Initial Decision. 2.1 An initial decision shall be required as a condition precedent to mediation of all Claims between the Owner and Design-Builder initiated prior to the date final payment is due, excluding those arising under Sections 10.3 and § 14.2.2 Procedure
Appears in 17 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Initial Decision. 2.1 An initial decision shall be required as a condition precedent to mediation of all Claims between the Owner and Design-Builder initiated prior to the date final payment is due, excluding those arising under Sections 10.3 and unless 45 days have passed after the Claim has been initiated with no decision having been rendered. Unless otherwise mutually agreed in writing, the Owner shall render the initial decision on Claims. § 14.2.2 Procedure
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Initial Decision. 2.1 An initial decision shall be required as a condition precedent to mediation of all Claims between the Owner Manager and Design-Builder initiated prior to the date final payment is due, excluding those arising under Sections 10.3 and § 14.2.2 Procedureand
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Initial Decision. 2.1 An initial decision shall be required as a condition precedent to mediation of all Claims between the Owner and Design-Builder initiated prior to the date final payment is due, excluding those arising under Sections 10.3 and § 14.2.2 Procedureand
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Initial Decision. 2.1 § 14.2.1 An initial decision shall be required as a condition precedent to mediation of all Claims between the Owner and Design-Builder initiated prior to the date final payment is due, excluding those arising under Sections 10.3 and § 14.2.2 Procedureand
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder