Late or non-payment. If a payment is not made by a party in accordance with clause 4.4 or clause 4.6 then the party required to make the payment must pay interest on the amount for the period from the date the payment is due until the date of payment calculated in accordance with clause 4.8.
Appears in 2 contracts
Samples: Connection Agreement, Connection Agreement
Late or non-payment. If a payment is not made by a party in accordance with clause 4.4 or clause 4.6 this agreement then the that party required to make the payment must pay interest on the amount for the period from the date the payment is due until the date of payment calculated in accordance with clause 4.816.6.
Appears in 1 contract
Late or non-payment. If a payment is not made by a party in accordance with clause 4.4 12.4 or clause 4.6 then 12.6 the party required to make the payment must pay interest on the amount for the period from the date the payment is due until the date of payment calculated in accordance with clause 4.812.8.
Appears in 1 contract
Samples: Network Operation Agreement
Late or non-payment. If a payment is not made by a party in accordance with clause 4.4 or clause 4.6 this agreement then the that party required to make the payment must pay interest on the amount for the period from the date the payment is due until the date of payment calculated in accordance with clause 4.810.5.
Appears in 1 contract
Samples: www.tasnetworks.com.au
Late or non-payment. If a party fails to make a payment is not made by a party in accordance with clause 4.4 or clause 4.6 X 7.3X then the that party required to make the payment must pay interest on the amount for the period from the date the payment is due until the date of payment calculated in accordance with clause 4.8.X7.7X.
Appears in 1 contract