Common use of Liquidated Damages for Delay in Substantial Completion Clause in Contracts

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount and no/100 dollars) ($amount) per day as liquidated damages for each day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 Any sums due and payable under this Paragraph 7.3 by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s actions or inactions substantially caused the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount and no/100 dollars) pay Owner the sum of ---No-- Dollars ($amount0.00) per day as liquidated damages for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 . Any sums due and payable under this Paragraph 7.3 hereunder by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s 's actions or inactions substantially caused contributed to the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All Such liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s 's performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably unexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Design and Construction Agreement

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount and no/100 dollars) (pay Owner the sum of $amount) 500 per day as liquidated damages for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 . Any sums due and payable under this Paragraph 7.3 hereunder by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s actions or inactions substantially caused contributed to the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All Such liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably unexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Guaranteed Maximum Price Design and Construction Agreement

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount insertamount and no/100 dollars) dollars ($amount0) per day as liquidated damages for each day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 Any sums due and payable under this Paragraph 7.3 by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s actions or inactions substantially caused the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Design Build Agreement

Liquidated Damages for Delay in Substantial Completion. .1 If Design/Builder fails to achieve Substantial Completion by , as detailed in Outline Specification Section 00 01 20 “List of Schedules , the Design/Builder shall be assessed pay Owner the sum of (amount and no/100 dollars) ($amount$ ) per day as liquidated damages for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the Scheduled date set forth herein for Substantial Completion Date. .2 of the Work. Any sums due and payable under this Paragraph 7.3 hereunder by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s actions or inactions substantially caused contributed to the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All Such liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Design and Construction Agreement

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount pay Owner the sum of Two Thousand, Seven Hundred, and no/100 dollars) Twelve Dollars ($amount2,712) per day as liquidated damages for day)for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 . Any sums due and payable under this Paragraph 7.3 hereunder by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s 's actions or inactions substantially caused contributed to the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All Such liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s 's performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Design/Build Contract

Liquidated Damages for Delay in Substantial Completion. .1 If Design/Builder fails to achieve Substantial Completion by , as detailed in Outline Specification Section 00 01 20 “List of Schedules , the Design/Builder shall be assessed pay Owner the sum of (amount and no/100 dollars) ($amount$ ) per day as liquidated damages for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the Scheduled date set forth herein for Substantial Completion Date. .2 of the Work. Any sums due and payable under this Paragraph 7.3 hereunder by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s 's actions or inactions substantially caused contributed to the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All Such liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s 's performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Design and Construction Agreement

AutoNDA by SimpleDocs

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount and no/100 dollars) pay Owner the sum of FIVE HUNDRED DOLLARS ($amount500) per day as liquidated damages for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 . Any sums due and payable under this Paragraph 7.3 hereunder by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this AgreementContract. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s 's actions or inactions substantially caused contributed to the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All Such liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s 's performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Design/Build Contract

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount and no/100 dollars) pay Owner the sum of _ One Thousand Dollars ($amount_1,000_) per day as liquidated damages for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 . Any sums due and payable under this Paragraph 7.3 hereunder by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s 's actions or inactions substantially caused contributed to the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All Such liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s 's performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.

Appears in 1 contract

Samples: Design/Build Contract

Liquidated Damages for Delay in Substantial Completion. .1 Design/Builder shall be assessed (amount insertamount and no/100 dollars) dollars ($amount0) per day as liquidated damages for each day of unexcused delay in achieving Substantial Completion beyond the Scheduled Completion Date. .2 Any sums due and payable under this Paragraph 7.3 by Design/Builder shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by Owner, estimated at the time of executing this Agreement. Such liquidated damages shall apply regardless of whether Design/Builder has been terminated by Owner prior to Substantial Completion so long as Design/Builder’s actions or inactions substantially caused the delay; provided, however, that if Design/Builder is in substantial compliance with the project schedule at the time of termination, no liquidated damages will be assessed against Design/Builder. All liquidated damages shall be in addition to and not in preclusion of the recovery of actual damages resulting from other defects in Design/Builder’s performance hereunder for matters other than delays in Substantial Completion. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due to Design/Builder an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. Owner shall provide Design/Builder a ten (10) day notice of its intent to withhold liquidated damages and the amount of said liquidated damages to be withheld. If and when Design/Builder overcomes the delay in achieving Substantial Completion, or any part thereof, for which Owner has withheld payment, Owner shall promptly release to Design/Builder those funds withheld, but no longer applicable as liquidated damages.then

Appears in 1 contract

Samples: Design Build Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!