, Vessel Shell to LGL, and Erect Building |
||||
Autoclave Brick, Compartment Walls Installation Onsite |
||||
Total time to complete lining, Standard Delivery |
XXX XXXX-0000, MOPU0063, MOPU-1010 Knight ###-##-#### A4 Rev 4.1 |
16 June 2009 Page 5 of 7 |
1. | Membrane installation in Malaysia will be in the fabricator’s shop, with the shell in a closed area on its saddles, stationary, surface prep complete and primed, with full utilities including gas fuel supply, site facilities, humidity control, and access to the vessel all provided by others | ||
2. | Brick installation into the vessel will begin after the vessel is set in the permanent building at the site | ||
3. | Hole watch personnel and vessel entry controls and documentation will be by LGL. | ||
4. | LGL shall provide priority access to the overhead crane for several hours daily, and a forklift plus other materials handling services for stocking lining materials from the laydown area to the work site. This includes moving contractor equipment needed during the installation. | ||
5. | Crews will have free and clear access to the man-ways and agitator openings of the vessels via the permanent building structure, must be adequate for materials staging and access to the vessel entry points. | ||
6. | Lead monitoring and control protocols needed while installing the GLYSIL 90 litharge mortar are included. This includes disposable coveralls for use during the GLYSIL 90 Mortar Installation. | ||
7. | The autoclave work area must include area fan cooling, protection from the weather, and shielding the shell from direct sunlight. | ||
8. | LGL to provide for a four desk site office trailer and crib room, all air conditioned and secured. A tool crib/container by York is included, delivered to Brisbane and set on site by LGL. | ||
9. | All work, storage and crib areas must be vehicle accessible in all site weather conditions. Accessible covered storage space, nominal 12 m by 6 m, adjacent to the construction site (maximum 50 metres away) shall be made available for storage of materials and equipment. | ||
10. | The York-Forter crew will work 12 hour days, 13 day fortnights, off every other Sunday. R&R rotation on a 28 day schedule. A similar schedule will apply to the membrane installation in the fabrication shop. | ||
11. | The owner shall provide and maintain utilities, including an ablution block with potable water and sewerage hookups, construction water, electricity 220 and 440v including hookups, and transport for personnel, materials and equipment to/from the work area and generally within the LGL site. | ||
12. | Removal and replacement of all covers, process piping and connections, process gaskets, and other items required for access will be by others. | ||
13. | Emergency Medical Facilities will be available to our crews on a 24hr/day basis, provided at no cost by others. | ||
14. | The owner will furnish protection from process fumes and other plant conditions which may interfere with our crew performing work. | ||
15. | We have not included services for any extended acid-cure. Detailed start-up and cool-down process condition requirements will be included as part of the documentation with the order. | ||
16. | Construction debris including GLYSIL 90 lead oxide mortar waste is to be placed in owner provided containers for disposal by owner. |
LGL MOPU-0035, MOPU0063, MOPU-1010 | 16 June 2009 | |
Knight ###-##-#### A4 Rev 4.1 | Page 6 of 7 |
• | Recommended commissioning procedure, allows taking unit direct to operation without acid curing. | ||
• | Startup and shutdown operating procedures recommendations. | ||
• | Executed copies of the contract documents to be prepared by LGL. |
• | An extended firm price commitment for the York-Forter installation services past 30 September 2011. | ||
• | A maintenance agreement for subsequent inspections of this vessel, the other autoclave trains, and other lined equipment. | ||
• | Prices for additional vessels, lined piping, etc. that are part of this system. | ||
• | Prices for spare parts. | ||
• | Knight can offer to purchase the required shipping containers for the lining materials as an extra item. Purchased containers will not risk demurrage charge assessments at loading or delivery to port, and can be held fully packed in Brisbane until Lihir Island is ready to take delivery. Some of these containers can be outfitted for temperature control to extend the life of the chemical mortars during transit, while awaiting onward shipment, and while at site. | ||
