Handing Over Procedure. 22.6.1 One year prior to the anticipated expiry of the Period, the "RWS" and the "DEVELOPER" shall meet and agree by mutual consensus on detailed procedures for the handing over of the Project and Project Facilities. The Parties shall meet to agree on such procedures as soon as possible and in any event within 15 days of either Party giving notice to the other Party requesting such meeting. At the time of such meeting, the "DEVELOPER" shall submit a detailed list of the structures, equipments, assets created by the "DEVELOPER" and to be handed over and the names of its representatives in charge of the transfer, and the "RWS" shall inform the "DEVELOPER" of the identity of its representatives in charge of the handing over procedure;