Common use of Generation compensation for Off-take constraints Clause in Contracts

Generation compensation for Off-take constraints. 4.10.1 Generation Compensation in offtake constraint due to Transmission Infrastructure not complete/ ready (Transmission constraint): After the Scheduled Commissioning Date, subject to the submission of documentary evidences from the Competent Authority, if the plant is ready in all respects including the dedicated transmission line to be established by the SPD to connect to the grid but the necessary power evacuation/ transmission infrastructure is not ready, for reasons not attributable to the SPD, leading to offtake constraint, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 8 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Generation compensation for Off-take constraints. 4.10.1 Generation Compensation in offtake constraint due to Transmission Infrastructure not complete/ ready (Transmission constraint): After the Scheduled Commissioning Date, subject to the submission of documentary evidences from the Competent Authority, if the plant is ready in all respects including the dedicated transmission line to be established by the SPD to connect to the grid but the necessary power evacuation/ transmission infrastructure is not ready, for reasons not attributable to the SPD, leading to offtake constraint, the generation compensation from the buying utility shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 4 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Generation compensation for Off-take constraints. 4.10.1 Generation Compensation in offtake constraint due to Transmission Infrastructure not complete/ ready (Transmission constraint): After the Scheduled Commissioning Date, subject to the submission of documentary evidences from the Competent Authority, if the plant is ready in all respects including the dedicated transmission line to be established by the SPD to connect to the grid but the necessary power evacuation/ transmission infrastructure is not ready, for reasons not attributable to the SPD, leading to offtake constraint, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 4 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Generation compensation for Off-take constraints. 4.10.1 Generation Compensation in offtake constraint due to Transmission Infrastructure not complete/ ready (Transmission constraint): After the Scheduled Commissioning Date, subject to the submission of documentary evidences from the Competent Authority, if the plant is ready in all respects including the dedicated transmission line to be established by the SPD to connect to the grid but the necessary power evacuation/ transmission infrastructure is not ready, for reasons not attributable to the SPD, leading to offtake constraint, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI.:

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Generation compensation for Off-take constraints. 4.10.1 Generation Compensation in offtake constraint due to Transmission Infrastructure not complete/ ready (Transmission constraint): After the Scheduled Commissioning Date, subject to the submission of documentary evidences from the Competent Authority, if the plant is ready in all respects including the dedicated transmission line to be established by the SPD to connect to the grid but the necessary power evacuation/ transmission infrastructure is not ready, for reasons not attributable to the SPD, leading to offtake constraint, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECIMAHAGENCO.:

Appears in 1 contract

Samples: Power Purchase Agreement

Generation compensation for Off-take constraints. 4.10.1 Generation Compensation in offtake constraint due to Transmission Infrastructure not complete/ ready (Transmission constraint): After the Scheduled Commissioning Date, subject to the submission of documentary evidences from the Competent Authority, if the plant is ready in all respects including the dedicated transmission line to be established by the SPD to connect to the grid but the necessary power evacuation/ transmission infrastructure is not ready, for reasons not attributable to the SPD, leading to offtake constraint, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECIEDA&N:

Appears in 1 contract

Samples: Power Purchase Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!