Generation compensation for Off-take constraints. 4.9.1 Generation Compensation in offtake constraints due to Grid Unavailability: During the operation of the plant, PGVCL shall endeavor to ensure 95% of grid availability ina contract year, however, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the SPG. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against PGVCL:
Appears in 5 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement (Ppa)
Generation compensation for Off-take constraints. 4.9.1 Generation Compensation in offtake constraints due to Grid Unavailability: During the operation of the plant, PGVCL shall endeavor to ensure 95% of grid availability ina in a contract year, however. However, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the SPG. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against PGVCL:
Appears in 2 contracts
Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement (Ppa)
Generation compensation for Off-take constraints. 4.9.1 Generation Compensation in offtake constraints due to Grid Unavailability: During the operation of the plant, PGVCL UGVCL shall endeavor to ensure 95% of grid availability ina in a contract year, however. However, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the SPG. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against PGVCLUGVCL:
Appears in 1 contract
Samples: Power Purchase Agreement (Ppa)