Generating Facility or Merchant Transmission. Facility Site Changes Project Developer may specify a change to the project Site only if: a. the Project Developer satisfied the requirements for Site Control for both the initial Site proposed in the New Service Request Application and the newly proposed site; and b. the initial Site and the proposed Site are adjacent parcels. c. Such Site Control is subject to the verification procedures set forth in Tariff, Subpart D, section 309(A)(2)(c) (Decision Point I Site Control verification).
Appears in 3 contracts
Samples: Generation Interconnection Procedures, Generation Interconnection Procedures, Generation Interconnection Procedures
Generating Facility or Merchant Transmission. Facility Site Changes Project Developer may specify a change to the project Site only if:
a. the Project Developer satisfied the requirements for Site Control for both the initial Site proposed in the New Service Request Application and the newly proposed site; and
b. the initial Site and the proposed Site are adjacent parcels.
c. Such Site Control site control is subject to the verification procedures set forth in Tariff, Subpart DC, section 309(A)(2)(c) (Decision Point DP I Site Control site control verification).
Appears in 1 contract
Samples: Generation Interconnection Procedure