• | Other items that are of value to Lihir can be offered on request. |
XXX XXXX-0000, MOPU0063, MOPU-1010 | 16 June 2009 | |
Knight ###-##-#### A4 Rev 4.1 | Page 7 of 7 |
XXXX AUSTRALIA PTY
XXXX KNIGHT DIVISION
CC:
Attachments: Provided with previous Quote version Rev 4
Lihir Attachments: Revised Forms provided separately
Minutes of Meeting 1st April, 2009
Minutes of Meeting 3rd June, 2009
Minutes of Meeting 9th and 10th June, 2009
MINUTES OF POST TENDER MEETING #4 | PAGE 1 | |
WORK PACKAGE MOPU-1010 & MOPU-0035 | 9th and 10th June, 2009 |
MEETING TYPE: | POST TENDER MEETING #4 WORK PACKAGE |
MOPU-1010 & MOPU-0035 |
||
TENDERER: | Xxxx Australia Pty Limited |
|||
DATE: | 9th June 2009 and 10th June 2009. |
|||
VENUE: | LSA Corporate Office, Brisbane |
|||
ATTENDEES: | LGL
|
Contractor (Xxxx) |
MINUTES OF POST TENDER MEETING #4 | PAGE 2 | |
WORK PACKAGE MOPU-1010 & MOPU-0035 | 9th and 10th June, 2009 |
MINUTES OF POST TENDER MEETING #4 | PAGE 3 | |
WORK PACKAGE MOPU-1010 & MOPU-0035 | 9th and 10th June, 2009 |
MINUTES OF POST TENDER MEETING #4 | PAGE 4 | |
WORK PACKAGE MOPU-1010 & MOPU-0035 | 9th and 10th June, 2009 |
MINUTES OF POST TENDER MEETING #4 | PAGE 5 | |
WORK PACKAGE MOPU-1010 & MOPU-0035 | 9th and 10th June, 2009 |
Minutes Recorded | Minutes accepted | |
for and On Behalf of | For and On Behalf of | |
LGL | Xxxx |
Date: 10/06/09 | Date: |
MINUTES OF POST TENDER MEETING #3 | PAGE 1 | |
WORK PACKAGE MOPU-1010 & MOPU-0035 | 03/06/2009 |
MEETING TYPE: | POST TENDER MEETING #3 | |||
WORK PACKAGE MOPU-1010 & MOPU-0035 | ||||
TENDERER: | Xxxx Australia Pty Limited | |||
DATE: | 3rdJune 2009 | |||
VENUE: | LSA Corporate Office, Brisbane | |||
ATTENDEES:
|
LGL | Contractor (Xxxx) |
MINUTES OF POST TENDER MEETING #3 | PAGE 2 | |
WORK PACKAGE MOPU-1010 & MOPU-0035 | 03/06/2009 |
Minutes Recorded | Minutes accepted | |
for and On Behalf of | For and On Behalf of | |
LGL | Xxxx | |
Date: 03/06/09 | Date: |
MINUTES OF POST TENDER MEETING #2 | PAGE 1 | |
WORK PACKAGE MOPU-0035 & MOPU-1010 | 01/04/2009 |
MEETING TYPE: | POST TENDER MEETING #2 | |||
WORK PACKAGE MOPU-0035 & MOPU-1010 | ||||
TENDERER: | Xxxx Australia Pty Limited | |||
DATE: | 1st April 2009 | |||
VENUE: | LSA Corporate Office, Brisbane | |||
ATTENDEES:
|
LGL | Contractor (Xxxx) |
1. | Price Basis Discussion: | |
Price basis for below prices includes Lining system, ex works, with installation, no freight. | ||
for March; made up of the following components: 1.2, 1.7, 0.4, 3.6 | ||
for January, difference — Xxxx advised that the January proposal made incorrect statement with regard to End date of September 2011, compared with 2010. Xxxx reported that YF quote was to 2010, not 2011 as erroneously stated. YF reported that the cost increase between March offer and Jan number relates to labour cost differences. | ||
LGL stated that it did not accept this statement, as 2011 date was included in the November submission (York Forter attachment to Xxxx’x tender). Xxxx to confirm the price basis is to September 2011, with pricing to compare with January submission, not increased cost as proposed within the March proposal. | ||
Xxxx informed the meeting that the Brick lining installation is YF’s scope, Pyroflex is Xxxx’x installation. figure includes Xxxx’x installation, utilising light gauge scaffold and utilisation of local labour, with W.E. Smiths assistance in sourcing this labour. Pyroflex installation is now included within MOPU-1010. | ||
LGL requested that Kock resubmit their quotation to clearly reflect the above noted pricing structure. | ||
2. | Visa / Work Permits Proposal: | |
Xxxx reported that it would be around per person. Proposal will be sent to LGL. Approximately 40 persons will require visa’s. This will include Malaysia component as well. Approx 5 – 6 for Malaysia, balance for PNG. | ||
LGL informed Xxxx that it would be required to have PNG Foreign company registration and certification. Details of the government website were provided to Xxxx for their information and consideration. (I can’t find the e-mail with the web address -we should insert the address here for completeness) |
MINUTES OF POST TENDER MEETING #2 | PAGE 2 | |
WORK PACKAGE MOPU-0035 & MOPU-1010 | 01/04/2009 |
