Common use of Further Revisions to Cost Estimate and Project Schedule Clause in Contracts

Further Revisions to Cost Estimate and Project Schedule. If necessary, the CM shall inform the A/E and the COUNTY of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule. Upon approval of the COUNTY of any such adjustments, the CM, with the assistance of the A/E, shall prepare a revised Detailed Estimate of Construction Cost or a revised Project Schedule, as applicable, incorporating such adjustments, and deliver to the COUNTY.

Appears in 3 contracts

Samples: Contract for Professional Services, Construction Management Services, Construction Management Services

AutoNDA by SimpleDocs

Further Revisions to Cost Estimate and Project Schedule. 6.9.1 If necessary, the CM A/E shall inform the A/E CM, the Contracting Authority, and the COUNTY Owner of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule. . 6.9.2 Upon approval of the COUNTY Contracting Authority and Owner of any such adjustments, the CM, with the assistance of the A/E, E shall assist the CM to prepare a revised Detailed Estimate of Construction Cost or a revised Project Schedule, as applicable, incorporating such adjustments, and deliver to the COUNTY.

Appears in 1 contract

Samples: Professional Services

AutoNDA by SimpleDocs