LOADING CRITERIA. Deviations sought by the bidder in respect of Payment terms, delivery period, Liquidated Damages (X.X.) shall be loaded on the bidder/s quoted prices during price evaluation by MDL. Among the equal bids, bidders with ISO 9000 series accreditation, over Non-ISO bidders, will be given preference. The loading criteria that will be adopted are detailed below & also as per Annexure-H. 21.1 It is desirable that the bidder accepts the Payment Terms indicated in clause 16 above. Varied payment terms quoted by bidders as compared to the terms stated in the Tender document shall be normalized by applying S.B.I. Prime Lending Rate (prevailing at the time of opening of Price bid) plus 2% p.a. rate of interest for the period at variation. (For Indigenous bidder) 21.2 For the additional time period sought by the bidder over the stipulated date of delivery as per Tender, 0.50% per completed week will be loaded to the quoted price. 21.3 Deviations sought in respect of Liquidated Damages (X X) Deviations sought in respect of rate per week and / or maximum ceiling in respect of liquidated damages shall be loaded to the quoted price. For e.g. The maximum ceiling towards liquidated damages speculated in the tender is 5% and the bidder seeks to limit it to, say 3.5% then the price quoted will be loaded by 1.5%. If the rate of X.X per week is 0.5% per week or part thereof as per tender and the bidder seeks it as, say, 0.4% per week or part thereof, the maximum ceiling on X X as per tender will first be equated to weeks (10 weeks in this case) and the rate proposed by the bidder i.e. 0.4% will be multiplied by the so equated maximum period (which works out to 4%) and the quoted price will be loaded accordingly by 1%. Delivery being the essence of the contract, it is desirable if the bidder/s adhere to the stipulated clause. 21.4 Deviations in respect of the period of Guarantee shall be loaded to the quoted price @ 0.25% per month or part thereof. This does not arise if the bidder quotes additional price for the differential period.
Appears in 2 contracts
Samples: Additional Service Level Agreement (Sla), Additional Service Level Agreement (Sla)
LOADING CRITERIA. Deviations sought by the bidder in respect of Payment terms, delivery period, Liquidated Damages (X.X.L.D.) shall be loaded on the bidderxxxxer/s quoted prices during price evaluation by MDL. Among the equal bids, bidders with ISO 9000 series accreditation, over Non-ISO bidders, will be given preference. The loading criteria that will be adopted are detailed below & also as per Annexure-H.
21.1 It is desirable that the bidder accepts the Payment Terms indicated in clause 16 above. Varied payment terms quoted by bidders as compared to the terms stated in the Tender document shall be normalized by applying S.B.I. Prime Lending Rate (prevailing at the time of opening of Price bid) plus 2% p.a. rate of interest for the period at variation. (For Indigenous bidder)
21.2 For the additional time period sought by the bidder over the stipulated date of delivery as per Tender, 0.50% per completed week will be loaded to the quoted price.
21.3 Deviations sought in respect of Liquidated Damages (X XL D) Deviations sought in respect resxxxt of rate per week and / or maximum ceiling in respect of liquidated damages shall be loaded to the quoted price. For e.g. The maximum ceiling towards liquidated damages speculated in the tender is 5% and the bidder seeks to limit it to, say 3.5% then the price quoted will be loaded by 1.5%. If the rate of X.X L.D per week is 0.5% per week or xx part thereof as per tender and the bidder seeks it as, say, 0.4% per week or part thereof, the maximum ceiling on X X L D as per tender will first be xx equated to weeks (10 weeks in this case) and the rate proposed by the bidder i.e. 0.4% will be multiplied by the so equated maximum period (which works out to 4%) and the quoted price will be loaded accordingly by 1%. Delivery being the essence of the contract, it is desirable if the bidder/s adhere to the stipulated clause.
21.4 Deviations in respect of the period of Guarantee shall be loaded to the quoted price @ 0.25% per month or part thereof. This does not arise if the bidder quotes additional price for the differential period.
Appears in 1 contract
LOADING CRITERIA. Deviations sought by the bidder in respect of Payment terms, delivery period, Liquidated Damages (X.X.L.D.) shall be loaded on the xxx bidder/s quoted prices during price evaluation by MDL. Among the equal bids, bidders with ISO 9000 series accreditation, over Non-ISO bidders, will be given preference. The loading criteria that will be adopted are detailed below & also as per Annexure-H.
21.1 22.1. It is desirable that the bidder accepts the Payment Terms indicated in clause 16 above. Varied payment terms quoted by bidders as compared to the terms stated in the Tender document shall be normalized by applying S.B.I. Prime Lending Rate (prevailing at the time of opening of Price bid) plus 2% p.a. rate of interest for the period at variation. (For Indigenous bidder)
21.2 22.2. For the additional time period sought by the bidder over the stipulated date of delivery as per Tender, 0.50% per completed week will be loaded to the quoted price.