3. | Titanium: | |
Xxxx informed the meeting that five vendors provided pricing for Xxxx’x proposal, and they all stated that pricing offered had been on the down swing at the time of the original quote, and could not be reduced any further. The validity period can be extended, Xxxx to confirm new validity period. | ||
Xxxx offered for LGL to purchase Ti directly. LGL advised Xxxx that at this point in time, the Ti would remain in Xxxx’x scope. | ||
4. | Payment Milestones: | |
MOPU-1010: | ||
LGL agreed to the proposed amendment to the MOPU-1010 payment milestone schedule, as noted in red above. | ||
MOPU-0035 | ||
Xxxx advised that the proposed schedule for MOPU-0035 is acceptable. | ||
5. | Drawings: | |
Autoclave building elevation drawings to be issued to Xxxx for information purposes. |
MINUTES OF POST TENDER MEETING #2 | PAGE 3 | |
WORK PACKAGE MOPU-0035 & MOPU-1010 | 01/04/2009 |
6. | Email 26/3/09 (further questions / clarifications) Discussion: |
1. | Single mob / demob |
• | Price includes allowance for personnel mob / demob | ||
• | It is LGL’s intention for the work to carry on through Easter, should the schedule of works fall at this time. Kock to confirm this is included in their price | ||
• | LGL may include Christmas break | ||
• | Kock advised that a Christmas break is not included in their price as reflected in their proposed schedule. However a Christmas break would not include a full mob / demob, only personnel | ||
• | Key dates from LGL’s schedule will be provided to Xxxx, once available |
2. | Pyroflex installation- utilisation of rollers |
• | No benefit to be had by utilising rollers | ||
• | Xxxx will not utilise rollers |
3. | Tender Validity |
• | Xxxx to advise revised validity period |
4. | Contract start / documents |
• | LoA taking 0035 as an example, creates contract b/w parties, represented by everything we have done collectively to come to that point, LoA wording mirrors that of that in the documents. | ||
• | Instrument of Agreement is the covering note for contract. The contract will include the LoA. | ||
• | Xxxx advised that their legal review had not been complete, and suggested a “wholesale” review of the documentation. LGL advised that this was not acceptable and would take an extended period of time to sort through. | ||
• | Xxxx requested that some form of commitment be made between LGL and Xxxx such as a Letter of Intent. LGL advised that it would not make a commitment. | ||
• | LGL need to know exactly what Xxxx disagree with in terms of the commercial terms and conditions prior to advancing any further. LGL requested Xxxx to continue with the contract negotiations, in order to be further considered in this process, as LGL consider the commercial aspects of Xxxx’x offer to be equally important as the technical aspects and that until LGL know the full extent of Xxxx’x requested changes to the terms and conditions they will be unable to progress towards any potential award. LGL advised that they will respond to Kock’s latest version of the departures matrix for both MOPU-0035 and MOPU-1010 within a couple of days and requested that Xxxx expedite their further response to this. |
5. | Sheet 10/B Sheet 1, Agreed that this form was not applicable now. | ||
6. | Sheet 10/B Sheet 2, typo with hourly rates, should be daily rates. | ||
7. | Schedule to be revised | ||
8. | Malaysian installation will be a third contract; LGL consider the form of contract will be as per MOPU-0035, with some variation to allow for Malaysian basis, in lieu of PNG basis. Xxxx to provide breakout pricing for the Pyroflex supply and installation, for LGL’s consideration. Xxxx to re-submit pricing for correct split between proposed contracts |
7. | Email 25/3/09 (post tender meeting deliverables) Discussion: |
1. | Insurances must comply with the requirements of the PNG insurance act, with risks based in PNG, to be insured by PNG based insurer, unless an exemption is obtained. | ||
2. | Pyroflex pricing breakdown to be provided by Xxxx. | ||
3. | Ti Price confirmed as CIF Brisbane. | ||
4. | Price basis from YF to be reviewed by Xxxx. |
8. | Post Meeting Note |
LGL has recently been advised that for work carried out in PNG (MOPU-0035), LGL is obligated to make the payment in PNG Kina, regardless of the currency of the contract. |
MINUTES OF POST TENDER MEETING #2 | PAGE 4 | |
WORK PACKAGE MOPU-0035 & MOPU-1010 | 01/04/2009 |
Minutes Recorded | Minutes accepted | |
for and On Behalf of | For and On Behalf of | |
LGL | Xxxx | |
Date: 01/04/09 | Date: |
MINUTES OF POST TENDER MEETING | PAGE 1 | |
WORK PACKAGE MOPU-0035 | 19/2/2009 |
MEETING TYPE: | POST TENDER MEETING | |||
WORK PACKAGE MOPU-0035 | ||||
TENDERER: | Xxxx Australia Pty Limited | |||
DATE: | 19th February 2009 | |||
VENUE: | Lihir Island Operations | |||
ATTENDEES:
|
LGL | Contractor (Xxxx) |
1. | Safety and Environment | |
Discuss the Xxxx’x submission in accordance with clause 2.5.4 (m) of the Tender document. |
o | To be submitted by Xxxx (for both Xxxx & YF) |
2. | Tender Form 3/A — Notices of Explanation: LGL advised that there were three Notices of Explanation issued during the Tender period. |
o | MOPU-0035-L Invitation to Tender — Autoclave Internal Equipment — Installation — Notice to Tenderer’s #1 (Issued 8/11/08) | ||
o | MOPU-0035-L Invitation to Tender - Autoclave Internal Equipment Installation — Notice to Tenderer’s #2 (Issued 13/11/08) | ||
o | MOPU-0035-L Invitation to Tender - Autoclave Internal Equipment Installation — Notice to Tenderer’s #3 (Issued 26/11/08) |
Xxxx confirmed that it had included all of these Notices. |
3. | Tender form 3/B — Addendum: LGL advised that there were no Addendum (a) issued during the Tender period. | |
4. | Tender Form 3/C — Tender Form: LGL asked if this form had been submitted in accordance with Clause 2.5.2 of the Conditions of Tendering. Xxxx to submit the form, with appropriate signatory. |
MINUTES OF POST TENDER MEETING | PAGE 2 | |
WORK PACKAGE MOPU-0035 | 19/2/2009 |
Xxxx confirmed that their Tender Price as , and needs to have the installation of the Pyroflex removed and added to the supply contract MOPU-1010. The Tender Price has a mjor component of at an exchange rate of to | ||
Xxxx confirmed that their Tender Price was based upon an Award date of 31st March, 2009 and a latest practical completion date of 30th September, 2011 and complied with LGL’s nominated key dates. YF noted that their annual wage increases occur at the end of September each year. | ||
5. | Tender Form 3/D — Interrelationship of Corporations: | |
LGL advised that the form as submitted was acceptable as submitted, but needs to be signed and resubmitted. | ||
6. | Tender Form 3/E — Deed of Guarantee, Undertaking and Substitution: LGL advised that if Xxxx were awarded this Contract that a Deed of Guarantee, Undertaking and Substitution would be required. Xxxx to sign and resubmit this form. | |
7. | Tender Form 3/F — Departures From Specifications and Tender Documents: LGL requested Xxxx to confirm that there were no other departures from Specifications and Tender Documents than as detailed on this form. | |
Xxxx confirmed that there were no other departures, apart from those noted within the submission. Xxxx to sign and resubmit this form. |
o | Hole watch personnel and vessel entry control by LGL — noted | ||
o | Dedicated materials handling equipment by LGL — noted. YF noted that a crane may not be required full time, if works scheduled well. Driver allocated for the forklift by YF. | ||
o | Crews will have free and clear access to vessel, etc — Agreed | ||
o | Monitoring included by Xxxx — agreed | ||
o | Weatherproof or roofed structure required to be in place -Agreed | ||
o | Fan cooling to autoclave required by Xxxx, supplied by LGL -Agreed. Xxxx noted that this is both internal and external cooling. | ||
o | Office trailer / crib room / tool crib not provided by Xxxx (contrary to written submission) — noted |
o | YF stipulated requirement of space for 4 office staff, 1 phone line, fax line | ||
o | Crib room space for 20 personnel — air con, fridge | ||
o | Tool crib included in YF scope, supplied to Brisbane. | ||
o | Covered storage space — YF noted will require a 12 x 6m space. |
o | YF working hours — 12 hours days, 13 day fortnight. Every second Sunday noted included. RDO’s banked by YF, so that no days off apart from every second Sunday. Rotation of every 28 days — noted |
MINUTES OF POST TENDER MEETING | PAGE 3 | |
WORK PACKAGE MOPU-0035 | 19/2/2009 |
o | Owner shall maintain utilities, ablutions, etc -Agreed. | ||
o | Water usage — equipment washdown (not potable), drinking water (potable). Agreed | ||
o | 415 and 240V supplied by LGL — Agreed | ||
