Increased Costs and/or Time. 4.4.1 If the Subcontractor fails to perform the reviews and comparisons required in Paragraphs 4.2 and 4.3, and as otherwise required by the Subcontract Documents, to the extent the Contractor is held liable to the Owner because of the Subcontractor's failure, the Subcontractor shall pay the costs and damages to the Contractor that would have been avoided if the Subcontractor had performed those obligations. 4.4.2 The Subcontractor may assert a Claim as provided in Article 6 if the Contractor's clarifications or instructions in response to requests for information are believed to require additional time or cost.
Appears in 3 contracts
Samples: Subcontract Agreement, Subcontract Agreement, Subcontract Agreement
Increased Costs and/or Time. 4.4.1 If the Subcontractor fails to perform the reviews and comparisons com- parisons required in Paragraphs 4.2 and 4.3, and as otherwise required re- quired by the Subcontract Documents, to the extent the Contractor is held liable to the Owner because of the Subcontractor's failure, the Subcontractor shall pay the costs and damages to the Contractor that would have been avoided if the Subcontractor had performed those obligations.
4.4.2 The Subcontractor may assert a Claim as provided in Article 6 if the Contractor's clarifications or instructions in response to requests re- quests for information are believed to require additional time or cost.
Appears in 1 contract
Samples: Subcontract Agreement
Increased Costs and/or Time. 4.4.1 The Subcontractor may assert a Claim as provided in Article 7 if the Contractor’s clarifications or instructions in response to requests for information are believed to require additional time or cost. If the Subcontractor fails to perform the reviews and comparisons required in Paragraphs 4.2 3.3 and 4.3, and as otherwise required by the Subcontract Documents3.4 above, to the extent the Contractor is held liable to the Owner because of the Subcontractor's ’s failure, the Subcontractor shall pay the costs and damages to the Contractor that would have been avoided if the Subcontractor had performed those obligations.
4.4.2 The Subcontractor may assert a Claim as provided in Article 6 if the Contractor's clarifications or instructions in response to requests for information are believed to require additional time or cost.
Appears in 1 contract
Samples: Subcontractor Agreement