21.3 22.3. Deviations sought in respect of Liquidated Damages (X XL D) Deviations sought in respect of rate per week and / or maximum ceiling in respect of liquidated damages shall be loaded to the quoted price. For e.g. The maximum ceiling towards liquidated damages speculated in the tender is 5% and the bidder seeks to limit it to, say 3.5% then the price quoted will be loaded by 1.5%. If the rate of X.X L.D per week is 0.5% per week or part thereof as per tender and the bidder seeks it as, say, 0.4% per week or part thereof, the maximum ceiling on X X L D as per tender will first be equated to weeks (10 weeks in this case) and the rate proposed by the bidder i.e. 0.4% will be multiplied by the so equated maximum period (which works out to 4%) and the quoted price will be loaded accordingly by 1%. Delivery being the essence of the contract, it is desirable if the bidder/s adhere to the stipulated clause.
21.4 22.4. Deviations in respect of the period of Guarantee shall be loaded to the quoted price @ 0.25% per month or part thereof. This does not arise if the bidder quotes additional price for the differential period.
Appears in 1 contract
LOADING CRITERIA. Deviations sought by the bidder in respect of Payment terms, delivery period, Liquidated Damages (X.X.) shall be loaded on the bidder/s quoted prices during price evaluation by MDL. Among the equal bids, bidders with ISO 9000 series accreditation, over Non-ISO bidders, will be given preference. The loading criteria that will be adopted are detailed below & also as per Annexure-H.L.
21.1 21.1. It is desirable that the bidder accepts the Payment Terms indicated in clause 16 15 above. Varied payment terms quoted by bidders as compared to the terms stated in the Tender document shall be normalized by applying S.B.I. Prime Lending Rate (prevailing at the time of opening of Price bid) plus 2% p.a. rate of interest for the period at variation. (For Indigenous bidder)
21.2 21.2. For the additional time period sought by the bidder over the stipulated date of delivery as per Tender, 0.50% per completed week will be loaded to the quoted price.
21.3 21.3. Deviations sought in respect of Liquidated Damages (X X) Deviations sought in respect of rate per week and / or maximum ceiling in respect of liquidated damages shall be loaded to the quoted price. For e.g. The maximum ceiling towards liquidated damages speculated in the tender is 5% and the bidder seeks to limit it to, say 3.5% then the price quoted will be loaded by 1.5%. If the rate of X.X per week is 0.5% per week or part thereof as per tender and the bidder seeks it as, say, 0.4% per week or part thereof, the maximum ceiling on X X as per tender will first be equated to weeks (10 weeks in this case) and the rate proposed by the bidder i.e. 0.4% will be multiplied by the so equated maximum period (which works out to 4%) and the quoted price will be loaded accordingly by 1%. Delivery being the essence of the contract, it is desirable if the bidder/s adhere to the stipulated clause.
21.4 21.4. Deviations in respect of the period of Guarantee shall be loaded to the quoted price @ 0.25% per month or part thereof. This does not arise if the bidder quotes additional price for the differential period.
Appears in 1 contract
Samples: Rate Contract for Services
LOADING CRITERIA. Deviations sought by the bidder in respect of Payment terms, delivery period, Liquidated Damages (X.X.) shall be loaded on the bidder/s quoted prices during price evaluation by MDL. Among the equal bids, bidders with ISO 9000 series accreditation, over Non-ISO bidders, will be given preference. The loading criteria that will be adopted are detailed below & also as per Annexure-H.
21.1 21.1. It is desirable that the bidder accepts the Payment Terms indicated in clause 16 above. Varied payment terms quoted by bidders as compared to the terms stated in the Tender document shall be normalized by applying S.B.I. Prime Lending Rate (prevailing at the time of opening of Price bid) plus 2% p.a. rate of interest for the period at variation. (For Indigenous bidder)
21.2 21.2. For the additional time period sought by the bidder over the stipulated date of delivery as per Tender, 0.50% per completed week will be loaded to the quoted price.
21.3 21.3. Deviations sought in respect of Liquidated Damages (X XL D) Deviations sought in respect of rate per week and / or maximum ceiling in respect of liquidated damages shall be loaded to the quoted price. For e.g. The maximum ceiling towards liquidated damages speculated in the tender is 5% and the bidder seeks to limit it to, say 3.5% then the price quoted will be loaded by 1.5%. If the rate of X.X L.D per week is 0.5% per week or part thereof as per tender and the bidder seeks it as, say, 0.4% per week or part thereof, the maximum ceiling on X X L D as per tender will first be equated to weeks (10 weeks in this case) and the rate proposed by the bidder i.e. 0.4% will be multiplied by the so equated maximum period (which works out to 4%) and the quoted price will be loaded accordingly by 1%. Delivery being the essence of the contract, it is desirable if the bidder/s adhere to the stipulated clause.
21.4 21.4. Deviations in respect of the period of Guarantee shall be loaded to the quoted price @ 0.25% per month or part thereof. This does not arise if the bidder quotes additional price for the differential period.
Appears in 1 contract