o | Removal and replacement of covers — by others — Agreed | ||
o | No piping to be connected to Autoclave — agreed | ||
o | Access to Emergency crews 24 hrs per day to be provided by LGL — agreed | ||
o | Protection from process fumes — agreed | ||
o | Disposal of lead mortar — by LGL — agreed | ||
o | YF letter 22nd Nov — Page 2 |
o | Additional line items costs — noted | ||
x | Xxxx includes Ti wall installation (although excluded by YF) | ||
o | Installation of scaffold is included in both cases | ||
o | Laundering facility - decontamination area required by YF — noted | ||
o | YF get workers compensation whilst in PNG | ||
x | Xxxx also requires this PNG workers compensation | ||
o | Only allowed 2 hrs for inductions. LGL clarified post meeting, that up to 3 inductions may be required, taking 2 days in total. | ||
o | Clause 37 — LGL takes issue with this clause (specifically “should company be divested, order would be immediately terminated”) — noted | ||
o | Clause 38 — needs to be mutual determination, not YF determination. |
8. | Tender Form 3/G — Key Personnel: | |
Xxxx confirmed that those personnel nominated on this Tender form would be fully available for this Work Package, however was unable to nominate specific XX and XX personnel at this time. | ||
Xxxx would assign a project manager (probably), who would be primary point of contact would report to KB. Xxxxx superintendent on site (4/5 available with 20+ years experience). | ||
Xxxx designated Project Manager would be authorised to accept documents or notices from LGL, price extra work, and correspond with LGL in relation to financial and confidential matters. | ||
Xxxx to sign and resubmit this form. | ||
9. | Tender Form 3/H — List of Current Projects: | |
LGL noted that Xxxx had several current projects in progress, and asked how this would affect this Work Package if awarded to Xxxx. Xxxx advised that most projects turn over in 6 -12 months, and that there is only one project that may overlap with the LGL projects. YF advised that they have no issues with placement of personnel on site. | ||
LGL noted these statements. | ||
Xxxx to sign and resubmit this form. |
MINUTES OF POST TENDER MEETING | PAGE 4 | |
WORK PACKAGE MOPU-0035 | 19/2/2009 |
10. | Tender Form 3/I — Wages, Allowances and Employment Conditions: | |
LGL confirmed that the site working hours were 24 per day. Xxxx confirmed that its price was based upon working 12 hrs / day, 13 days per fortnight. | ||
Xxxx confirmed it had allowed an R&R roster of 28 days on, 7 days off (including travel). | ||
LGL stated that rostered time off site for personnel must be staggered to ensure a smooth continuity of work on site. Xxxx agreed to do this. | ||
Xxxx confirmed that it had not allowed to provide crib huts in accordance with all relevant requirements. | ||
LGL advised that toilet facilities would be provided for the use by the Contractor. | ||
Xxxx confirmed that it had not allowed to transport all personnel from the camp to and from the site on a daily basis as this is to be provided by LGL. LGL agreed. Xxxx confirmed it had allowed to mobilise and demobilise all personnel from their point of hire accordingly in its Tender price. | ||
Xxxx confirmed that suitable vehicles would not be provided for transportation of site personnel. LGL to supply bus service. | ||
Xxxx to sign and resubmit this form. | ||
11. | Tender Form 3/J Sheets 1 and 2 — Tenderer’s Plant and Equipment: | |
LGL asked Xxxx to advise the meeting what items of plant it would mobilise to site if awarded this work package. | ||
Xxxx advised that they had allowed the plant as detailed in its Tender form 10/B sheet 3 of 3. Provide details of relevant equipment to be supplied Xxxx, utilising sheet Appendix 3/X. | ||
Xxxx confirmed they had made all allowances in its Tender Price to transport all necessary equipment and materials to and from Brisbane. | ||
LGL advised that all Contractors on site will be required to be self sufficient and that no small tools or consumables would be available from LGL’s warehouse. Xxxx confirmed their understanding of this. | ||
Xxxx to sign and resubmit these forms. | ||
12. | Tender Form 3/K — Work to be Subcontracted: | |
LGL requested Xxxx to advise the meeting if they intended to subcontract any portion of the work. | ||
Xxxx advised that York Forter would be sub contracted for the lining installation, and Xxxx Xxxxxx LLC for the supply of the bricks. | ||
