Inspection by Operator. (a) Subject to Clause 6.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure. (b) Any inspection by the Operator under Clause 6.3(a) shall be subject to (i) the Operator providing reasonable written notice to QR Network of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times; (ii) any such inspection being conducted in the presence of a representative of QR Network; and (iii) such other reasonable conditions as may be imposed by QR Network on such inspection including, but not limited to, compliance with QR Network’s Safeworking Procedures and Safety Standards; and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.
Appears in 2 contracts
Samples: Access Agreement, Operator Access Agreement
Inspection by Operator. (a) Subject to Clause 6.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
(b) Any inspection by the Operator under Clause 6.3(a) shall be subject to
(i) the Operator providing reasonable written notice to QR Network of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times;
(ii) any such inspection being conducted in the presence of a representative of QR NetworkQR; and
(iii) such other reasonable conditions as may be imposed by QR Network on such inspection including, but not limited to, compliance with QR NetworkQR’s Safeworking Procedures and Safety Standards; and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.
Appears in 1 contract
Samples: Operator Access Agreement
Inspection by Operator. (a) (a) Subject to Clause 6.3(b7.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
. (b) (b) Any inspection by the Operator under Clause 6.3(a7.3(a) shall be subject to:
(i) (i) the Operator providing reasonable written notice to QR Network of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times;
; (ii) (ii) any such inspection being conducted in the presence of a representative of QR Network; and
and (iii) (iii) such other reasonable conditions as may be imposed by QR Network on such inspection including, but not limited to, compliance with QR Network’s Safeworking Procedures and Safety Standards; , and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.
Appears in 1 contract
Samples: Train Operations Agreement
Inspection by Operator. (a) Subject to Clause 6.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure Network and circumstances surrounding the Infrastructure Network comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure Network and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
(b) Network. Any inspection by the Operator under Clause 6.3(a) shall be subject to:
(i) the Operator providing reasonable written notice to QR Network Queensland Rail of its requirement to inspect the Infrastructure Network and conducting that inspection at reasonable times;
(ii) any such inspection being conducted in the presence of a representative of QR NetworkQueensland Rail; and
(a) (b)
(iii) such other reasonable conditions as may be imposed by QR Network Queensland Rail on such inspection including, but not limited to, compliance with QR NetworkQueensland Rail’s Safeworking Procedures and Safety Standards; , and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.
Appears in 1 contract
Samples: Train Operations Agreement
Inspection by Operator. (a) Subject to Clause 6.3(b7.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
(b) Any inspection by the Operator under Clause 6.3(a7.3(a) shall be subject to:
(i) the Operator providing reasonable written notice to QR Network of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times;
(ii) any such inspection being conducted in the presence of a representative of QR Network; and
(iii) such other reasonable conditions as may be imposed by QR Network on such inspection including, but not limited to, compliance with QR Network’s Network‟s Safeworking Procedures and Safety Standards; , and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.
Appears in 1 contract
Samples: Train Operations Agreement
Inspection by Operator. (a) Subject to Clause 6.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
(b) Any inspection by the Operator under Clause 6.3(a) shall be subject to
(i) the Operator providing reasonable written notice to QR Network of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times;
(ii) any such inspection being conducted in the presence of a representative of QR Network; and
(iii) such other reasonable conditions as may be imposed by QR Network on such inspection including, but not limited to, compliance with QR Network’s Safeworking Procedures and Safety Standards; and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.;
Appears in 1 contract
Samples: Coal Access Agreement
Inspection by Operator. (a) Subject to Clause 6.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
(b) Any inspection by the Operator under Clause 6.3(a) shall be subject to
(i) the Operator providing reasonable written notice to QR Network Queensland Rail of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times;
(ii) any such inspection being conducted in the presence of a representative of QR NetworkQueensland Rail; and
(iii) such other reasonable conditions as may be imposed by QR Network Queensland Rail on such inspection including, but not limited to, compliance with QR NetworkQ ueensland Rail’s Safeworking Procedures and Safety Standards; and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.
Appears in 1 contract
Samples: Access Agreement
Inspection by Operator.
(a) Subject to Clause 6.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
(b) Any inspection by the Operator under Clause 6.3(a) shall be subject to:
(i) the Operator providing reasonable written notice to QR Network of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times;
(ii) any such inspection being conducted in the presence of a representative of QR Network; and
(iii) such other reasonable conditions as may be imposed by QR Network on such inspection including, but not limited to, compliance with QR Network’s Safeworking Procedures and Safety Standards; and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.
Appears in 1 contract
Samples: Access Agreement
Inspection by Operator. (a) (a) Subject to Clause 6.3(b7.3(b), the Operator may, prior to the initial commencement of Train Services, at its cost and risk, inspect the Infrastructure and circumstances surrounding the Infrastructure comprising the Nominated Network including, but not limited to, fencing and level crossing protection in order to satisfy itself as to the standard of the Infrastructure and assess the operational, environmental and safety risks associated with operation of Train Services on the Infrastructure.
. (b) (b) Any inspection by the Operator under Clause 6.3(a7.3(a) shall be subject to:
(i) (i) the Operator providing reasonable written notice to QR QRAurizon Network of its requirement to inspect the Infrastructure and conducting that inspection at reasonable times;
; (ii) (ii) any such inspection being conducted in the presence of a representative of QR QRAurizon Network; and
and (iii) (iii) such other reasonable conditions as may be imposed by QR QRAurizon Network on such inspection including, but not limited to, compliance with QR QRAurizon Network’s Safeworking Procedures and Safety Standards; , and shall be conducted in such a manner as to not cause any disruption to any Train Movements or to the undertaking of Maintenance Work or Enhancements.