Issuance of Building Permits. The following permits will not be issued for a phase until the items addressed by each permit necessary to serve that phase are completed and accepted by the City. A. No building permit shall be issued until the public sanitary sewer and water systems are completed and accepted by the City. B. No building permits shall be issued until surface and storm water drainage systems are completed and accepted by the City. C. No building permits shall be issued until the rough grading plan has been submitted and accepted by the City. D. No building permit for a lot shall be issued until payment of the park Development fee, if applicable. E. No building permit shall be issued until the road base, curbs and gutters on the streets have been installed and preliminarily accepted by the City unless otherwise permitted by the City Engineer. F. No building permits shall be issued until the sanitary sewer system is televised and all repairs to the defects to the same are made, and the City is supplied a digital copy of the sanitary sewer system and all sewer lines are cleaned. G. Final acceptance of the improvements permitted shall not be given until all as- built plans have been submitted and approved by the City. H. No occupancy permits be issued until all private utilities have been installed and accepted by the City. I. No building permits shall be issued until removal of unwanted items, including buildings, have been completed. J. No occupancy permit shall be issued by the City for any lot until the first lift of asphalt has been installed on the street adjoining said lot.
Appears in 2 contracts
Samples: Developer's Agreement, Subdivision Developer's Agreement
Issuance of Building Permits. The following permits will not be issued for a phase until the items addressed by each permit necessary to serve that phase are completed and accepted by the City.
A. No building permit shall be issued until the public sanitary sewer and water systems are completed and accepted by the City.
B. No building permits shall be issued until surface and storm water drainage systems are completed and accepted by the City.
C. No building permits shall be issued until the rough grading plan has been submitted and accepted by the City.
D. No building permit for a lot shall be issued until payment of the park Development fee, if applicable.
E. No building permit shall be issued until the road base, curbs and gutters on the streets have been installed and preliminarily accepted by the City unless otherwise permitted by the City EngineerCity.
F. No building permits shall be issued until the sanitary sewer system is televised and all repairs to the defects to the same are made, and the City is supplied a digital copy of the sanitary sewer system and all sewer lines are cleaned.
G. Final acceptance of the improvements permitted shall not be given until all as- as-built plans have been submitted and approved by the City.
H. No occupancy permits be issued until all private utilities have been installed and accepted by the City.
I. No building permits shall be issued until removal of unwanted items, including buildings, have been completed.
J. No occupancy permit shall be issued by the City for any lot until the first lift of asphalt has been installed on the street adjoining said lot.
Appears in 1 contract
Samples: Developer's Agreement
Issuance of Building Permits. The following permits will not be issued for a phase until the items addressed by each permit necessary to serve that phase are completed and accepted by the City.
A. No building permit shall be issued until the public sanitary sewer and water systems are completed and accepted by the City.
B. No building permits shall be issued until surface and storm water drainage systems are completed and accepted by the City.
C. No building permits shall be issued until the rough grading plan and lot grading plan has been submitted and accepted by the City.
D. No building permit for a lot shall be issued until payment of the park Development fee, if applicable.
E. No building permit shall be issued until the road base, curbs and gutters on the streets have been installed and preliminarily accepted by the City unless otherwise permitted by the City Engineer.
F. No building permits shall be issued until the sanitary sewer system is televised and all repairs to the defects to the same are made, and the City is supplied a digital copy of the sanitary sewer system and all sewer lines are cleaned.
G. Final acceptance of the improvements permitted shall not be given until all as- built plans have been submitted and approved by the City.
H. No occupancy permits be issued until all private utilities have been installed and accepted by the City.
I. No building permits shall be issued until removal of unwanted items, including buildings, have been completed.
J. No occupancy permit shall be issued by the City for any lot until the first lift of asphalt has been installed on the street adjoining said lot.
Appears in 1 contract
Samples: Developer's Agreement
Issuance of Building Permits. The following permits will not be issued for a phase until the items addressed by each permit necessary to serve that phase are completed and accepted by the City.
A. No building permit shall be issued until the public sanitary sewer and water systems are completed and accepted by the City.
B. No building permits shall be issued until surface and storm water drainage systems are completed and accepted by the City.
C. No building permits shall be issued until the rough grading plan and lot grading plan has been submitted and accepted by the City.
D. No building permit for a lot shall be issued until payment of the park Development fee, if applicable.
E. No building permit shall be issued until the road base, curbs and gutters (except as allowed in Section I, A. 2.) on the streets have been installed and preliminarily accepted by the City unless otherwise permitted by the City Engineer.
F. No building permits shall be issued until the sanitary sewer system is televised and all repairs to the defects to the same are made, and the City is supplied a digital copy of the sanitary sewer system and all sewer lines are cleaned.
G. Final acceptance of the improvements permitted shall not be given until all as- built plans have been submitted and approved by the City.
H. No occupancy permits be issued until all private utilities have been installed and accepted by the City.
I. No building permits shall be issued until removal of unwanted items, including buildings, have been completed.
J. No occupancy permit shall be issued by the City for any lot until the first lift of asphalt has been installed on the street adjoining said lot.
Appears in 1 contract
Samples: Developer's Agreement
Issuance of Building Permits. The following permits will not be issued for a phase until the items addressed by each permit necessary to serve that phase are completed and accepted by the City.
A. No building permit shall be issued until the public sanitary sewer and water systems are completed and accepted by the City.
B. No building permits shall be issued until surface and storm water drainage systems are completed and accepted by the City.
C. No building permits shall be issued until the rough grading plan has been submitted and accepted by the City.
D. No building permit for a lot shall be issued until payment of the park Development fee, if applicable.
E. No building permit shall be issued until the road base, curbs and gutters on the streets have been installed and preliminarily accepted by the City unless otherwise permitted by the City EngineerCity.
F. No building permits shall be issued until the sanitary sewer system is televised and all repairs to the defects to the same are made, and the City is supplied a digital copy of the sanitary sewer system and all sewer lines are cleaned.
G. Final acceptance of the improvements permitted shall not be given until all as- built plans have been submitted and approved by the City.
H. No occupancy permits be issued until all private utilities have been installed and accepted by the City.
I. No building permits shall be issued until removal of unwanted items, including buildings, have been completed.
J. No occupancy permit shall be issued by the City for any lot until the first lift of asphalt has been installed on the street adjoining said lot.
Appears in 1 contract
Samples: Subdivision Developer’s Agreement
Issuance of Building Permits. The following permits will not be issued for a phase until the items addressed by each permit necessary to serve that phase are completed and accepted by the City.
A. No building permit shall be issued until the public sanitary sewer and water systems are completed and accepted by the City.
B. No building permits shall be issued until surface and storm water drainage systems are completed and accepted by the City.
C. No building permits shall be issued until the rough grading plan has been submitted and accepted by the City.
D. No building permit for a lot shall be issued until payment of the park Development fee, if applicable.
E. No building permit shall be issued until the road base, curbs and gutters on the streets have been installed and preliminarily accepted by the City unless otherwise permitted by the City EngineerCity.
F. No building permits shall be issued until the sanitary sewer system is televised and all repairs to the defects to the same are made, and the City is supplied a digital copy of the sanitary sewer system and all sewer lines are cleaned.
G. Final acceptance of the improvements permitted shall not be given until all as- built plans have been submitted and approved by the City.
H. No occupancy permits be issued until all private utilities have been installed and accepted by the City.
I. No building permits shall be issued until removal of unwanted items, including buildings, have been completed.
J. No occupancy permit shall be issued by the City for any lot until the first lift of asphalt has been installed on the street adjoining said lot.
Appears in 1 contract
Samples: Developer's Agreement