Titanium supplier to be determined — noted. | ||
Xxxx to sign and resubmit this form. | ||
13. | Tender Form 3/L — Cash Flow Programme: | |
LGL advised the meeting that a revised cash flow programme shall be submitted [signed] once agreement on milestone payment schedule has been reached. |
MINUTES OF POST TENDER MEETING | PAGE 5 | |
WORK PACKAGE MOPU-0035 | 19/2/2009 |
14. | Tender Form 10/A — Components of Tender Price: | |
LGL advised that this form was acceptable as submitted. | ||
LGL advised that this form would have to be resubmitted [signed] to reflect any changes in Xxxx’x price arising out of this meeting (including the removal of the installation of the Pyroflex from this contract). | ||
15. | Tender Form 10/B: Rates for Dayworks and Variation: | |
Sheet 1 of 3: LGL advised that the sheet was incomplete. Xxxx to submit completed form. | ||
Sheet 2 of 3: LGL advised the rates were unacceptable. Rates to be provided. | ||
Sheet 3 of 3: LGL asked Xxxx if the rates included operators where applicable? Xxxx advised rates are not applicable to these equipment items. | ||
LGL advised the rates were unacceptable. Xxxx to resubmit form. Xxxx to resubmit all three forms as above and signed. | ||
16. | Tender Form 10/C — Tender Schedule: | |
Xxxx confirmed that their Tender Schedule was based upon an award date of 31st March, 2009 and with the latest practical completion of 30th September 2011, and complied with all other nominated key dates within the documents. | ||
LGL reiterated it intent to review progress and any possible claims only under the auspices of Clause 4.2.4 “Progress and Programming of the Works”. LGL further stated that any claims that were not presented within the procedures laid down in this Clause would be rejected by LGL. Xxxx confirmed their understanding and agreement with this. | ||
Kock to resubmit their signed schedule once LGL advised their schedule. | ||
17. | Tender Form 10/D — Projected Weekly Manpower: | |
LGL advised the form was unacceptable as submitted. LGL requested Xxxx to update from from meeting discussions and resubmit a signed form. | ||
18. | Quality Control Procedures: | |
LGL requested details of the quality control procedures that Xxxx would implement if they were awarded this Work Package: | ||
Xxxx advised: Xxxx to submit Quality program for LGL’s consideration, including York Forter works and Xxxx’x works. These are to be submitted by date in point 26 below. | ||
19. | Confirmation of Site Inspection: | |
Xxxx confirmed that it had not inspected the site. | ||
Xxxx to confirm post meeting that it had fully informed itself in accordance with Clause 2.3 “Tenderer to Inform Itself”. | ||
20. | Insurances: | |
Not discussed, as it is currently under negotaiton as part of the terms and conditions negotations. | ||
21. | Financial Considerations: | |
Not discussed, as it is currently under negotaiton as part of the terms and conditions negotations. |
MINUTES OF POST TENDER MEETING | PAGE 6 | |
WORK PACKAGE MOPU-0035 | 19/2/2009 |
22. | Tender Letter: | |
The following items from Xxxx covering letter submitted with the Tender require clarification: | ||
Clarification of tender letter points undertaken elsewhere in minutes. | ||
23. | Specification / Scope of Work: | |
Specification and Scope of Work deviations were discussed elsewhere in meeting. | ||
Tender schedule to be changed, in accordance with discussions. | ||
Xxxx confirmed that it understood and had allowed for all Work required by the Tender Scope of Work, as amended today. | ||
24. | Alternative Tender Submission: | |
Xxxx confirmed that it had not submitted any alternative tender submissions other than discussed herein. | ||
25. | Other | |
LGL sent an email to dated 12th February for action by 17th February. Xxxx to confirm receipt of email, and to now respond by 4pm (Brisbane time), Thursday 26th February, 2009. | ||
26. | Date for Resubmission of Information: | |
LGL requested that the following outstanding information be submitted by Thursday 26th February, 2009. Xxxx advised that it would do so. | ||
Items for action are referenced in points 1, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, and 18. |
Minutes Recorded | Minutes accepted | |
for and On Behalf of | For and On Behalf of | |
LGL | Xxxx | |
Date: 19/2/09 | Date: |