Initial Breakdown and Periodical Payments. Each Application for Payment shall be submitted at least ten days before each payment falls due, and the Design-Builder shall, before the first application, shall submit to the Program Manager a Schedule of Values as required by Paragraph 4.3.1.2 above of the various parts of the work, including quantities, aggregating the total sum of the Contract, divided in the same manner set forth in the Application for Payment Form set forth in Exhibit K and so arranged and so itemized as to meet the approval of the Program Manager and, further, if requested, supported by such evidence as to its correctness as the Program Manager may direct.
Appears in 14 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract