Common use of Interconnection of Third Party Facilities to Customer System Clause in Contracts

Interconnection of Third Party Facilities to Customer System. 5.4.1 Customer will provide advance written notice to National Grid prior to the proposed interconnection to the Customer System of any: (1) new Generator ; (2) 10% increase or more in the capacity of an existing Generator connected to the Customer System ; or (3) peak load increases of 10% or greater over the peak load stated in Exhibit A. Such written notice shall be provided within 30 Calendar Days of Customer receiving an interconnection or service request or notice of a proposed increase in Generator capacity.

Appears in 4 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement