Items Excluded from the Cost of the Work. Any provisions in this Agreement to the contrary notwithstanding, Cost of Work shall NOT include the following items: 8.3.1 Salaries or other compensation of CMR’s personnel stationed at the CMR’s principal office or offices, except as may be specifically provided in Section 8.2.1 above, or as may be provided in UGC Article 11. 8.3.2 Expenses of the CMR’s principal office and other offices. 8.3.3 Overhead and general expenses, except as may be expressly included in Sections 8.2 above. 8.3.4 CMR’s capital expenses, including interest, on the CMR’s capital employed for the Work. 8.3.5 Except as provided in Section 8.1.6.2 of this Agreement, costs due to the negligence or failure of CMR, Subcontractors, or anyone directly or indirectly employed or engaged by any of them, to fulfill a specific responsibility under this Agreement. 8.3.6 Costs of acceleration of the Work arising as a result of delay caused by the negligence of CMR, or its Subcontractor or other persons over whom CMR or any Subcontractor exercises control or is legally responsible, including any and all overtime wages, unabsorbed home office overhead, or other consequential loss incurred by CMR. 8.3.7 Any and all costs not otherwise expressly authorized to be charged as a Cost of the Work herein, including, without limitation, any cost which would exceed the Guaranteed Maximum Price established by the GMP Amendment. 8.3.8 Premium costs/charges for or relating to subcontractor payment and performance bonds and/or subcontractor default insurance. 8.3.9 Any cost not specifically and expressly identified in Sections 8.1 to 8.2 above.
Appears in 4 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
Items Excluded from the Cost of the Work. Any provisions in this Agreement to the contrary notwithstanding, Cost of Work shall NOT include the following items:
8.3.1 : Salaries or other compensation of CMR’s personnel stationed at the CMR’s principal office or offices, except as may be specifically provided in Section 8.2.1 above, or as may be provided in UGC Article 11.
8.3.2 . Expenses of the CMR’s principal office and other offices.
8.3.3 . Overhead and general expenses, except as may be expressly included in Sections 8.2 above.
8.3.4 . CMR’s capital expenses, including interest, on the CMR’s capital employed for the Work.
8.3.5 . Except as provided in Section 8.1.6.2 of this Agreement, costs due to the negligence or failure of CMR, Subcontractors, or anyone directly or indirectly employed or engaged by any of them, to fulfill a specific responsibility under this Agreement.
8.3.6 . Costs of acceleration of the Work arising as a result of delay caused by the negligence of CMR, or its Subcontractor or other persons over whom CMR or any Subcontractor exercises control or is legally responsible, including any and all overtime wages, unabsorbed home office overhead, or other consequential loss incurred by CMR.
8.3.7 . Any and all costs not otherwise expressly authorized to be charged as a Cost of the Work herein, including, without limitation, any cost which would exceed the Guaranteed Maximum Price established by the GMP Amendment.
8.3.8 . Premium costs/charges for or relating to subcontractor payment and performance bonds and/or subcontractor default insurance.
8.3.9 . Any cost not specifically and expressly identified in Sections 8.1 to 8.2 above. Costs for services incurred during the Preconstruction Services Phase of the Project (these are paid as Preconstruction Services).