Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.3. Owner's total liability for any changes under Article 4 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive: (a) The Contractor's direct labor, costs and labor burden associated with performance of the work, (b) The direct costs of any subcontractor, (c) The direct costs of any materials, including applicable sales taxes, (d) Rental costs of any rental equipment, (e) Ownership costs of any owned equipment, and (f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 10 contracts
Samples: Contract for Construction, Contract for Construction, Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 3.1 and 4.23.2, or any construction change directives under Article 4.33.3. OwnerCCPRC's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.3. Owner's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 3.1 and 4.23.2, or any construction change directives under Article 4.3this Article. Owner's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.3. OwnerCLARENDON COUNTY's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Design Build Construction Agreement
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.3. OwnerCCPRC's total liability for any changes under Article 4 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 10 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.33.2. Owner's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.3. OwnerCCPRC's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Design Build Construction Agreement
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.3. OwnerCCPRC's total liability for any changes under Article 4 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 3.1 and 4.23.2, or any construction change directives under Article 4.33.2. Owner's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 3.1 and 4.23.2, or any construction change directives under Article 4.33.3. OwnerCCPRC's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 10% of the change order cost.
Appears in 1 contract
Samples: Construction Contract
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 3.1 and 4.23.2, or any construction change directives under Article 4.33.3. OwnerCCPRC's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 1 0 % of the change order cost.
Appears in 1 contract
Samples: Construction Contract
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 3.1 and 4.23.2, or any construction change directives under Article 4.3. Owner's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 and 4.2, or any construction change directives under Article 4.3. OwnerCCPRC's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 10 % of the change order cost.
Appears in 1 contract
Samples: Design Build Agreement
Limits on Contract Adjustments. The following limitations shall apply to any change orders issued pursuant to Articles 4.1 3.1 and 4.23.2, or any construction change directives under Article 4.33.3. Owner's total liability for any changes under Article 4 3 shall not exceed the cumulative total of the following costs which are incurred in connection with the performance of a change order or change directive:
(a) The Contractor's direct labor, costs and labor burden associated with performance of the work,
(b) The direct costs of any subcontractor,
(c) The direct costs of any materials, including applicable sales taxes,
(d) Rental costs of any rental equipment,
(e) Ownership costs of any owned equipment, and
(f) Field and general overhead, direct profit, and profit above subcontractor cost shall be considered as an aggregate total and shall not exceed 15 % of the change order cost.
Appears in 1 contract
Samples: Contract for Construction